You are on page 1of 3

WORK BREAKDOWN STRUCTURE (WBS)

Pre-
Module Submodule Day Poc requisite Start Date Finish Date
activity
1 General
Requirements
SM01 Permits 3 August 5, 2024 August 8, 2024
SM02 Mobilization, 0.5 SM01 August 9, 2024 August 9, 2024
Demolition
SM03 Temporary Field 150 SM02 August 9, 2024 November 3, 2024
Office and temporary
Storage
SM04 Temporary 150 SM03 August 9, 2024 November 3, 2024
Electricity & Water
SM05 Temporary Fence 150 SM04 August 9, 2024 November 3, 2024
SM06 Site Clearing and 1 SM05 August 10, 2024 August 10, 2024
Grubbing
SM07 Batter board and 1 SM06 August 11, 2024 August 11, 2024
Laying out
2 Earthworks
SM08 Structure Excavation 16.00 - August 12, 2024 August 19, 2024
(Common Soil)
SM09 Embankment from 6.00 SM08 August 12, 2024 August 19, 2024
Structure Excavation
SM10 Embankment from 6.00 SM08 August 12, 2024 August 19, 2024
Common Borrow
SM11 Gravel Fill 5.00 SM08 August 20, 2024 August 25, 2024
4 FOOTING
SM12 RSB 2.00 SM11 August 26, 2024 August 28, 2024
SM13 Concreting 1.00 SM12 August 29, 2024 August 29, 2024
5 WALL FOOTING
SM014 RSB 2.00 SM8 August 30, 2024 August 31, 2024
SM15 Concreting 1.00 SM14 September 1, 2024 September 1, 2024
6 COLUMN (FDN -
GF)
SM16 Formworks 1.00 SM17 September 2, 2024 September 2, 2024
SM17 RSB 5.00 SM27 September 3, 2024 September 9, 2024
SM18 Concreting 1.00 SM16 September 2, 2024 September 2, 2024
7 FOOTING TIE
BEAM
SM19 Formworks 1.00 SM20 September 8, 2024 September 8, 2024
SM20 RSB 9.00 SM27 August 30, 2024 September 8, 2024
SM21 Concreting 1.00 SM19 September 9, 2024 September 9, 2024
8 FLOOR BEAM
SM22 Formworks 1.00 SM23 September 19, September 19, 2024
2024
SM23 RSB 10.00 SM21 September 9, 2024 September 19, 2024
SM24 Concreting 1.00 SM22 September 20, September 20, 2024
2024
9 MASONRY (FDN -
GF)
SM25 RSB 4.00 SM15 August 26, 2024 August 30, 2024
SM26 CHB Layering 3.00 SM25 August 30, 2024 September 1, 2024
SM27 CHB Layering 4.00 SM25 August 30, 2024 September 2, 2024
10 COLUMN (GF-SF)
SM28 Formworks 1.00 SM29 October 4, 2024 October 4, 2024
SM29 RSB 12.00 SM24 September 20, October 4, 2024
2024
SM30 Concreting 1.00 SM28 October 5, 2024 October 5, 2024
11 MASONRY (GF -
SF)
SM31 RSB 1.00 SM30 October 6, 2024 October 6, 2024
SM32 CHB Layering 12.00 SM31 October 6, 2024 October 17, 2024
12 SLAB ON FILL
SM33 RSB 8.00 SM37 October 14, 2024 October 21, 2024
SM34 Concreting 1.00 SM38 October 22, 2024 October 22, 2024
13 STAIRS
SM35 Formworks 1.00 SM36 October 13, 2024 October 13, 2024
SM36 RSB 9.00 SM30 October 5, 2024 October 13, 2024
SM37 Concreting 1.00 SM35 October 14, 2024 October 14, 2024
SM38 Handrail and railings 1.00 SM37 October 15, 2024 October 15, 2024
14 2ND FLOOR
BEAM
SM39 Formworks 1.00 SM40 October 30, 2024 October 30, 2024
SM40 RSB 13.00 SM32 October 17, 2024 October 30, 2024
SM41 Concreting 1.00 SM39 October 31, 2024 October 31, 2024
15 COLUMN (SF-RF)
SM42 Formworks 1.00 SM43 October 30, 2024 October 30, 2024
SM43 RSB 13.00 SM29 October 17,2024 October 30, 2024
SM44 Concreting 1.00 SM42 October 31, 2024 October 31, 2024
16 MASONRY (SF-
RF)
SM45 RSB 1.00 SM50 November 14, 2024 November 14, 2024
SM46 CHB Layering 7.00 SM45 November 14, 2024 November 21, 2024
17 MASONRY (SF-
RF)
SM47 RSB 1.00 SM50 November 14, 2024 November 14, 2024
SM48 CHB Layering 13.00 SM47 November 14, 2024 November 27, 2024
18 Suspended Slab
SM49 RSB 14.00 SM44 October 31, 2024 November 13, 2024
SM50 Concreting 1.00 SM49 November 14, 2024 November 14, 2024
19 ROOF BEAM
SM51 Formworks 1.00 SM51 December 10, 2024 December 10, 2024
SM52 RSB 13.00 SM44 November 27, 2024 December 10, 2024
SM53 Concreting 1.00 SM51 December 11, 2024 December 11, 2024
20 Roofing Works
SM54 Steel Truss 1.00 SM52 December 11, 2024 December 11, 2024
fabrication
SM55 Steel Truss 8.00 SM54 December 11, 2024 December 11, 2024
Installation
SM56 Plates Installation 1.00 SM55 December 11, 2024 December 11, 2024
SM57 Purlins Installation 3.00 SM56 December 11, 2024 December 13, 2024
SM58 Roofing 4.00 SM57 December 13, 2024 December 16, 2024
SM59 Gutter 1.00 SM58 December 16, 2024 December 16, 2024
21 Plastering
SM60 Two face walls 8.00 SM48 December 14,2024 December 21, 2024
22 Doors and Windows
SM61 Doors Installation 1.00 SM48 November 27, 2024 November 27, 2024
SM62 Window Installation 5.00 SM48 November 27, 2024 December 1, 2024
23 Electrical Works
SM63 Conduit, Boxes, and 12.00 SM48 November 27, 2024 December 8, 2024
Fittings (Conduit
Works, Conduit
Rough in)
SM64 Wires and Wiring 18.00 SM48 November 27, 2024 December 14,2024
Devices
SM65 Panelboard 1.00 SM48 November 27, 2024 November 27, 2024
SM66 Lighting Fixture and 13.00 SM48 November 27, 2024 December 9, 2024
Lamps
SM67 Airconditioning 1.00 SM48 November 27, 2024 November 27, 2024
Units, Exhaust Fans,
Orbit Fan
24 Ceiling
SM68 Ceiling Installation 7.00 SM453 December 11, 2024 December 17, 2024
25 Plumbing
SM69 Sewer line 13.00 SM08 August 18, 2024 August 30, 2024
SM70 Plumbing Fixtures 12.00 SM72 August 31, 2024 September 11, 2024
SM71 Cold Waterline 12.00 SM72 August 31, 2024 September 11, 2024
Works
SM72 Septic Vault Pipe 1.00 SM08 August 18, 2024 August 18, 2024
SM73 Septic vault (concrete 13.00 SM08 August 18, 2024 August 31, 2024
, CHB)
SM74 Catch Basin Concrete 1.00 SM08 August 18, 2024 August 18, 2024
26 Tiling Works
SM75 Glazed Tiles 8.00 SM50 November 14, 2024 November 23, 2024
SM76 Unglazed Tiles 6.00 SM50 November 14, 2024 November 21, 2024
27 Painting
SM77 Masonry, Concrete 9.00 SM61 November 27, 2024 December 5, 2024

You might also like