Design Comparison of Wain River Bridge on New Capital City Toll Road Section
3A Karangjoang - KKT Kariangau
CITATIONS READS
0 9
3 authors, including:
SEE PROFILE
All content following this page was uploaded by Andrew Nugraha Standyarto on 20 October 2023.
ABSTRACT
To distribute country development and as a centralization of government, Indonesia will move its capital city
from the crowded Jakarta in Java Island to New Capital City (IKN) of Nusantara in East Kalimantan. To ensure the
connectivity and accessibility between existing city of Balikpapan to Nusantara, several sections of toll roads are built
from 2022 - 2024, including Toll Road of Section 3A that connects Karangjoang to Container Terminal of Kariangau.
There are many structures that will be built along the trace such as pile slab, box culvert, underpass, overpass and the
913 m long bridge that crosses 3 segments of Wain River on STA 18+664. From initial DED, the main span of bridge
only uses 50 m PCI Girder, but from more thorough survey and agreement with Ministry of Transportation, it’s agreed
that from the 5 m designed clearance is then changed to 10.5 m to accommodate local company’s passing tugboats
and pontons. Bridge design on the passed 3 main spans of river is then conducted on 2 alternatives, 66 m Steel Box
Girder (SBG) and 60.8 m Bulb Tee / Prestressed Concrete T (PCT) Girder. Both designs are compared based on
method, cost and duration. Both bridges will use launching gantry for erection with 250 billion IDR cost in 114 days
just for SBG main span while Bulb Tee with cost of 178.5 billion IDR in 102 days. From the analysis done, the SBG
design is more costly by 40.22% and time consuming by 11.76% to be implemented. Therefore, Bulb Tee Girder is
applied for Wain River Bridge main spans.
Keywords: New Capital City, Toll Road, Bulb Tee, Steel Box Girder, Launching Gantry
1. INTRODUCTION
Construction distribution, centralization of government and following Government Regulation, Indonesia will
move the capital city from the crowded Jakarta in Java Island to New Capital City (IKN) of Nusantara in East
Kalimantan. To ensure the connectivity, accessibility, goods mobility and travel time of 30 minutes between existing
city of Balikpapan to the new capital city of Nusantara, several sections of toll roads are built from 2022 - 2024,
Karangjoang – Kariangau – Tempadung – Balang Island - IKN. Toll Road of Section 3A specifically connects
Karangjoang to Container Terminal of Kariangau with 13.4 km length. IKN Toll Road section 3A is shown on Figure
1 as follow:
Figure 4. Long Section and Plan View of Typical Girder Erection with Launcher (Izza et al., 2019)
3. MATERIALS AND METHODS
Materials and Methods to conduct the study of Wain River Bridge is shown on the flowchart as follow on Figure 5:
4. RESULTS
To ensure best design is selected in IKN Toll road, comparison is done on 3 significant aspects that are method of
erection, duration and cost. Due to vertical clearance change from 5 m to 10.4 m, DED structure such as embankments
are modified to Slab on Pile and also bridge to maintain the height and accommodate soft soil layers on swamp area
in Wain River. The bridges are separated as 18 spans on side A (north side of trace) and 19 spans on side B (south
side of toll trace). The design of Wain Bridge River uses various spans of standard bridges of 60ish m main spans
(PCT and SBG) highlighted in the red box and 40 – 40.5 m PCI Girder with all 19 spans of Wain River Bridge are
shown as follow on Figure 6:
IKN Balikpapan
Side A
Side B
Figure 6. Plan View of Wain River Standard Bridge (DED Review, 2022)
Results of conducting 3 types of analysis to determine which design is better are below:
4.1 Design and Method of Work Analysis
To accommodate the passing boats under the bridge, the longest spans on the river will be compared between PCT and
SBG design. The 6 main spans are P5-P6, P10-P11, P14-P15 on Balikpapan direction and P5-P6, P11-P12, P15-P16
on IKN direction. Designs are modeled using Midas Civil software with appropriate loadings based on the standard.
PCT girder weight is 220 ton, SBG weight is 213 ton. PCI girder weight is 96 ton with 300 ton lifting capacity of
LG and 430 ton of weight. Both designs will use launching gantry for erection with slightly different steps for each.
Design comparisons are shown below:
a. Bulb Tee (PCT)
Bulb Tee girder with length of 60.8 m is chosen as the main span for crossing the Wain river with PCI girder ranging
from 40 m to 45 m are used for the approach span before connected to the Slab on Pile. Long section, cross section
and Bulb Tee girder detail are shown as follow on Figure 7:
IKN Balikpapan
SIDE A
SIDE B
Figure 7. (a) Long Section (Balikpapan and IKN Direction) and (b) Cross Section of Wain River Bridge with Bulb
Tee Main Span (Project Data, 2023)
The erection of all girders are done with a set of Launching Gantry for each direction to optimize time of girder
feeding and avoid disturbance to mangrove area on the ground.
Same with Bulb Tee and other PIC girder spans, erection of all SBG and all precast concrete girders are done with a
set of Launching Gantry due to the crossing river of Wain.
Schedules for main span girder erection using standard bridges design are show as follow on Table 1:
Table 1. Schedule of Wain River SBG Bridge (Author Data, 2022)
Duration (Day)
No Work Sequence
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38
Bulb Tee (PCT) Main Span
P5 - P6 Side A (7 Girders)
1 Launcher Setting from P4-P5
2 PCT Segment Mobilization & Setting 2 2 2 1
3 Strand Installation, Setting & Grouting
4 PCT Erection 2 2 3
P5 - P6 Side B (7 Girders)
5 Launcher Slide to Side B
6 PCT Segment Mobilization & Setting 2 2 2 1
7 Strand Installation, Setting & Grouting
8 PCT Erection 2 2 3
Steel Box Girder (SBG) Main Span
P5 - P6 Side A (3 Girders)
1 Launcher Setting from P4-P5
2 SBG Segment Mobilization & Setting 1 1 1
3 Internal Bracing Installation & Bolt Jointing
4 SBG Erection 1 1 1
P5 - P6 Side B (3 Girders)
5 Launcher Slide to Side B
6 SBG Segment Mobilization & Setting 1 1 1
7 Internal Bracing Installation & Bolt Jointing
8 SBG Erection 1 1 1
According to the schedule analysis, the duration to finish PCT main span is faster by 4 days than SBG. With 3
main spans of each design, duration for PCT erection is 3 x 34 = 102 days while SBG erection is 3 x 38 = 114 days,
making SBG erection is slower by 11.76% due to its more complicated sequence of SBG segment & accessories
mobilization to site and also installation including the internal bracing inside the SBG and many bolt and plate
connections along the girder need extra attention.
Based on Directorate General of Highways’ General Specification 2018 Rev 2, there are 3 pay items affected by these
2 respective designs that are girder provision, girder installation and foundation. Each pay item are structured from 3
components which are man, material and machine. The 30 MPa reinforced concrete volume (m3) of pile cap, pier and
pierhead elements are considered similar and can be neglected. The cost of each method is explained in Table 1 below:
Table 2 Cost Comparison of Bulb Tee and Steel Box Girder (Author Data, 2023)
Pay Item Work Item Unit Unit Price (IDR) Volume Price (IDR)
Bulb Tee (PCT) 178,496,681,080
7.2.(11a) Provision of 60 m Bulb Tee (PCT) Girder Pcs 2,341,490,500 42 98,342,601,000
7.2.(11b) Installation of 60 m Bulb Tee (PCT) Girder Pcs 511,735,240 42 21,492,880,080
7.6.(19b) 1000 mm Diameter Boredpile m 5,800,000 10,114 58,661,200,000
Steel Box Girder (SBG) 250,282,920,000
7.4.(1b) Provision of Structural Steel Grade 345 MPa Kg 41,830 3,834,000 160,376,220,000
7.4.(2) Installation of Structural Steel Kg 11,750 3,834,000 45,049,500,000
7.6.(19b) 1000 mm Diameter Boredpile m 5,800,000 7,734 44,857,200,000
71,786,238,920
Deviation
40.22%
From the cost analysis, it can be clearly seen that provision and installation costs are higher by 63% and 109,6%
respectively in SBG than in Bulb Tee design while boredpile foundation cost is lower by 23,53% in SBG due to its
lighter girder weight withstood by substructure. In total, the cost to construct SBG bridge along with its accessories
(bolt connection, internal and external bracing) are more costly by 40,22% than Bulb Tee designed bridge.
According to the conducted analysis, the result of comparison for each aspect is as follow on Table 3:
Table 3 Aspect Comparison of Bulb Tee and Steel Box Girder (Author Data, 2023)
Option
Aspect
1 2
Design Bulb Tee (PCT) Steel Box Girder (SBG)
Method Launching Gantry Launching Gantry
Duration (Day) 102 114
Cost (IDR) 178,496,681,080 250,282,920,000
Maintenance Minimum Routine
From the table above, Bulb Tee excels in 3 aspects that are fewer main span duration by 12 days or 11.76%, lower
cost by 71.79 billion IDR and minimum maintenance for concrete structure rather than SBG. SBG option has
disadvantages due to more complicated erection method, more expensive structural steel and routine maintenance of
coating for steel structure preservation.
5. CONCLUSIONS
To conclude, from the analysis done, Bulb Tee and SBG designs are compared based on method, cost and duration
aspects. Using launching gantry for erection of both designs, Steel Box Girder (SBG) main spans cost 250 billion IDR
in 114 days with further extra cost for coating, while Bulb Tee cost 178.5 billion IDR in 102 days. From the result,
the special bridge design is more costly by 40.22% and time consuming by 11.67% to be implemented. Therefore,
Bulb Tee Girder is used to ensure Wain River Bridge can be functional by July 2024.
6. ACKNOWLEDGEMENTS
In writing this paper, the writers would give the utmost gratitude to Ministry of Public Works and Housing of
Indonesia, IKN Toll Road Segment Karangjoang – KKT Kariangau Project Team that consists of HK-Adhi-Abipraya
JV and PT Wahana Perencana Persada (WPP) for the opportunity, sharing of data and continuous discussion.
7. REFERENCES
[1] Detail Engineering Design (DED) of IKN Toll Road: Segment Karangjoang – KKT Kariangau.
[2] Hazairin, Widyaningsih, E. & Sakinah, N. N. 2022. Analisis Perbandingan Biaya Penggunaan Steel Box Girder
Berdasarkan Variasi Jumlah dan Dimensi (Studi Kasus: Jembatan Cimanuk Maktal). RekaRacana: Jurnal Teknik
Sipil, Maret 2022.
[1] Ismerianto, Nuh, S. M. & Syahrudin. METODE PELAKSANAAN STRUKTUR ATAS JEMBATAN TAYAN.
Program Studi Teknik Sipil Universitas Tanjungpura Pontianak. Pontianak.
[2] Izza, F. K., Praditama, M. A., Kirana, C. N., Setiyono, K. J., Sudarmono. (2019). KAJIAN WAKTU
PENYELESAIAN METODE CRANE DAN METODE LAUNCHER DALAM PELAKSANAAN ERECTION
GIRDER JEMBATAN (Studi Kasus : Pembangunan Jalan Tol Semarang – Solo Ruas Salatiga – Boyolali Sta
40+409 – Sta 71+785). Wahana TEKNIK SIPIL Vol. 24 No. 1 Juni 2019 47 – 59.
[3] Leo, E., A. M. H., Nur. (2017). KAJIAN EFISIENSI BULB-TEE SHAPE AND HALF SLAB GIRDER
DENGAN BLISTER TUNGGAL TERHADAP PC-I GIRDER. Jurnal Muara Sains, Teknologi, Kedokteran, dan
Ilmu Kesehatan Vol. 1, No. 1, April 2017: hlm 309-317.
[4] Liftindo. (2021). LAPORAN PERHITUNGAN STRUKTUR ERECTION PCT GIRDER PROYEK
JEMBATAN PEREULAK, ACEH.
[5] Pohan and Abror N. 2008. Perencanaan Jembatan Steel Box Girder Berdasarkan AASHTO LRFD 1998 dan
Aplikasi Program Utrap 2.0. Repositori Institusi Universitas Sumatera Utara (RI-USU)
[6] New Capital City Toll Road Section 3A: Karangjoang – KKT Kariangau Project Data
[7] Sangaji, A., Azhar, M. (2020). PENGARUH BIAYA DAN WAKTU ERECTION STEEL BOX GIRDER (SBG)
JALAN TOL JAKARTA CIKAMPEK ELEVATED II RUAS SIMPANG SUSUN CIKUNIR KARAWANG
BARAT. Jurnal Sain dan Teknologi TEKNIK UTAMA, Edisi khusus, No 3, Oktober 2020
[8] Sumaidi, Astawa, M. D. and S. Erki, B. PERENCANAAN JEMBATAN STEEL BOX GIRDER TIPE
KOMPOSITE DUA MATERIAL BAJA-BETON DENGAN DUA GELAGAR SERAGAM. JURNAL
ENVIROTEK VOL. 10 NO. 2. Program Studi Teknik Sipil, Universitas Pembangunan Nasional Veteran Jawa
Timur.