Activity Symbol Activity Description Predecessors Duration

A Create project layout -


B Obtain necessary -
permits and approvals
C Develop a detailed A
renovation plans and
specifications
D Purchase new B
materials
E Remove existing C, D
finishes and materials
F Address any structural E
issues or repairs
G Prepare the site for F
construction
H Framing and rough-in G
I Execute carpentry and H
finishes to the walls
J Bathroom renovation I
K Kitchen renovation I
L Installation of flooring I
and filling in other
areas
M Fixtures installation in J
kitchen
N Install new cabinets K
and counterparts in
kitchen
O Fixtures installation in L
other areas
P Conduct fire chuchu M, N, O

J M
A C
E F G K N P

B D H I
L O