FIXING OF REAR STORM MOULD

INTERIOR ANGLE TO STUD FRAME.


PROPRIETRY TYPE OF FIXING
& SPACING TO WIND LOADING
92MM STUD FRAME REGULATIONS. AS/NZS 1170.2
& VERIFIED BY FACADE
13MM PLASTERBOARD
ENGINEER.
LINING, SET & PAINT
FINISHED ZINC/ALUM BACKPAN TO
INSULATION TO STUD FRAME CLOSE CAVITY. SEALED
IN ACCORDANCE WITH TO BRICK & STUD
0703
BUILDING MATERIALS PLASTERBOARD REVEAL LINE
DESIGN (BASIX/SECTION J)
LINE OF SUBSILL BELOW
13
92
265

50

CAVITY FLASH BELOW


110

SARKING TO INTERNAL WALL


INSTALLED IN ACCORDANCE TO
AS/NZS4200.2. FOR BRICK BRICK SILL
VENEER FACADE WALLS
20x32x1.6MM POWDERCOATED
ALUMINIUM TRIM STORM MOULD
BRICK VENEER WALL
ANGLES BED IN SEALANT TO
CONSTRUCTED TO AS3700 WITH
JAMB OR PROVIDE SUBJAMB TO
CAVITY FLASHING TO WALL &
SUIT PROPRIETARY WINDOW
CONTINUE ALONG UNDER
FRAME SIZE
WINDOW TO AS2904
SEALANT & BACKING ROD TO
WINDOW SUBCONTRACTORS
DETAILS & AS VERIFIED BY
EXTERIOR FACADE ENGINEER

CONSTRUCTION TRADE SEQUENCE


1. INSTALL STUD FRAME 6. INSTALL SUBSILL TO WINDOW OPENING TOGETHER WITH FULLY
SEALED 'END DAM' PIECE
2. INSTALL SARKING TO WALL & ACROSS OPENING
7. INSTALL ALUMINIUM STORM MOULD TRIM TOGETHER WITH
3. CUT SARKING & CORNERS ACROSS OPENING AT 45° & FOLD SUBHEAD TO WINDOW OPENING WITH ALL SIDES FULLY SEALED
SARKING INTO INTERNAL FACE OF OPENING ALL IN ACCORDANCE WITH BACKING ROD. NOTE: INSPECTION HOLD POINT TO FACADE
WITH PROPRIETARY FIXING @ TAPPING, & BANDAGES TO OPENING ENGINEER. TO FIXINGS & SEALS

4. PULL STUD WALL WITH INSULATIO AS SPECIFIED VIA BASIX/ 8. INSTALL WINDOW SYSTEM TO OPENING
SECTION J
9. INTERNAL FINISHING & LINING TRADE TO COMPLETE SET
5. CONSTRUCT MASONRY VENEER WALL TIED TO INTERNAL JOINT & PAINT FINISH TO PLASTERBOARD
LIGHTWEIGHT STRUCTURAL STUD WALL IN ACCORDANCE TO AS3700

NOTE:

ZINC/ALUM METAL SHEET BACK PAN TO BE INSTALLED IN LIEU OF A PERMEABLE SARKING IN ACCORDANCE WITH PARKVIEW PERFORMANCE SPECIFICATION AND/OR
PROJECT SPECIFICATION AND WIND ASSESSMENT REPORT. ZINC/ALUM METAL SHEET BACK PAN IS TO BE INSTALLED IN LIEU OF PERMEABLE SARKING TO ALL
LIGHTWEIGHT UNPROTECTED EXTERNAL WALLS (I.E. NOT COVERED BY BALCONIES OR THE LIKE) WITHIN CLIMATE ZONES 1-5 TO MANAGE WORKMANSHIP AND WATER
INGRESS ISSUES FROM A TRADITIONAL PERMEABLE SARKING.

FOR CLIMATE ZONES 6-8 A PERMEABLE SARKING MUST BE INSTALLED IN ACCORDANCE WITH PART F6 ‘CONDENSATION MANAGEMENT’ OF THE NCC. FOR THESE CLIMATE
ZONES 6-8 A PERMEABLE RIGID AIR BARRIER SUCH AS ‘SINIAT’ OR ‘CEMINTEL’ OR SIMILAR IS TO BE INSTALLED IN LIEU OF A PERMEABLE SARKING TO MANAGE
WORKMANSHIP AND WATER INGRESS ISSUES FROM A TRADITIONAL PERMEABLE SARKING.

Project: Title: Project #: Scale: Drawn by:


PARKVIEW STANDARD WINDOW JAMB - BRICK 742 1 : 5 @A4 AK
DETAILS VENEER WALL Drawing No: Rev: Approved by:

0104 C IN PARKVIEW CONSTRUCTIONS PTY LTD


ABN 41078064963

FINAL ©COPY RIGHT PARKVIEW CONSTRUCTIONS


ALL RIGHTS ARE RESERVED. NO PART OF THIS PUBLICATION MAY BE REPRODUCED OR TRANSMITTED IN ANY
REV NO. REV DESCRIPTION DATE FORM OR BY ANY MEANS, WITHOUT THE EXPRESSED PERMISSION OF PARKVIEW CONSTRUCTIONS, UNLESS
SPECIFICALLY ALLOWED FOR BY THE TERMS OF A CONTRACTUAL AGREEMENT WITH PARKVIEW
A Preliminary Issue Nov 2018 CONSTRUCTIONS. PARKVIEW CONSTRUCTIONS GRANTS THE PRINCIPAL AND/OR CONSULTANT AN
B For Review 15/05/2019 IRREVOCABLE LICENCE TO USE THIS DOCUMENT FOR THE PROVEN WITH THE PRINCIPAL AND/
ORCONSULTANT TO ENSURE THAT THIS DOCUMENT IS USED ONLY FOR THE PORPOSE OF THE PROJECT.
C Final Issue 09/10/2019