CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS

Location :

Contractor / Manufacturer :

-----------------------------------------

1 Tests on Main Switchboard

i. Has the wiring diagram of the main


switchboard been obtained from the
switchboard manufacturer ? [ ]

ii. Is incoming cable(s) de-energised ? [ ]

iii. Has the main switchboard been isolated from


the rest of the LT installation by opening
all the incoming and outing circuit
breakers, couplers and disconnecting the
incoming neutral cables from the
switchboard ? [ ]

iv. Are wiring connections and terminal labels


in accordance with the wiring diagram
supplied for the main switchboard ? [ ]

v. Is the earthing on the main switchboard


effective ? (check visually) [ ]

vi. Are all C.T. ratings (burdens, ratios,


class, polarity) in accordance with the
tender drawings ? [ ]

vii. Has the insulation resistance of the main


switchboard been measured and the results
recorded on Annex A ? [ ]

viii. Is the ammeter selector switch functioning


correctly ? (inject a current into one phase,
the ammeter should give a reading only when
that phase is selected; repeat for the other
two phases). [ ]

ix. Have the ammeters, voltmeters and KWH meters


(if any) been calibrated ? [ ]

CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS


1 Tests on Main Switchboard (cont'd)

x. Have the overcurrent and time delay relay


settings been adjusted and set correctly and
the settings recorded an Annex A ? [ ]

xi. Have earth-fault and time delay relay


settings been adjusted and set correctly
and the settings recorded on Annex A ? [ ]

xii. Have the incoming neutral cables been


reconnected to the main switchboard ? [ ]

xiii. For main switchboard with 2 incomers

a) Repeat above tests ii to xii

b) With coupler closed, are the main


busbars in phase ? [ ]

c) Is the mechanical interlock system


in order ? [ ]

Remarks (if any of the above answers is NO)

CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS

2 Verification of Polarity
i. Is the supply OFF ? [ ]

ii. Have all metal conduits and trunking been


bonded to earth ? [ ]

iii. Are all flexible cords, switches, fuses,


plugs, socket outlets and circuit breakers
in good serviceable condition ? [ ]

iv. Is the polarity throughout the installation correct ? [ ]

v. Are all single pole control devices in


live conductors only ? [ ]

-----------------------------------------

3 Effectiveness of Earthing Tests

a) Installation's earth electrode resistance test

i. Has the earth electrode(s) been


disconnected from the main switchboard ? [ ]

ii. Has the copper tape interlinking the earth


electrodes (if more than one electrode) been
disconnected and replaced with 1.5mm² PVC cable ? [ ]

iii. Has the overall earth electrode resistance


been measured and recorded in Annex A ? [ ]

iv. Has the 1.5mm² PVC cable been removed and


replaced with the original interlinking copper
tape (if any) and the earth electrode(s)
reconnected to the main switchboard ? [ ]

b) Lightning Protection System's earth electrode


resistance test

i. Has the overall earth electrode been


measured ? [ ]

Overall earth electrode resistance


is _______ ohms. [ ]
CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS

4 Insulation Resistance Tests

a) Pre-test checks
i. Is the supply OFF ? [ ]

ii. Are all permanent fittings (eg wall fans,


lamps, etc) connected ? [ ]

iii. Are all switches, circuits breakers,


etc OFF ? [ ]

b) Insulation resistance tests from main


switchboard to distribution boards

i. Has the insulation resistance been


measured and the results recorded
on Annex B / or C ? [ ]

c) Insulation resistance tests from


distribution boards to final sub-circuits

i. Has the insulation resistance been


measured and the results recorded
on Annex B and/ or C ? [ ]

d) Insulation resistance tests of individual


equipment (eg 3 phase motors) not included
in (b) & (c )

i. Has the insulation resistance been


measured and the results recorded on
Annex B and/ or C ? [ ]

-----------------------------------------

5 Ring Circuit Continuity Test

i. Is the supply OFF ? [ ]

ii. Are all ring circuit connecting


satisfactory ? [ ]

CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS

6 Phase Sequence Test

i. Is the supply OFF ? [ ]

ii. Is the phase sequence at the main


switchboard correct ? [ ]

7 Test of 13A Socket Outlet Connections

i. Is the supply ON ? [ ]

ii. Are the connections of all the 13A


socket outlets correct ? (check
using Ring Main Tester) [ ]

8 Earth-loop Impedance Test

i. Is the supply ON ? [ ]

ii. Has the socket outlet furthest from


the main switchboard been located ? [ ]

iii. Have all switches, MCBs, etc between


this outlet and the main switchboard
been closed ? [ ]

iv. Have all RCCBs (if any) installed


between this outlet and the main
switchboard been disconnected and
bypassed with jumper wires ? [ ]

v. Has the earth-loop impedance been


measured ? [ ]

Earth-loop impedance is ______ ohms

vi. Have the jumper wires been removed and the


RCCBs reconnected ? [ ]

CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS

9 On-load Tests

i. Is the supply ON ? [ ]

ii. Are all circuit breakers and other


protective devices in the installation
closed ? [ ]
iii. Did any protective devices trip when all
the lights, fans, etc were switched on ? [ ]

iv. Are all the lights, fans. etc


functioning properly ? [ ]

10 RCCB Tripping Tests

i. Is the supply ON ? [ ]

ii. Is the RCCB functioning properly ? [ ]

Note : Each RCCB should trip when its TEST


button is pressed and also when subjected
to an earth-leakage current (from an RCCB
tester plugged into a socket outlet supplied
by that RCCB) equal to its rated tripping
current.

iii. Have all the RCCBs been reset ? [ ]

CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS

11 Commissioning & Handling Over

i. Is the supply on and are all circuit breakers


and other protective devices closed ? [ ]

ii. Has an inventory check been made and


the results recorded on Annex D ? [ ]

iii. Have the operating and maintenance


manuals (if any) been compiled for
systems other than the normal LT
installation (eg fire detection system) ? [ ]

iv. Have all the relevant drawings been


updated to As Built status ? [ ]

v. Have arrangements been made to hand


over the operating and maintenance
manuals (if any) and the As Built
drawings to Area Office ? [ ]

vi. Has the installation been handed


over to the user unit ? [ ]

Note : Indicate Y for YES, N for NO or


NA (Not Applicable) in the brackets provided.

-----------------------------------------

Tested by Witnessed by

Name : Name :

LEW Grade : Appointment :

Signature : Signature :

Date : Date :
CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS

ANNEX A

Test Results of Main Switchboard Sheet No :

Location :

Project :

Drawing No :

-----------------------------------------

1 Insulation Resistance (megohm) :


Test Voltage : 500V

R-Y Y-B B-R R-N Y-N B-N R-E Y-E B-E N-E

2 Main Circuit Breaker Details

Make : Type : Serial No :

Rated Volt : Rated Amp :

Capacity : Making KA Breaking KA

CT Ratio : YA : Class :

O/C Relay : DTL/IDMTL

Make : Type : Burden :

E/F Relay : DTL/IDMTL

Make : Type : Burden :

O/C Setting : % sec

E/F Setting : % sec

D/A Instantaneous Setting :

R % Y % B %

CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS


3 The earth electrode of the installation has been tested as __________ ohms.

4 Busbar size : Nos x Width x Thickness (in mm)

Phase Size (mm)

Red

Yellow

Blue

Neutral
CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS

Insulation resistance test record for 3 phase circuits ANNEX B

Location : Incoming Supply : Sheet No :

Project : Incoming circuit breaker


current rating :
Drawing No :
Incoming cable
Section Tested : MSB to DBs / DB to final sub-circuits / Individual equipment* (type & size) :

Tested at Switchboard / DB* No : RCCB Test : Pass/Fail/N.A.

CCT CCT Breaker Cable Circuit Insulation Resistance (Megohm)


No. Current rating (type & size) Description R-Y Y-B B-R R-N Y-N B-N R-E Y-E B-E N-E Remarks

* Delete as necessary

Tested by Witnessed by

Name : Name :

LEW Grade : Appointment :

Signature : Signature :

Date : Date :
CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS

Insulation resistance test record for single phase circuits ANNEX C

Location : Sheet No :

Project : Incoming Supply :

Drawing No : Incoming circuit breaker current rating :

Section Tested : MSB to DBs / DB to final sub-circuits / Individual equipment* Incoming cable (type & size) :

Tested at Switchboard / DB* No : RCCB Test : Pass/Fail/N.A.

Circuit Circuit breaker Cable Circuit Insulation Resistance (Megohm)


No. current rating (type & size) Description L-N L-E N-E Remarks

* Delete as necessary

Tested by Witnessed By

Name : Name :

LEW Grade : Appointment :

Signature : Signature :

Date : Date :
CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS

Inventory record of electrical fixtures and fittings ANNEX D

Project No : Sheet No :
Location / Bldg No : Drawing No :

Detailed Inventory Record of __________________ Storey


Fixtures Location Rm No: Rm No: Rm No: Rm No: Rm No:
Lamp Fluo c/w sw
Lamp ceiling c/w sw
Lamp bracket c/w sw
Spot light
Lamp Hi-bay
Lamp Low-bay
Lamp security
Exit light
Fan ceiling c/w reg
Fan ceiling (osci'ing)
Wall fan c/w sw
Fan exhaust c/w sw
13 Amp S/S/O (single)
13 Amp S/S/O (twin)
15 Amp S/S/O
Isolator (20A)
Isolator (30A)
Street light
Perimeter light
Fire Alarm Detection
System (as shown in as-
built)
Telecom manhole
Distribution Board
Freq Converter

Remarks :

Handovered By : Taken Over By :

Name/Signature/Date/Appt Name/Signature/Date/Appt
CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS

ANNEX E

CHECKLIST FOR INSTALLATION INSPECTION

All boxes are to be filled. Use NA where not applicable and NT where not tested.

1 All round clearance of the main switchboard shall


be not less than 600mm and the layout of the
switchroom is in accordance with the approved plan [ ]

2 The switchroom door shall open outwards from the


inside of the switchroom without the need to use
a key. [ ]

3 Precaution shall be taken where any pipes such as


sewerage and water pipes are run through or into
the switchroom [ ]

4 All switchroom requirements listed below shall be


provided :

(a) Fire Extinguisher [ ]

(b) Rubber Mat (5 mm thick) [ ]

(c ) First-Aid Chart [ ]

(d) Single-Line Drawing endorsed by LEW [ ]

(e) Danger Signs on Doors and Removable Panels [ ]


of Switchboard

(f) Socket Outlets [ ]

(g) Adequate Lighting [ ]

(h) Cabinet for keys and Log Book [ ]

5 A set of incoming lights, outgoing lights or


voltmeter and ammeter complete with selector
switches are provided at the main switchboard [ ]

6 Removable neutral links are provided adjacent


to the main incoming and all outgoing 3-pole
circuit breakers [ ]

CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS


7 Busbars in main switchboard are adequately
rated [ ]

8 Protection against direct contact with accessible


live parts shall be provided for the switchboard.
The main incoming live terminals shall be
protected by barrier of at least IP2X [ ]

9 No under-voltage tripping device is used in the


incoming or supply associated with lift
installation [ ]

10 Check DC supply and battery source, if any, are


in working condition [ ]

11 Check that the installation is generally in


accordance with the single-line drawing [ ]

12 Passageway, inside and outside the switchroom,


shall be kept clear [ ]

13 Check that the relay settings are not tampered with [ ]

14 There is proper labelling on the switchboard for


all circuits. Labelling shall be permanent and
durable type. A permanent label indicating the
approved load shall be affixed to the incoming
panel [ ]

15 Rated breaking capacity of circuit breakers are


adequate at point of installation [ ]

16 Proper supports are provided for all wirings or


cables within the switchboard and other parts of
the installation [ ]

17 A proper earth bar is provided. A permanent label


indicating the earth value and test date shall be
affixed to the main earth bar. Check that all
protective conductors are effectively connected
to earth [ ]

18 Proper earth electrode inspection chamber is


provided and accessible. Warning notice
"Safety Electrical Connection - Do Not Remove"
is provided [ ]

CHECKLIST FOR TESTING AND COMMISSIONING OF LT INSTALLATIONS

19 Main equipotential bonding provided for all


exposed conductive parts and extraneous conductive
parts as necessary [ ]

20 Metallic trunkings and conduits are bonded to earth


and electrical continuity is effectively maintained [ ]

21 Cables, conductors and CPC are correctively sized


for their purposes [ ]

22 Links, switches, socket outlets, joints, terminations


and other accessories are in good condition [ ]

23 No switch or fuse is inserted in the neutral or


protective conductor unless it is required for
special purpose [ ]

24 Installation resistance between the conductors


and to earth at the main switchboard and other
parts of the installation shall be at least
1 M-ohm. (for LV installation) [ ]

25 Polarity at switches and socket outlets are correct [ ]

26 RCCBs are provided for all lighting and socket


outlet circuits in domestic units [ ]

27 Check the suitability of the type of MCBs and


RCCBs used [ ]

28 Circuits to high risk areas are protected by


RCCBs of 30 mA sensitivity (e.g. children
playground, garden lighting and areas which
are likely to be wet) [ ]

29 Electrical fitting or accessory installed outdoor


are suitable for outdoor use [ ]

PARTICULARS OF QP / INSPECTION OFFICER

Name : Appointment :

Signature : Date :

You might also like