1
UPDATE MINUTES OF MEETING WEEK 10
MINUTES OF MEETING
Topic Weekly Meeting Survey Services Pomalaa Week 10
Meeting No 003/CARS-PTVI-MOM/08/III/2024
- RAHADIAN K WIJAYA
PTVI Participants - ANDI BASO
Toolbox meeting ditambahkan dengan kesiapan temen temen bekerja pada saat bulan ramadhan. Fisik, psikis, mental dan jam tidur. Agus Week 11 Close
Tim carsurin belum ada yang punya account vale. Perlu request ke Tim IT nya Vale Agus Week 11 Open
No Nama Posisi 04-Mar 05-Mar 06-Mar 07-Mar 08-Mar 09-Mar 10-Mar TOTAL MANPOWER 12
1 Agus Salim PJO ON SITE ON SITE ON SITE ON SITE ON SITE ON SITE ON SITE 11
2 Zainal Abidin Senior Surveyor ON SITE ON SITE ON SITE ON SITE ON SITE ON SITE OFF SITE 1
3 Leo Mardi Surveyor ON SITE ON SITE ON SITE ON SITE ON SITE ON SITE
O
50,00%
0,00%
3
TNA ANALYSIS
INCIDENT WORKING NEAR OR Standart Operasional LICENSE LICENSE PILOT
No. Name Position BN GIP HAZID PPE BFA BSWP SSIP FIRST AID L1 JSA SDT BSS RA BASIC FE SWP SLOPE STABILITY POP POM JUT
INVESTIGATION IN WATER Disposal SAFETY DRONE
1 Aghust Salim PJO C043714 21/2/2024 21/2/2024 21/2/2024 21/2/2024 21/2/2024 21/2/2024 27/02/2024 18/05/2020 24/03/2021 08/08/2024 03/07/2024
2 Zainal Abidin Senior Surveyor C043716 21/2/2024 21/2/2024 21/2/2024 21/2/2024 21/2/2024 21/2/2024 27/02/2024 31/12/2025 31/01/2024
3 Leo Mardi Tanjung Survey Drafter C043715 21/2/2024 21/2/2024 21/2/2024 21/2/2024 21/2/2024 21/2/2024 27/02/2024
4 Riyan Ciptadi Surveyor C037573 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 27/02/2024
Muh. Jaya
5 Assistant Surveyor C033850 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 27/02/2024
Kurniawan
Idpan Pausari
6 Helper C037729 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 27/02/2024
Ramadan
7 Maliki Farid Drone Pilot 21/02/2024 21/02/2024 21/02/2024 21/02/2024 21/02/2024 21/02/2024 16/02/2024
C043717
8 Baharuddin Observer Drone C040190 01-May-23 01-May-23 01-May-23 01-May-23 01-May-23 01-May-23 27/02/2024
9 Muh. Mas'ud Umar Safety Coordinator C037675 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 23/02/2024 22/02/2024 27/02/2024
10 Muh. Rivaldi Driver 1 C037671 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22 07-Aug-22
12 Salsabila Admin Officer C039261 14-Jul-23 14-Jul-23 14-Jul-23 14-Jul-23 14-Jul-23 14-Jul-23
TOTAL TNA 12 12 12 12 12 12 0 1 0 0 1 0 0 8 0 0 0 2 1 0 2 2
PPE
SDT
RA
SSIP
JUT
BSWP
BASIC FE
GIP
HAZID
SWP
BSS
FIRST AID L1
JSA
POP
POM
SLOPE STABILITY
WORKING NEAR OR IN
INVESTIGATION
Standart Operasional
LICENSE SAFETY
BSS 12 JUT 10
INCIDENT
LICENSE PILOT
RA 11 10
DRONE
Disposal
WATER
4
MAN HOURS
Man Hours Report
Total Days 2 6 6 6
Total Manpower 12 12 12 12
Weekly Man Hours 192 576 576 576
Maximal Man Hours 576 576 576 576 Man Hours Week to Date March
2500
Total Man Hours 192 768 1344 1920
Day Lost 0 0 0 0 2000
Lost Time Injuri FR 0 0 0 0
1500
Saverity Rate (SR) 0 0 0 0
1000
500
0
Week 7 Week 8 Week 9 Week 10
Weekly Man Hours 192 576 576 576
Maximal Man Hours 576 576 576 576
Total Man Hours 192 768 1344 1920
5
SAFETY REPORT
DESCRIPTION Maret
INCIDENT W9 W10
N1 - -
N2 - -
N3 - -
N4 - -
N5 - -
TOTAL - -
HSE
100% 100%
PERFORMANCE
6
TOOLBOX MEETING
Total
No Date Theme Presenter Weekly
Participants
1 04/03/2024 Kebersihan Agust Salim 11
2 05/03/2024 Kewajiban untuk penggunaan LOTO M Yamyar Ashari 11
3 06/03/2024 Pengendalian Resiko Bahaya Leo Mardi 10
Week 10
4 07/03/2024 Kelangkapan APD dan alat kerja Andi Baso Muftiali 10
5 08/03/2024 Menjaga kesehatan jiwa raga Baharudin 10
6 09/03/2024 Kesiapan kerja di bulan puasa Ryan Ciptadi 10
Absensi Toolbox Meeting Absensi Toolbox Meeting Absensi Toolbox Meeting Absensi Toolbox Meeting
Absensi Toolbox Meeting Absensi Toolbox Meeting
: 4/3/2024 : 5/3/2024 : 8/3/2024 : 9/3/2024
: 6/3/2024 : 7/3/2024
7
REVIEW NO PLAN ISSUE DATE DUE DATE STATUS Closing Date
SAFETY PROGRAM
Pembuatan sign master point
WEEK 10 1 4 Maret 2024 15 maret 2024 Open
dan emergency exit
5 Pembuatan safety campaign 4 Maret 2024 11 Maret 2024 Continue 9 Maret 2024
Sosialisasi mengenai
6 4 Maret 2024 11 Maret 2024 Close 9 Maret 2024
kewaspadaan di Bulan Puasa
9
PROGRAM 5S
10
EQUIPMENT
Percentage CALIBRATION
NO EQUIPMENT QTY S/N Status Receiving Date Utilization Date CONDITION REMARK
Availability DATE NEXT
1 DJI - Matrice 350 RTK Universal (EU) 1 1581F6GKB238E00400T0 Waiting Permit 16 February 2024 100% Good *Waiting SIDOPI Certified
2 D-RTK 2 High Precision GNSS Mobile Station 1 359BKB200101HD RFU 16 February 2024 8 Maret 2024 100% Good
3 WingtraOne GEN II RX1RII PPK 1 5268 Waiting Permit 16 February 2024 100% Good *Waiting SIDOPI Certified
4 Total Station Leica TS10 3 1 RFU 2 Maret 2024 8 Maret 2024 100% Good
5 GPS Base 1 4902089 RFU 2 Maret 2024 8 Maret 2024 100% Good
6 GPS Rover 1 4902100 RFU 2 Maret 2024 8 Maret 2024 100% Good
7 Pole TS 1 RFU 2 Maret 2024 8 Maret 2024 100% Good
8 Pole GPS RFU 2 Maret 2024 8 Maret 2024 100% Good
9 Tripod TS 2 RFU 2 Maret 2024 8 Maret 2024 100% Good
10 Tripod GPS 2 RFU 2 Maret 2024 8 Maret 2024 100% Good
6VP011786
11 GPS Handheld 2 RFU 16 February 2024 8 Maret 2024 100% Good
6VP010320
12 Trimble Catalyst 1 6340100167 RFU 03 Maret 2024 8 Maret 2024 100% Good
13 Pole Catalyst 2 RFU 03 Maret 2024 8 Maret 2024 100% Good
14 Laptop 4 RFU 16 February 2024 8 Maret 2024 100% Good Laptop Administration
15 HP 6 RFU 16 Maret 2024 8 Maret 2024 100% Good
16 Printer 1 RFU 16 February 2024 8 Maret 2024 100% Good
17 Laptop High Spesification 2 RFU 28 February 2024 8 Maret 2024 100% Good Laptop Data Processing
11
SOFTWARE
12
DATA ALAT PELINDUNG DIRI
Seragam Kerja
Safety Shoes
Safety Glass
Bee Net
Helmet
Gloves
Vest
NO NAMA POSISI KETERANGAN
13
LIST SARANA
No. Nama Kendaraan No. Kendaraan No. CT Expired Komisioning No Mesin No Chassis KET
1 Mitsubishi Pajero Sport B 1522 LKU Progress Progress 4N15UKJ6187 MK2KSWPNUPJ002133 Pendaftaran CT
2 Mitsubishi Pajero Sport B 1523 LKU Progress Progress Pendaftaran CT
Note : Untuk Mobil dengan no kendaraan B 1522 LKU dan B1523 LKU sudah update perpanjangan STNK dengan Surat Keterangan Pengganti STNK sementara
yang berlaku sampai 9 Juni 2024. kedua dokumen STNK sementara sudah disubmit Kembali untuk pengajuan CT dan menunggu feedback.
14
Komsumi BBM/Fuel B 1522
FUEL LKU, Week
CONSUMPTION 10
RECAPITULATION
B 1522 LKU
Date Hours KM Total Driver Before After PENGGUNAAN BBM SARANA B 1522 LKU
22/02/24
22/02/24
26/02/24
27/02/24
04/03/24
27 februari 2024 16,44 785 30 MALIKI FARID M
15
Komsumi BBM/Fuel B 1523 LKU, Week 10
Date Hours KM Total Driver Before After PENGGUNAAN BBM SARANA B 1523 LKU
21/02/24
27/02/24
01/03/24
03/03/24
06/03/24
03 March 2024 11,14 1360 12 MUH RIVALDI
Summary Fuel Consumption
Total kilometer 458 km
Total liter 90 liter
06 March 2024 14,36 1449 42 MUH RIVALDI
Total Hours 14 hari
Total consumption per-day 6 liter/hari
Total km per-day 33 km/hari
Note: Pengisian BBM dilakukan di SPBU terdekat
(BBM Dexlite)
16
Weekly Activity WK 10
Survey Stake-out
Pending; 3
Stockpiles Volume - DOS
Stockpiles Volume
Monitoring Deformation
Maps
As-built Survey
0 1 2 3 4 5 Job Issue :
- Pending job berkaitan dengan job stakeout Land Acquisition yang menunggu list
ACTIVITY koordinat bidang tanah yang fix dari Ibu Mega.
- Job On Going Berkaitan dengan Job stakeout area MHR01 yang masih dalam
proses pengerjaan.
18
Weekly Activity WK 10
JOB SUPPORT
Department Count
7%
6%
Mine Plan, Geotech and Hidro
Mine Plan, Geotech and Hidro Pomalaa 10
Pomalaa
Mine Infrast Maintenance and Development 3
20%
Mine Infrast Maintenance and Survey Service 1
Development
Project IGP Pomalaa 1
Survey Service
67%
19
MONTH TO DATE ACTIVITY – MARCH 2024
Topographic Survey
JOB ACHIEVEMENT MONTH TO DATE
Inspection - Joint Survey MARCH
Survey Stake-out On Going; 1
Stockpiles Volume
Monitoring Deformation
19
Maps
As-built Survey
0 1 2 3 4 5 6 7 8 9 10
20
PETA LOKASI WEEKLY ACTIVITY WEEK 10
JNP
22%
23,14
WAS
54% hektar
SJS
24%
21
DOKUMENTASI KEGIATAN
22
Perintah Kerja Harian
23
Logbook Data Lapangan
24
Logbook Data Processing
25
DOKUMENTASI PROCESSING
26
DOKUMENTASI PROCESSING
27
DOKUMENTASI INVENTARIS
28
DOKUMENTASI TANGGAL 4 MARET 2023
Pengukuran BM Sementara area PT SJS
29
DOKUMENTASI TANGGAL 5 MARET 2023
Pengecekan alat dengan pihak Vale, Stakeout Land Acquisition dan Aerial Foto Early Work
30
DOKUMENTASI TANGGAL 6 MARET 2023
Pengecekan Kesehatan, Stakeout Land Acquisition dan Aerial Photo Early Work
31
DOKUMENTASI TANGGAL 7 MARET 2023
Stakeout Land Acquisition dan Processing Data Aerial Photo Early Work
32
DOKUMENTASI TANGGAL 8 MARET 2023
Pengecekan serta utilisasi alat Leica GS18 dan Processing Data serta submit data Aerial Photo Early Work
33
DOKUMENTASI TANGGAL 9 MARET 2023
Pengukuran BM Sementara area RER 03 PT SJS
34
Thank You
35