You are on page 1of 4

VISION PROPERTIES DEVELOPMENT CORPORATION

PROJECT SUNTRUST SOLANA


NATIVIDAD LOPEZ ST., COR. AYALA BLVD., ERMITA, MANILA

PROPOSED PRECAST FOR THE


FIRE EXIT CURTAIN WALL
(RECTIFICATION METHODOLOGY FOR THE CURTAIN WALL OPENING INCLUDING PRECAST PANELIZATION AND INSTALLATION)

PRESENTED TO:
SUNTRUST PROPERTIES INCORPORATION

JULY 2021

PROJECT: SOLANA CONDOMINIUM


VISION
PROPERTIES DEVELOPMENT
OWNER: SUNTRUST PROPERTIES
SUBMITTAL
CONTRACT SCOPE: 0000014730 REQUEST FOR APPROVAL
8
CONCRETE LEDGE CONCRETE LEDGE

A3

350

PROPOSED PRECAST

1900

128
300

300
E
127

SEE PRECAST PLAN PROPOSED PRECAST


A2 PANEL SEE DRAWING A2

219122
FIRE EXIT CURTAIN WALL
PROPOSED PRECAST CONCRETE

A1 CURTAIN WALL
MULLION
243 JOBMIX

SCALE :NTS

PROJECT: SOLANA CONDOMINIUM


VISION
PROPERTIES DEVELOPMENT
OWNER: SUNTRUST PROPERTIES
SUBMITTAL
CONTRACT SCOPE: 0000014730 REQUEST FOR APPROVAL
20MM DIA REBAR DOWEL 20MM DIA REBAR DOWEL
EMBEDDED TO EXISTING EMBEDDED TO CONCRETE LEDGE
PRECAST/BEAM BY 100MM BY 100MM DEPTH WITH
DEPTH WITH CONCRETE EPOXY CONCRETE EPOXY

100
150
CONCRETE LEDGE

20MM DIA. REBAR NON-SHRINK GROUT

LENGTH OF PRECAST = 2450


15MM THK STYROFOAM

PROPOSED ADD'L PRECAST


STEEL MESH
20MM DIA. PRECAST

EXISTING PRECAST
DOWEL FULL WELDED TO

2650
PRECAST/BEAM AND
150

CONCRETE LEDGE DOWEL

(EXTERIOR SIDE)
(INTERIOR SIDE)
FIRE EXIT CURTAIN WALL
PRECAST PLAN DETAIL
A2
SCALE :NTS FIRE EXIT CURTAIN WALL
PRECAST CONNECTION DETAIL
A3
SCALE :NTS

PROJECT: SOLANA CONDOMINIUM


VISION
PROPERTIES DEVELOPMENT
OWNER: SUNTRUST PROPERTIES
SUBMITTAL
CONTRACT SCOPE: 0000014730 REQUEST FOR APPROVAL
METHODOLOGY STATEMENT FOR THE RECTIFICATION OF FIRE EXIT STAIR
CURTAIN WALL OPENING AND INSTALLATION OF PRECAST WALL.

1. RECTIFICATION OF FIRE EXIT CURTAIN WALL OPENING


1.1 FOR THE CLEAR OPENING, REFERENCE LINE (HEREAFTER REFERRED TO AS "PITIK" ) SHALL BE PROVIDED. FROM "PITIK",
950MM SHALL BE PROJECTED TO BOTH SIDES TO ESTABLISH 1900MM CLEAR OPENING. THE FIRE EXIT CURTAIN WALL SHALL
HAVE 1900MM CLEAR OPENING FROM FIFTH FLOOR UP TO THE ROOFDECK.

1.2 IN CASES WHEREIN THE EXISTING SIDE OF THE CURTAIL WALL OPENING LACKED OR EXCEEDED FROM THE ESTABLISHED
"PITIK", CHIPPING WORKS AND PLASTERING WORKS WILL BE EXECUTED. IF THE REQUIRED PLASTERING WORKS EXCEEDED
40MM, STRUCTURAL SUPPORT SUCH AS STEEL MESH OR REBAR SHALL BE ADDED.

1.3 PRIOR TO THE MOBILIZATION OF PLASTERING WORKS, ALL SURFACES SHALL BE CHISELED TO ATTAIN A ROUGH
CONCRETE SURFACE. NEXT, APPLY CONCRETE EPOXY, WAIT UNTIL THE EPOXY IS HALFWAY CURED, THEN PROCEED TO THE
PLASTERING WORK.

1.4 FOR THE ALIGNMENT OF STAIR MIDLANDING BEAM AND PERIMETER BEAM, GRIDLINE "PITIK" SHALL BE ESTABLISHED
FIRST. FROM THE "PITIK" 127MM OFFSET SHALL BE PROJECTED (SEE DRAWING A-1). ALL BEAM FACES THAT WOULD EXCEED
FROM THE 127MM OFFSET SHALL BE CHIPPED AND RECTIFIED TO THE REQUIRED ALIGNMENT. HOWEVER, BEAM FACES THAT
WOULD NOT EXCEED FROM THE 127MM OFFSET SHALL BE RETAINED, THESE BEAMS WILL BE RECTIFIED FOR ITS AESTHETIC.

2. FABRICATION OF PRECAST PANELS:


2.1 ON THE CASTING BED, FIRST, ESTABLISH "PITIK" FOR THE REQUIRED SIZE OF THE PRECAST. THEN PROCEED TO THE
FABRICATION OF FORMWORKS. AFTER FORMWORKS, LAY THE STYROFOAM, STEEL MESH, AND 20MM REBAR AS PRESCRIBE
IN THE DRAWING (SEE DRAWING A-2).

2.2 MIXTURE OF 1:3 CEMENT-SAND RATIO SHALL BE USE AS CONCRETE JOB MIX FOR THE PRECAST. MAKE SURE THAT THE
PRECAST REINFORCEMENTS ARE IN PLACE AND THE FORMWORKS IS FIXED, THEN PROCEED TO THE POURING OF CONCRETE
ON TO THE FORMWORKS. USE VIBRATOR TO VIBRATE THE CONCRETE IN ORDER TO AVOID HONEYCOMBS.

2.3 LET THE CONCRETE MIXTURE SET FOR AT LEAST 2 DAYS TO CURE. AFTER CURING PERIOD, STRIP THE PRECAST FROM ITS
FORMWORKS.

3. INSTALLATION OF PRECAST PANELS:


3.1 PREPARE THE AREA WHERE THE PRECAST WILL BE INSTALLED. DRILL 22MM DIAMETER HOLES FOR THE EMBEDMENT OF
PRECAST DOWELS. EMBED 100MM DEEP 20MM DIAMETER REBAR DOWELS WITH CONCRETE EPOXY ON THE DRILLED HOLES.

3.2 PRECAST PANEL MAY BE LIFTED TO ITS LOCATION USING GONDOLA OR TOWER CRANE. IF USING GONDOLA, ONLY SINGLE
PANEL PER LIFT WILL BE ALLOWED. MAKE SURE THAT THE EMBEDDED REBAR DOWELS ARE SECURE. FIX THE PRECAST TO ITS
LOCATION, FULL WELD PRECAST TO THE DOWELS (SEE DRAWING A-3). MAKE SURE TO SATISFY THE REQUIRED 1900MM CLEAR
OPENING BEFORE FIXING THE PRECAST.

4. MAKING GOOD OF THE INSTALLED PRECAST:


4.1 PRECAST GAP CONNECTION WILL BE SEALED UP WITH NON-SHRINK GROUT (SEE DRAWING A-3). TO SATISFY THE 128MM
MULLION WIDTH OF THE CURTAIN WALL, 122MM DEPTH PATCHING OF CONCRETE JOBMIX WILL BE EXECUTED AT THE INTERIOR
SIDE OF THE PRECAST PANEL (SEE DRAWING A-1).

4.2 PROCEED TO THE RUBCON OF THE PRECAST THEN APPLY PRIMER TO THE OPENING OF THE CURTAIN WALL. AFTER THAT,
THE INSTALLED PRECAST AND THE ENTIRE CURTAIN WALL OPENING MAY NOW BE HANDOVER TO THE CURTAIL WALL
CONTRACTOR FOR ACCEPTANCE.

PROJECT: SOLANA CONDOMINIUM


OWNER: SUNTRUST PROPERTIES
SUBMITTAL
VISION
PROPERTIES DEVELOPMENT
CONTRACT SCOPE: 0000014730 REQUEST FOR APPROVAL

You might also like