The Mark

AJK Engineers (Pvt.) Ltd.


ANCHOR DETAILS LAYER 1
Sr. Anchor Drilling Depth Primary Cement Secondary Cement Stressing Stressing
No. No. Date (ft) Grout on bags Grout on bags Due date date
1 1B-2B 25-Feb-2024 70.75 27-Feb-2024 6 28-Feb-2024 1.5 13-Mar-2024
2 3B-4B 25-Feb-2024 70.75 27-Feb-2024 7 28-Feb-2024 1.5 13-Mar-2024
3 5B-6B 23-Feb-2024 70.75 27-Feb-2024 6 28-Feb-2024 1 13-Mar-2024
4 7B-8B 23-Feb-2024 70.75 27-Feb-2024 6 28-Feb-2024 1.5 13-Mar-2024
5 9B-10B 25-Feb-2024 70.75 27-Feb-2024 6 28-Feb-2024 4 13-Mar-2024
6 11B-12B 25-Feb-2024 70.75 27-Feb-2024 6 28-Feb-2024 1 13-Mar-2024
7 13B-14B 25-Feb-2024 70.75 27-Feb-2024 6 28-Feb-2024 2 13-Mar-2024
8 15B-16B 25-Feb-2024 70.75 27-Feb-2024 6 28-Feb-2024 1.5 13-Mar-2024
9 17B-18B 25-Feb-2024 70.75 27-Feb-2024 7 28-Feb-2024 1 13-Mar-2024
10 19B-20B 25-Feb-2024 70.75 27-Feb-2024 7 28-Feb-2024 1 13-Mar-2024
11 21B-22B 25-Feb-2024 70.75 27-Feb-2024 9 28-Feb-2024 1 13-Mar-2024
12 3A-4A 24-Feb-2024 70.75 27-Feb-2024 7 28-Feb-2024 1.5 13-Mar-2024
13 5A-6A 24-Feb-2024 70.75 27-Feb-2024 7 28-Feb-2024 1 13-Mar-2024
14 7A-8A 24-Feb-2024 70.75 27-Feb-2024 11 28-Feb-2024 1 13-Mar-2024
15 9A-10A 24-Feb-2024 70.75 27-Feb-2024 8 28-Feb-2024 2 13-Mar-2024
16 11A-12A 26-Feb-2024 70.75 27-Feb-2024 7 28-Feb-2024 1.5 13-Mar-2024
17 13A-14A 26-Feb-2024 70.75 27-Feb-2024 7 28-Feb-2024 1 13-Mar-2024
18 15A-16A 26-Feb-2024 70.75 27-Feb-2024 7 28-Feb-2024 1.5 13-Mar-2024
The Mark
AJK Engineers (Pvt.) Ltd.
ANCHOR DETAILS LAYER 1
Sr. Anchor Drilling Depth Primary Cement Secondary Cement Stressing Stressing
No. No. Date (ft) Grout on bags Grout on bags Due date date
19 17A-18A 27-Feb-2024 70.75 27-Feb-2024 7 28-Feb-2024 1.5 13-Mar-2024
20 19A-20A 27-Feb-2024 70.75 27-Feb-2024 7 28-Feb-2024 1.5 13-Mar-2024
21 2B-3B 1-Mar-2024 70.75 3-Mar-2024 7 4-Mar-2024 1.5 18-Mar-2024
22 4B-5B 1-Mar-2024 70.75 3-Mar-2024 7 4-Mar-2024 1 18-Mar-2024
23 6B-7B 1-Mar-2024 70.75 3-Mar-2024 7 4-Mar-2024 0.5 18-Mar-2024
24 8B-9B 29-Feb-2024 70.75 3-Mar-2024 8 4-Mar-2024 0.5 18-Mar-2024
25 10B-11B 29-Feb-2024 70.75 3-Mar-2024 8 4-Mar-2024 0.5 18-Mar-2024
26 12B-13B 29-Feb-2024 70.75 3-Mar-2024 8 4-Mar-2024 0.5 18-Mar-2024
27 14B-15B 29-Feb-2024 70.75 3-Mar-2024 6 4-Mar-2024 0.5 18-Mar-2024
28 16B-17 29-Feb-2024 70.75 3-Mar-2024 6 4-Mar-2024 1 18-Mar-2024
29 18B-19B 29-Feb-2024 70.75 3-Mar-2024 7 4-Mar-2024 1 18-Mar-2024
30 20B-21B 28-Feb-2024 70.75 3-Mar-2024 6 4-Mar-2024 2 18-Mar-2024
31 22B-23B 28-Feb-2024 70.75 3-Mar-2024 7 4-Mar-2024 0.5 18-Mar-2024
32 6A-7A 2-Mar-2024 70.75 3-Mar-2024 7 4-Mar-2024 1 18-Mar-2024
33 8A-9A 2-Mar-2024 70.75 3-Mar-2024 6 4-Mar-2024 2.5 18-Mar-2024
34 10A-11A 2-Mar-2024 70.75 3-Mar-2024 8 4-Mar-2024 1.5 18-Mar-2024
35 12A-13A 2-Mar-2024 70.75 3-Mar-2024 8 4-Mar-2024 1 18-Mar-2024
36 14A-15A 2-Mar-2024 70.75 3-Mar-2024 8 4-Mar-2024 1.5 18-Mar-2024
The Mark
AJK Engineers (Pvt.) Ltd.
ANCHOR DETAILS LAYER 1
Sr. Anchor Drilling Depth Primary Cement Secondary Cement Stressing Stressing
No. No. Date (ft) Grout on bags Grout on bags Due date date
37 16A-17A 3-Mar-2024 70.75 3-Mar-2024 8 4-Mar-2024 1 18-Mar-2024

38 18A-19A 3-Mar-2024 70.75 3-Mar-2024 7 4-Mar-2024 1 18-Mar-2024

39 1A-2A 5-Mar-2024 70.75 7-Mar-2024 8 8-Mar-2024 0.5 22-Mar-2024

40 2A-3A 4-Mar-2024 70.75 7-Mar-2024 6 8-Mar-2024 0.5 22-Mar-2024

41 1A-1B 6-Mar-2024 70.75 7-Mar-2024 10 8-Mar-2024 0.5 22-Mar-2024

42 4A-5A 4-Mar-2024 70.75 7-Mar-2024 10 8-Mar-2024 1 22-Mar-2024

43 20A-21A 5-Mar-2024 70.75 7-Mar-2024 9 8-Mar-2024 1 22-Mar-2024

44 23B-24B 5-Mar-2024 70.75 7-Mar-2024 9 8-Mar-2024 1 22-Mar-2024

45 24B-25B 5-Mar-2024 70.75 7-Mar-2024 6 8-Mar-2024 2 22-Mar-2024

46 25B-26B 6-Mar-2024 70.75 7-Mar-2024 6 8-Mar-2024 1.5 22-Mar-2024

47

48

Total cement Total cement


Total Drilling 3254.5 333 56.5 Total Cement 403.5