You are on page 1of 6

CyberBullying Detection Prevention & Counseling-System

CSE-327 PROJECT
Members: Farhan Ishrak Tahmid - 2031458642, Farhana Akbar - 2012482642, Md Nafiur Rahman - 2014154642
Project Start: Fri, 7/28/2023
Today: Thu, 11/2/2023
Display Week: 1 Jul 24, 2023 Jul 31, 2023 Aug 7, 2023 Aug 14, 2023 Aug 21, 2023 Aug 28, 2023 Sep 4, 2023 Sep 11, 2023 Sep 18, 2023
24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
TASK NAME AND ASSIGNED TASK START
END DATE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DESCRIPTION TO PROGRESS DATE

Project Timeline
All Group
Project Idea 100% 07/20/23 07/28/23
Members
All Group
Project Proposal 100% 07/28/23 08/09/23
Members
Farhan
User Story Template Ishrak 100% 08/10/23 08/14/23
Tahmid
All Group
User Case Diagram 100% 08/18/23 08/23/23
Members
Md Nafiur
User Interface Design 100% 09/25/23 09/01/23
Rahman
Farhan
Git Ishrak 100% 09/26/23 09/28/23
Tahmid
Farhana
Jira 90% 09/25/23 09/28/23
Akbar
Farhana
Activity Diagram 100% 10/01/23 10/04/23
Akbar
Farhan
Class Diagram Ishrak 100% 10/03/23 10/06/23
Tahmid
Cocomo Effort Farhana
100% 10/18/23 10/21/23
Estimation Akbar
Md Nafiur
Budgeting 100% 10/21/23 10/26/23
Rahman
Farhan
Two Time Line Charts Ishrak 100% 10/29/23 11/01/23
Tahmid
CyberBullying Detection Prevention & Counseling-System
CSE-327 PROJECT
Members: Farhan Ishrak Tahmid - 2031458642, Farhana Akbar - 2012482642, Md Nafiur Rahman - 2014154642
Project Start: Fri, 7/28/2023
Today: Thu, 11/2/2023
Display Week: 2 Jul 31, 2023 Aug 7, 2023 Aug 14, 2023 Aug 21, 2023 Aug 28, 2023 Sep 4, 2023 Sep 11, 2023 Sep 18, 2023 Sep 25, 2023
31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1
TASK NAME AND ASSIGNED TASK START
END DATE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DESCRIPTION TO PROGRESS DATE

Project Timeline
All Group
Project Idea 100% 07/20/23 07/28/23
Members
All Group
Project Proposal 100% 07/28/23 08/09/23
Members
Farhan
User Story Template Ishrak 100% 08/10/23 08/14/23
Tahmid
All Group
User Case Diagram 100% 08/18/23 08/23/23
Members
Md Nafiur
User Interface Design 100% 09/25/23 09/01/23
Rahman
Farhan
Git Ishrak 100% 09/26/23 09/28/23
Tahmid
Farhana
Jira 90% 09/25/23 09/28/23
Akbar
Farhana
Activity Diagram 100% 10/01/23 10/04/23
Akbar
Farhan
Class Diagram Ishrak 100% 10/03/23 10/06/23
Tahmid
Cocomo Effort Farhana
100% 10/18/23 10/21/23
Estimation Akbar
Md Nafiur
Budgeting 100% 10/21/23 10/26/23
Rahman
Farhan
Two Time Line Charts Ishrak 100% 10/29/23 11/01/23
Tahmid
CyberBullying Detection Prevention & Counseling-System
CSE-327 PROJECT
Members: Farhan Ishrak Tahmid - 2031458642, Farhana Akbar - 2012482642, Md Nafiur Rahman - 2014154642
Project Start: Fri, 7/28/2023
Today: Thu, 11/2/2023
Display Week: 3 Aug 7, 2023 Aug 14, 2023 Aug 21, 2023 Aug 28, 2023 Sep 4, 2023 Sep 11, 2023 Sep 18, 2023 Sep 25, 2023 Oct 2, 2023
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8
TASK NAME AND ASSIGNED TASK START
END DATE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DESCRIPTION TO PROGRESS DATE

Project Timeline
All Group
Project Idea 100% 07/20/23 07/28/23
Members
All Group
Project Proposal 100% 07/28/23 08/09/23
Members
Farhan
User Story Template Ishrak 100% 08/10/23 08/14/23
Tahmid
All Group
User Case Diagram 100% 08/18/23 08/23/23
Members
Md Nafiur
User Interface Design 100% 09/25/23 09/01/23
Rahman
Farhan
Git Ishrak 100% 09/26/23 09/28/23
Tahmid
Farhana
Jira 90% 09/25/23 09/28/23
Akbar
Farhana
Activity Diagram 100% 10/01/23 10/04/23
Akbar
Farhan
Class Diagram Ishrak 100% 10/03/23 10/06/23
Tahmid
Cocomo Effort Farhana
100% 10/18/23 10/21/23
Estimation Akbar
Md Nafiur
Budgeting 100% 10/21/23 10/26/23
Rahman
Farhan
Two Time Line Charts Ishrak 100% 10/29/23 11/01/23
Tahmid
CyberBullying Detection Prevention & Counseling-System
CSE-327 PROJECT
Members: Farhan Ishrak Tahmid - 2031458642, Farhana Akbar - 2012482642, Md Nafiur Rahman - 2014154642
Project Start: Fri, 7/28/2023
Today: Thu, 11/2/2023
Display Week: 4 Aug 14, 2023 Aug 21, 2023 Aug 28, 2023 Sep 4, 2023 Sep 11, 2023 Sep 18, 2023 Sep 25, 2023 Oct 2, 2023 Oct 9, 2023
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
TASK NAME AND ASSIGNED TASK START
END DATE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DESCRIPTION TO PROGRESS DATE

Project Timeline
All Group
Project Idea 100% 07/20/23 07/28/23
Members
All Group
Project Proposal 100% 07/28/23 08/09/23
Members
Farhan
User Story Template Ishrak 100% 08/10/23 08/14/23
Tahmid
All Group
User Case Diagram 100% 08/18/23 08/23/23
Members
Md Nafiur
User Interface Design 100% 09/25/23 09/01/23
Rahman
Farhan
Git Ishrak 100% 09/26/23 09/28/23
Tahmid
Farhana
Jira 90% 09/25/23 09/28/23
Akbar
Farhana
Activity Diagram 100% 10/01/23 10/04/23
Akbar
Farhan
Class Diagram Ishrak 100% 10/03/23 10/06/23
Tahmid
Cocomo Effort Farhana
100% 10/18/23 10/21/23
Estimation Akbar
Md Nafiur
Budgeting 100% 10/21/23 10/26/23
Rahman
Farhan
Two Time Line Charts Ishrak 100% 10/29/23 11/01/23
Tahmid
CyberBullying Detection Prevention & Counseling-System
CSE-327 PROJECT
Members: Farhan Ishrak Tahmid - 2031458642, Farhana Akbar - 2012482642, Md Nafiur Rahman - 2014154642
Project Start: Fri, 7/28/2023
Today: Thu, 11/2/2023
Display Week: 6 Aug 28, 2023 Sep 4, 2023 Sep 11, 2023 Sep 18, 2023 Sep 25, 2023 Oct 2, 2023 Oct 9, 2023 Oct 16, 2023 Oct 23, 2023
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
TASK NAME AND ASSIGNED TASK START
END DATE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DESCRIPTION TO PROGRESS DATE

Project Timeline
All Group
Project Idea 100% 07/20/23 07/28/23
Members
All Group
Project Proposal 100% 07/28/23 08/09/23
Members
Farhan
User Story Template Ishrak 100% 08/10/23 08/14/23
Tahmid
All Group
User Case Diagram 100% 08/18/23 08/23/23
Members
Md Nafiur
User Interface Design 100% 09/25/23 09/01/23
Rahman
Farhan
Git Ishrak 100% 09/26/23 09/28/23
Tahmid
Farhana
Jira 90% 09/25/23 09/28/23
Akbar
Farhana
Activity Diagram 100% 10/01/23 10/04/23
Akbar
Farhan
Class Diagram Ishrak 100% 10/03/23 10/06/23
Tahmid
Cocomo Effort Farhana
100% 10/18/23 10/21/23
Estimation Akbar
Md Nafiur
Budgeting 100% 10/21/23 10/26/23
Rahman
Farhan
Two Time Line Charts Ishrak 100% 10/29/23 11/01/23
Tahmid
CyberBullying Detection Prevention & Counseling-System
CSE-327 PROJECT
Members: Farhan Ishrak Tahmid - 2031458642, Farhana Akbar - 2012482642, Md Nafiur Rahman - 2014154642
Project Start: Fri, 7/28/2023
Today: Thu, 11/2/2023
Display Week: 7 Sep 4, 2023 Sep 11, 2023 Sep 18, 2023 Sep 25, 2023 Oct 2, 2023 Oct 9, 2023 Oct 16, 2023 Oct 23, 2023 Oct 30, 2023
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5
TASK NAME AND ASSIGNED TASK START
END DATE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DESCRIPTION TO PROGRESS DATE

Project Timeline
All Group
Project Idea 100% 07/20/23 07/28/23
Members
All Group
Project Proposal 100% 07/28/23 08/09/23
Members
Farhan
User Story Template Ishrak 100% 08/10/23 08/14/23
Tahmid
All Group
User Case Diagram 100% 08/18/23 08/23/23
Members
Md Nafiur
User Interface Design 100% 09/25/23 09/01/23
Rahman
Farhan
Git Ishrak 100% 09/26/23 09/28/23
Tahmid
Farhana
Jira 90% 09/25/23 09/28/23
Akbar
Farhana
Activity Diagram 100% 10/01/23 10/04/23
Akbar
Farhan
Class Diagram Ishrak 100% 10/03/23 10/06/23
Tahmid
Cocomo Effort Farhana
100% 10/18/23 10/21/23
Estimation Akbar
Md Nafiur
Budgeting 100% 10/21/23 10/26/23
Rahman
Farhan
Two Time Line Charts Ishrak 100% 10/29/23 11/01/23
Tahmid