4 Detailed System Design Progress

1. Aruba Wifi
I. WLAN Services
II. Provisioning different type of wireless access services
III. Measured and stored for marketing purpose
IV. Use public internet needed to be logged for register and authorized
V. Security and restriction limit usage of specific protocol and application
VI. Public traffic tunneled for router and firewall able to support 10K concurrent users.
VII. Portal - Clear Pass System
VIII. Master Management Software & Hardware
IX. Wi-Fi which able to integrated with 3rd party software / equipment
X. Employer and passenger wireless access proposal and portal design
XI. SSID and security proposal for various device including employer, passenger, BMS, ip phone etc.
XII. Whether the implementation of the portal needs to add third-party equipment,
XIII. The detailed design of the portal

As per discussion yesterday with Aruba & CCMC on voice conference, all in the above needed to insert into the
proposal and will be send to me for verification and after that send to Mr. Zhou for 2 nd verification. As the revised
proposal will be submitted to us on next week Monday.

2. AWTS
I. Management System
II. Alcatel Lucent Enterprise Solution detailed design (Network Architecture)
III. Security solution (Network and System Security)
IV. System Backup
V. System Configuration Summary (Product List)
VI. Test Plan procedure (System Test)
VII. Call Recording Test
VIII. Cabinets Drawings for the PBX system

As per discussion yesterday with Aruba & CCMC on voice conference, all this above will need to in detail and insert
into the proposal, like example which device is going to insert into MCR 1 and which part is going to insert in MCR 2,
proposal needed to write down in MCR 1 and MCR 2 what are the arrangement of this device and the AWTS base on
each port what, where and used for. This proposal will be submit again to me from Visco and will verify by Mr.Bo and
me. As inform they will submit to me by this week Saturday.

3. IPTV & AV
I. Detail Design Proposal
As per discussion on Tuesday with IT Team & Krovan team in PP Office, the proposal is not worth doing it as because
the proposal is too short due to we on process the front end and the IT Team is still looking for the satellite provider.
At first we want communicate with DSS team to learn more about the flow but after the consideration, if we insert
the DSS system into the proposal,for the configuration, installation, purcashing and responsibility will be by
Terrasyss. As DSS side is not in CCMC and Terrasyss scope of work as confirm by Mr.Liu. This project we are still
following up and it was postponed as due to we are putting priority on the WI-FI, AWTS and Car Parking

4. Car Parking
I. Car Parking Entry and Exit Diagram
Diagram needed to provide CCMC the foundation, dimension and size. Awaiting for our drawing team Reangsey to
provide the drawing with the size and dimension to us to submit to CCMC Mr. Luo