Work Order

Date: 2023-08-29
Prepared By: Priya Ramdatt and Selina Fraser
Approved By:

Description of operation: Cement Movement Operation from JF Wharf/ Rock Hard Bond to Alya Campsite Linden or beyond (KM) No. of bags at the bond
776. LGEX Trucks and Sub contractors (Shan Singh, Micheal Jerry) will be used to transport cement.

Truck Drivers Payment/ Truck Rental Porters Payment


No. of Days No. Trips Bridge Crossing Fuel Per Day
$5000 Per
($,4000)
Porter
LGEX Sub Con. LGEX ($12,000) Sub Con. ($85,000)
Day 1 3 3 $ 36,000.00 $ - $ 15,000.00 $ 24,000.00
Day 2 6 3 2 $ 36,000.00 $ 170,000.00 $ 15,000.00 $ 24,000.00
Day 3 6 3 2 $ 36,000.00 $ 170,000.00 $ 15,000.00 $ 24,000.00
Day 4 6 3 2 $ 36,000.00 $ 170,000.00 $ 15,000.00 $ 24,000.00
4 trips with a full
Day 5 6 3 2 $ 36,000.00 $ 170,000.00 $ 15,000.00 $ 24,000.00 tank of fuel i.e.
33/4 = 14 *
Day 6 6 3 2 $ 36,000.00 $ 170,000.00 $ 15,000.00 $ 24,000.00 $85,000 This is
Day 7 6 3 2 $ 36,000.00 $ 170,000.00 $ 15,000.00 $ 24,000.00 only for LGEX
trucks
Day 8 5 3 2 $ 36,000.00 $ 170,000.00 $ 15,000.00 $ 24,000.00
Day 9 5 3 2 $ 36,000.00 $ 170,000.00 $ 15,000.00 $ 24,000.00
Day 10 5 3 2 $ 36,000.00 $ 170,000.00 $ 15,000.00 $ 24,000.00
Day 11 5 3 2 $ 36,000.00 $ 170,000.00 $ 15,000.00 $ 24,000.00

Total 59 33 20 $ 396,000.00 $ 1,700,000.00 $ 165,000.00 $ 264,000.00 $ 701,250.00

Additional Expense - 1 Spare tire $ 70,000.00

Estimated cost for this operation is: $ 3,296,250.00

Duration of Operation: Operation completed by:


30th August, 2023 to the 12th September, 2023

Completion Notes