8KVA:
SYMINIFI
16KVA:
SYMSTRFI
Site Preparation
Structural/Environmental Requirements
The weight of the SymmetraTM rests on four 3.8cm Install in a temperature controlled, clean, dry, and pro-
(1.5") diameter leveling feet. Make sure the installa- tected indoor area that is free of conductive contami-
tion site is structurally sound. nants. The atmosphere must be free of dust and cor-
Note: Weights shown are for empty frames and frames rosive fumes, and with adequate airflow.
fully loaded with modules.
Environmental Conditions:
D i m e n si on s n Relative Humidity: 0 to 95%, non-condensing.
S y m m et r aTM Wei g h t
C om pon e n t kg (lb)
W x D x H cm n Temperature: 0°C to 40°C (32°F to 104°F).
(inc hes) n Elevation: 0m to 3,048m (0ft to 10,000ft).
SYMINIFI 82kg n Electro-Static Discharge (ESD) Susceptibility:
(No Modules) (180lb) 61 x 71 x 86.4 System components are capable of withstanding
(24" x 28" x 34" ) “through air” electrostatic discharges up to an am-
SYMINIFI 155kg
plitude of +/-15kV and “direct discharge” elec-
(With Modules) (340lb)
trostatic discharges up to an amplitude of +/-8kV
SYMSTRFI 155kg without failure, abnormal operation, or degrada-
(No Modules) (340lb) 61 x 71 x 122 tion in performance. ESD test methods conform
SYMSTRFI 343kg (24" x 28" x 48" ) to IEC 801-2.
(With Modules) (755lb)
SY X R 4 145kg 61 x 71 x 43 BTU Output
(With Modules) (318lb) (24" x 28" x 17" )
Refer to the table for BTU output of a fully loaded
S Y X R 12 423kg 61 x 71 x 122
(With Modules) (930lb) (24" x 28" x 48" )
SymmetraTM . The BTU output is significantly higher
while the batteries are charging. Under normal oper-
SYBATT 28kg 22.9 x 50.8 x 15.2 ating conditions, battery recharge periods are rela-
(Battery Module) (60lb) (9" x 20" x 6" ) tively infrequent.
SY PM 16kg 25.4 x 50.8 x 15.2
(Power Module) (35lb) (10" x 20" x 6" )
B T U/H r
B T U/H r ( ba t t e r i e s
Space Considerations F r am e
S i ze
( ba t t e r i e s
fully
c h ar g i n g , f u l l
f r a m e c a p a c i t y,
Allow 30.5cm (12") of clearance behind the frame c h ar g ed ) N +1 m od u l e
for adequate airflow, and 122cm (48") of clearance c on f i g u r a t i on )
in the front of the Symmetra TM to access the
PowerView interface and to install power and battery SYMINIFI 2,321 7,578
modules.
SYMSTRFI 4,642 13,456
Storage of Modules
The battery modules must be temporarily stored until
the frame is permanently installed. To preserve bat-
tery life, always store batteries in a cool, dry place.
Note: Installing battery modules in a SymmetraTM that
is not powered will discharge the batteries and could
damage them permanently. Do not install battery
modules into the SymmetraTM frame until the system
is connected to input power.
Wiring Preparation
n All power and control wiring must be in- n Single phase power is distributed to load equip-
stalled by a qualified electrician and must ment via hardwired connections and by plugging
comply with applicable local and country the load equipment into the convenience power
codes. panel at the rear of the frame.
n Use flexible metal conduit for ease of ser- n With the PowerView user interface, the Power
vice and maintenance of the system. Array can be configured to deliver either 220V,
230V, or 240V.
Single Phase
Output Power to
Load Equipment
220V,
230V,
or 240V
Output Input
L1 Wire Ground
Output
Neutral Input
L1
Output
Ground
Input
Neutral
Output Wiring
(Single Phase) Input Wiring (Single Phase)
Site Preparation:
q 1. Determined where the SymmetraTM Power Array will be installed.
q 2. Floor is structurally sound to support a fully loaded SymmetraTM frame and additional XR frames.
(See table - page 3.)
q 3. Installation site meets minimum environmental requirements.
q 4. Installation site cooling system can support the additional heat output of the SymmetraTM.
Electrical Preparation:
q 1. Required input voltage is available.
q 2. Determined all output wiring configurations to be installed.
q 3. Scheduled an electrician to install the SymmetraTM Power Array.
q 4. Delivered a copy of this document to the electrician. (Important.)
q 5. Made electrician aware of the electrician’s checklist in chapter 4 of the User’s Manual.