Module Submodule Day Poc Pre- Start Date Finish Date

requisite
activity
1 General
Requirements
SM01 Permits 3 Jan 2, 2024 Jan 5, 2024
SM02 Mobilization, 0.5 SM01 Jan 6, 2024 Jan 6, 2024
Demolition
SM03 Temporary Storage 150 SM02 Jan 6, 2024 June 4, 2024
SM04 Temporary 150 SM03 Jan 6, 2024 June 4, 2024
Electricity & Water
SM05 Temporary Fence 150 SM04 Jan 6, 2024 June 4, 2024
SM06 Site Clearing and 1 SM05 Jan 7, 2024 Jan 7, 2024
Grubbing
SM07 Batter board and 1 SM06 Jan 8, 2024 Jan 8, 2024
laying out
2 Earthworks
SM08 Structure 6.00 - March 12, 2024 March 19, 2024
Excavation
(Common Soil)
SM09 Embankment from 6.00 SM08 March 12, 2024 March 19, 2024
Structure
Excavation
SM10 Embankment from 6.00 SM08 March 12, 2024 March 19, 2024
Common Borrow
SM11 Gravel Fill 5.00 SM08 March 20, 2024 March 25, 2024
4 FOOTING
SM12 RSB 2.00 SM11 March 26, 2024 March 28, 2024
SM13 Concreting 1.00 SM12 March 29, 2024 March 29, 2024
5 WALL FOOTING
SM014 RSB 2.00 SM8 March 30, 2024 March 31, 2024
SM15 Concreting 1.00 SM14 April 1, 2024 April 1, 2024
6 COLUMN (FDN -
GF)
SM16 Formworks 1.00 SM17 April 2, 2024 April 2, 2024
SM17 RSB 5.00 SM27 April 3, 2024 April 9, 2024
SM18 Concreting 1.00 SM16 April 2, 2024 April 2, 2024
7 FOOTING TIE
BEAM
SM19 Formworks 1.00 SM20 April 8, 2024 April 8, 2024
SM20 RSB 9.00 SM27 March 30, 2024 April 8, 2024
SM21 Concreting 1.00 SM19 April 9, 2024 April 9, 2024
8 FLOOR BEAM
SM22 Formworks 1.00 SM23 April 19, 2024 April 19, 2024
SM23 RSB 10.00 SM21 April 9, 2024 April 19, 2024
SM24 Concreting 1.00 SM22 April 20, 2024 April 20, 2024
9 MASONRY (FDN -
GF)
SM25 RSB 4.00 SM15 March 26, 2024 March 30, 2024
SM26 CHB Layering 3.00 SM25 March 30, 2024 April 1, 2024
SM27 CHB Layering 4.00 SM25 March 30, 2024 April 2, 2024
10 COLUMN (GF-SF)
SM28 Formworks 1.00 SM29 May 4, 2024 May 4, 2024
SM29 RSB 12.00 SM24 April 20, 2024 May 4, 2024
SM30 Concreting 1.00 SM28 May 5, 2024 May 5, 2024
11 MASONRY (GF -
SF)
SM31 RSB 1.00 SM30 May 6, 2024 May 6, 2024
SM32 CHB Layering 12.00 SM31 May 6, 2024 May 17, 2024
12 SLAB ON FILL
SM33 RSB 8.00 SM37 May 14, 2024 May 21, 2024
SM34 Concreting 1.00 SM38 May 22, 2024 May 22, 2024
13 STAIRS
SM35 Formworks 1.00 SM36 May 13, 2024 May 13, 2024
SM36 RSB 9.00 SM30 May 5, 2024 May 13, 2024
SM37 Concreting 1.00 SM35 May 14, 2024 May 14, 2024
SM38 Handrail and 1.00 SM37 May 15, 2024 May 15, 2024
railings
14 2ND FLOOR
BEAM
SM39 Formworks 1.00 SM40 May 30, 2024 May 30, 2024
SM40 RSB 13.00 SM32 May 17, 2024 May 30, 2024
SM41 Concreting 1.00 SM39 May 31, 2024 May 31, 2024
15 COLUMN (SF-RF)
SM42 Formworks 1.00 SM43 May 30, 2024 May 30, 2024
SM43 RSB 13.00 SM29 May 17,2024 May 30, 2024
SM44 Concreting 1.00 SM42 May 31, 2024 May 31, 2024
16 MASONRY (SF-
RF)
SM45 RSB 1.00 SM50 June 14, 2024 June 14, 2024
SM46 CHB Layering 7.00 SM45 June 14, 2024 June 21, 2024
17 MASONRY (SF-
RF)
SM47 RSB 1.00 SM50 June 14, 2024 June 14, 2024
SM48 CHB Layering 13.00 SM47 June 14, 2024 June 27, 2024
18 Suspended Slab
SM49 RSB 14.00 SM44 May 31, 2024 June 13, 2024
SM50 Concreting 1.00 SM49 June 14, 2024 June 14, 2024
19 ROOF BEAM
SM51 Formworks 1.00 SM51 July 10, 2024 July 10, 2024
SM52 RSB 13.00 SM44 June 27, 2024 July 10, 2024
SM53 Concreting 1.00 SM51 July 11, 2024 July 11, 2024
20 Roofing Works
SM54 Steel Truss 1.00 SM52 July 11, 2024 July 11, 2024
fabrication
SM55 Steel Truss 8.00 SM54 July 11, 2024 July 11, 2024
Installation
SM56 Plates Installation 1.00 SM55 July 11, 2024 July 11, 2024
SM57 Purlins Installation 3.00 SM56 July 11, 2024 July 13, 2024
SM58 Roofing 4.00 SM57 July 13, 2024 July 16, 2024
SM59 Gutter 1.00 SM58 July 16, 2024 July 16, 2024
21 Plastering
SM60 Two face wall 8.00 SM48 July 14,2024 July 21, 2024
22 Doors and
Windows
SM61 Doors Installation 1.00 SM48 June 27, 2024 June 27, 2024
SM62 Window Installation 5.00 SM48 June 27, 2024 July 1, 2024
23 Electrical Works
SM63 Conduit, Boxes, 12.00 SM48 June 27, 2024 July 8, 2024
and Fittings
(Conduit
works, Conduit
Rough in)
SM64 Wires and Wiring 18.00 SM48 June 27, 2024 July 14,2024
Devices
SM65 Panelboard 1.00 SM48 June 27, 2024 June 27, 2024
SM66 Lighting Fixture and 13.00 SM48 June 27, 2024 July 9, 2024
Lamps
SM67 Airconditioning 1.00 SM48 June 27, 2024 June 27, 2024
Units, Exhaust
Fans, Orbit Fan
24 Ceiling
SM68 Ceiling Installation 7.00 SM453 July 11, 2024 July 17, 2024
25 Plumbing
SM69 Sewer line 13.00 SM08 March 18, 2024 March 30, 2024
SM70 Plumbing Fixtures 12.00 SM72 March 31, 2024 April 11, 2024
SM71 Cold Waterline 12.00 SM72 March 31, 2024 April 11, 2024
Works
SM72 Septic Vault Pipe 1.00 SM08 March 18, 2024 March 18, 2024
SM73 Septic vault 13.00 SM08 March 18, 2024 March 31, 2024
(concrete, CHB)
SM74 Catch Basin 1.00 SM08 March 18, 2024 March 18, 2024
Concrete
26 Tiling Works
SM75 Glazed Tiles 8.00 SM50 June 14, 2024 June 23, 2024
SM76 Unglazed Tiles 6.00 SM50 June 14, 2024 June 21, 2024
27 Painting
SM77 Woods 9.00 SM61 June 27, 2024 July 5, 2024
SM78 Masonry, Concrete 6.00 SM48 July 21, 2024 July 26, 2024