Professional Documents
Culture Documents
Fajar Ariessita*
Timur M. Simanjuntak*
Elin Ika Gartika*
Kamal Hamzah*
M. Rifki Akbar*
Antonius Himawan**
The Telisa reservoir is a saturated, low The optimum fracture height is in the range of 70–
permeability, shaly sandstone with two flow units, 90 ft. This is consistent with average reservoir
each containing an initial gas cap, separated by a thickness in the Telisa. Too small fracture heights
shale break. Figure 3 shows the porosity map in do not provide adequate transmissibility or cross-
Sand 1 and Sand 2. The most porous formation is in flow area. On the other hand, too large fracture
the southern part (porosity around 30%); while in heights could cause fracture propagation into gas
other areas it varies between 10–25%. The smallest cap or bottom-water zone.
Sw, around 40%, is also identified in the southern
part in Sand 1, where the average Sw in Sand 2 is The optimum fracture width is 0.3–0.7 inches. This
50%, (Figure 4). is expected since fractures with small widths
provide low conductivity at the wellbore, while
Figure 5 shows the Telisa sand model in the Kaji those with large widths exhibit very short half-
field, which consists of two sands separated by 5–7 lengths and probably poor placement of proppant
ft shale, while Figure 6 displays the open-hole log within the fracture.
of the Telisa sand. The resistivity is quite low,
around 3–7 ohm.m. Even though it shows low The optimum fluid efficiency is in the range of 50–
resistivity zone, it is proven to be hydrocarbon- 70%. No obvious correlation is recognized between
bearing sand. the initial oil production rate and the PAD volume
used in the main-frac stage. It should be noted that
Hydrocarbons were observed during drilling, with the PAD volume (expressed as a fraction of total
C1–C4 gas and oil showing up to 30%. The sand is PAD plus proppant slurry volume) is usually
calculated from fluid efficiency after the mini-frac in the fine grid 3-D model are shown in Figure 9.
stage. This polygon encompasses all Telisa sands within
the oil-water contact or where net thickness is more
Three proppant sizes are used in fracturing Telisa than 5 ft.
wells. Although the observed oil production data do
not show a distinct trend, it appears that 20–40 Several scenarios were developed to find the
mesh size proppant without mixing provide better optimum case in terms of oil recovery and
results compared with other sizes. operational reliability. Based on reservoir
simulation, a low water injection rate from a
As expected, the wells completed in high resistivity, dominantly peripheral pattern will perform well and
high porosity, and thick reservoir regions exhibit therefore has a significant effect on increasing the
high initial oil production rates. The data indicate oil recovery factor from 9% to 13%.
that a minimum of 2 ft hydrocarbon pore thickness
(net pay porosity oil saturation) is required for After deciding that water injection was the most
economical oil rates. feasible and applicable method to maintain pressure
in this sandstone, a detailed and more intensive
Observed production data indicate that delays in study was conducted to assess the compatibility of
putting wells on production after drilling generally the injection water with the formation. The study
results in lower oil production rates. This is consisted of (1) laboratory test for core-flooding
probably due to the extensive formation damage experiments to evaluate the characteristics of
caused by clay swelling. permeability damage during water injection, scaling
tendency in formation, and near wellbore plugging;
Production from the Telisa formation reached its (2) a pilot injection test to determine well
peak of 7000 BOPD in 2006. Rapid reservoir injectivity; (3) reformulation of the reservoir
pressure depletion, 80 psi / % STOOIP produced, simulation for defining the optimum velocity of
contributed to a rapidly decreasing production rate. water injection for best oil recovery.
As a result, this sand required pressure maintenance
immediately. An integrated and holistic preliminary METHODS
study conducted in 2008 analyzed the three
injection methods: gas, water, and a combination of Laboratory Test
gas and water. The results are shown in Table 1.
The incompatibility between injection fluids, such
Due to the gas shortage in the Kaji Semoga field, as water flood or chemical injection, and reservoir
gas injection is not possible, even though it rock and fluid, may cause scale production and
produces the biggest cumulative oil. Water injection formation damage, which can lower the oil
is more viable because of its abundant availability. production performance. To overcome these
However, water injection is challenging because of problems, before injecting any fluid into a reservoir,
the presence of water sensitive clays, such as laboratory studies should be performed to evaluate
kaolinite, smectite and illite in the shaly sandstone the effect of the injection fluid on the reservoir rock
reservoir. As water is injected kaolinite will swell and fluid. The laboratory work includes evaluation
and smectite and illite will cause fines migration. of injection fluid quality and compatibility with
reservoir, scaling tendency, return permeability and
A geological and reservoir model was made for this plugging indication tests. The injection water was
simulation study using a satisfactory history match taken from the Kaji manifold and the formation
of observed production and reservoir pressure water and core was taken from the Telisa reservoir.
performance from a previous study. Hydraulic
fracturing was incorporated in the model by adding Compatibility Test
fractures and increasing transmissibility. An
integrated GGR study with a three-dimensional (3- The objective of this testing was to evaluate the
D) model was also conducted to examine the solids depositional tendency of the mixture of
advantages of an alternative pressure maintenance injection and formation water. The experiments
scheme and to evaluate if water injection is feasible were conducted at reservoir temperature (182 F).
and applicable in this formation. A fine-grid 3-D The injection water sample was taken from the Kaji
geological model was made to represent the Telisa field manifold, while the formation water was taken
reservoir in the Kaji field. Table 2 gives the model from the Telisa well. The compatibility test between
characteristics. The fault pillars and polygons used the injection water (WI Kaji field manifold) and the
formation water (Telisa reservoir) is shown in Table injection water, WI Kaji Field Manifold, and the
3. Telisa reservoir formation water have no tendency
to form CaSO4, BaSO4, and SrSO4 scale at both
A proportional deposit number is calculated based surface temperature and reservoir temperature, as
on the percentage of fluid in the mixture, that is, the the concentration of the ions exists below the
proportional deposit number of 25% WI KJ M + saturated condition. Thus, the injection water is
75% TLS KJ mixture is (25% * 8.0500 mg/l) + compatible enough to inject in the Telisa reservoir.
(75% * 14.9750 mg/l) = 13.2438 mg/l (Figure 10).
The formed deposit is the actual deposit number Return Permeability Test.
that formed. It was concluded that the formation
water from the Telisa reservoir is compatible with The objective of this testing is to evaluate the
the injection water as the amount of the deposit decrease in core permeability due to any
formed after mixing the two is lower than the incompatibility between the Telisa core and
original proportional deposit number. It means that injection water. For this purpose, a core from the
when they are mixed, the new additional deposit Telisa well was injected with water (from the water
will not be formed. injection manifold in Kaji). The permeability was
measured after a specific amount of water was
Scaling Tendency Analysis injected in core plug pore volume. The result of the
test is shown in Figure 11.
The objective of this testing is to evaluate the
tendency of the scale formation by mixing injection Permeability is not the only property being
and formation water. The experiments were measured during the return permeability testing.
performed at room (77 F) and sampling temperature Petrographic and XRD analysis was performed
condition (176 F). The injection water sample was before and after testing (Table 8). The results of the
taken from the Kaji field manifold, while the return permeability test between the water injection
formation water was taken from the Telisa well. Kaji Field Manifold and the Telisa reservoir core
result show:
Analysis of CaCO3 scale formation from injection
water or after mixing with formation water was No change in clay composition.
calculated by applying the Stiff and Davis method.
Using SI as the Stability Index: if SI is negative, the A decrease in core permeability of about 40–
water is undersaturated with CaCO3 and scale 50%, because of clay fine migration (at 40–70
formation is unlikely. If SI is positive, scale is likely cumulative throughput-PV).
to form. The results of the CaCO3 scaling tendency
calculation from several water samples can be seen Based on the compatibility test results, there is no
in Table 4. indication of clay swelling, thus the injection water
is compatible enough to be injected into the Telisa
The test results show that both the tested samples of reservoir.
injection and formation water have the ability to
form the CaCO3 scale. The Telisa reservoir Plugging Tendency Analysis
formation water has no tendency to form CaCO3
scale at low temperature because the water pH is Based on Pang1, a filter equal to 1/3 pore throat size
low, about 6.40, thus ions still exist in the soluble needed to be installed to avoid formation plugging.
condition. The fluid exists in the equilibrium system Special core analysis shows that the biggest
since the solubility value (S) is equal to the sum of distribution in the Telisa reservoir pore size has a
concentrations of Ca++, Ba++, Sr++, or SO4 diameter more than 1.5 microns (Table 9).
(expressed in meq/l). However, if the S value is less Consequently, installing a 0.5-micron filter is
than the actual concentration, the fluid is in the mandatory to avoid formation plugging.
supersaturated condition and it is possible for the
scale to be formed. On the contrary, if the S value is Injectivity and Fall-Off Test
more than the actual concentration, the fluid
condition does not support scale formation. To determine well injectivity, injectivity tests
followed by fall-off tests were conducted in two
The above results, shown in Tables 5 to 7, show the wells in the southern section of the reservoir, KS-X
actual concentration of the solution still exists and KS-Y (Figure 12). The results of these tests
below the soluble concentration. It means that the showed that at initial injection time, the wells had
good injectivity, but it deteriorated over time. It was December 2013, an acidizing job was carried out to
suspected that the injection water filled up the bypass wellbore damage caused by scale build up in
existing fracture before it reached the formation. the perforation hole. It was suspected that scale
The fall-off test determined the actual stable originated from the untreated injection water from
injection rate. The pilot injection test executed in Baturaja Limestone. By removing the near wellbore
May 2009 confirmed a stable injection rate in the skin, the injection rate improved.
range of 400–600 BWIPD. The effect of pilot
injection on pressure was detected by the static Then, in August 2010, four more wells were
bottom-hole pressure sensors in the adjacent wells, converted into injection wells in addition to the first
which registered an increase in bottom-hole two injection wells. Two wells are in the northern
pressure. part and four wells in the southern part.
Unfortunately, the injection performance in the
The results in KS-X showed very high injectivity northern part is not as effective as in the south.
(Table 10). This high injectivity proved to be From the open-hole logs it is suspected that the
unsustainable in the long term. The decrease in shale content is higher in the northern area. The
injectivity is suspected to come from injected fluid total injection rate was 6000 BWIPD from six
filling the fracture during early time. wells. Similar to the southern part, a drop in
injection rate to 2500 BWIPD after a month of
The fall off test determined the actual stable injection was noticed, which returned to initial
injection rate (Figure 13). Despite the drop in values three months later. Lifting from the
injectivity, the test analysis showed that KS-X well surrounding well slightly decreased because
still had negative skin from hydraulic fracture and injection in the northern part was not as successful
good wellbore conditions for injection as listed in as injection in the south. The decline in rate reduced
Final Report of Development Optimization for from 45% to 30% annually and the recovery factor
Telisa Reservoir Kaji Field (Medco, 2008). increased from 9.3% to 10.1%. Figure 17 shows
subsurface location of injection well Y.
METHODS AND RESULTS
The effect of pilot injection on pressure is detected
PILOT INJECTION by static bottom hole survey (SBHP) in the adjacent
wells (wells F, G, H, I) which registered an increase
In May 2009, the two pilot injection wells KS-X of 500 psi in the bottom hole pressures (Figure 18)
and KS-Y were put on a pressure maintenance as reported by Dwi Marlia (2009).
project.
FULL SCALE
The initial injection rate was 600 BWIPD; however,
it dropped for a moment to 200 BWIPD, before Currently seventeen wells have been converted to
increasing to 1000 BWIPD. Clay swelling in the injection wells and the total injection rate is around
near wellbore region was the suspected reason of 6500 BWIPD (Figure 19, blue line). Total lifting is
the sudden drop that caused temporarily plugging 3000 BFPD (brown line) and yielding is 1750
before being broken down and swept away. As a BOPD (green line). Since 2009, the average WC
result, the injection rate increased after the initial has gradually increased from 20% to 42% (purple
drop. The effect was monitored in the surrounding line). Besides the increase in reservoir pressure, an
wells. Influx and water cut from the Telisa wells increase in WC indicates that the pressure
increased after three months of injection. Lifting maintenance program is successful. The decrease in
was doubled from 3000 BFPD to 6000 BFPD and injection rate is probably due to skin build up and
the WC jumped from 20% to 40%, yielding 1800 scale growth. Skin build up can be stimulated with
BOPD of oil gain. Figure 14 is a subsurface map of sandstone acidizing to bypass calcareous cement
the injection well (well X) and the five surrounding and scale. Scale formed since the injection water
wells (wells A, B, C, D, E) that are currently comes from several sources: Telisa sandstone,
producing. Well X is located in the southern part of Baturaja limestone, and fresh water.
Sand 2 and the spacing to the adjacent wells is 320–
550 m (Figure 15). One interesting fact is that since 2009 the volume of
produced gas has also slowly decreased (red line).
Figure 16 is the hall plot of well X that started Increasing reservoir pressure will force the solution
injecting in May 2009. Until today, this well is still gas to dissolve in the fluid phase; therefore, the
injecting at a rate of about 600 BWIPD. In produced gas is not easily released.
The effect of pressure maintenance is also indicated According to reservoir simulation, this project
by progressive increase in reservoir pressure, as is able to contribute an additional reserve of
shown in Figure 20. In the southern part, some around 4.1% of OOIP.
wells have reached 500–600 psi of reservoir
pressure, whereas in the northern part the pressure RECOMMENDATIONS
has reached 400-psi only. This is due to the higher
shale content in the northern part. Consequently, Convert four remaining wells to injection wells
injection in the northern part has been less efficient. to build a full-scale pattern for the pressure
maintenance program to obtain optimum
Twenty-one injection wells will be injecting a total recoverable reserve.
target rate of 12,500 BWIPD. Four wells are not
injecting due to network system. The recovery Apply tracer survey to identify the water
factor is expected to be 13.4%, providing an injection flow path.
additional reserve of approximately 4.1% of OOIP
(Figure 21). Restart hydraulic fracturing campaign when
reservoir pressure has reached 500-psi.
Reformulated reservoir simulation is also being run
to match the actual condition to deliver a more Install ESP to replace gas lift as artificial lift.
accurate production forecast for this project.
Reformulate reservoir simulation for full-scale
Hydraulic fracturing campaign will be reapplied to pattern to optimize injection program.
stimulate other potential Telisa wells. Due to gas
shortage switching the artificial lift from gas lift to Start infill-drilling program to increase recovery
an ESP is also an option. An ESP has been installed factor of this formation.
in one of the Telisa producer wells for a year, with
satisfactory result: 1200 BFPD, 92% WC, yielding ACKNOWLEDGEMENTS
96 BOPD. This well was also acidized last year
since it suffered formation damage. Telisa Authors wish to express their appreciation to Medco
sandstone also consists of calcareous cement, which E&P Indonesia, SKK Migas, Ditjen MIGAS, and
dissolves in acid. Therefore, a sandstone acidizing the Government of Indonesia for permission to
trial project has gained 400 BOPD since it started in publish the information on this project. We would
December 2013. An infill drilling campaign in this also like to thank all who contributed to this project,
tight sandstone formation is the next project to including the Petroleum Engineering team, the
increase the recovery factor and eventually escalate Petroleum Geoscience team, the Surface Facility
cumulative production. Engineering team, and the Production Department
of Rimau Asset.
CONCLUSIONS
REFERENCES
A water injection program started in 2009 has
proved very successful in maintaining reservoir Marlia, Dwi. A Comprehensive Study for Full Scale
pressure in the tight Telisa sandstone formation, Water Injection Project in Shaly Sandstone
with several observable indications in the Reservoir, Kaji Telisa Formation. 2009. IATMI09-
surrounding wells: 047.
Reservoir pressure has increased from 300 psi Medco E&P Indonesia, Final Report of
to 400–500 psi. Development Optimization for Telisa Reservoir
Kaji Field, Rimau Block,
Average WC has increased from 20% to 42%.
Medco E&P Indonesia, Plan of Development Telisa
GOR has decreased from 1000 SCF/STB to 400 & Talang Akar Formation, Kaji Semoga Field,
SCF/STB. Rimau Block, October 2005.
Recovery Factor is expected to increase from Priyantoro, Tri. Journey of Hydraulic Fracturing
9.3% to 13.4%. Improvement to Increase Oil Recovery from
Sandstone Formation in Rimau Block. 2009.
SPE156550-PP.
TABLE 1
TABLE 2
Parameter Value
Formed Proportional
No Composition Deposit, Deposit, Explanation
mg/l mg/l
1 0% WI KJ M + 100% TLS KJ 14.9750 14.9750 ‐
2 25% WI KJ M + 75% TLS KJ 10.8000 13.2438 compatible
3 50% WI KJ M + 50% TLS KJ 9.6750 11.5125 compatible
4 75% WI KJ M + 25% TLS KJ 6.6750 9.7813 compatible
5 100% WI KJ M + 0% TLS KJ 8.0500 8.0500 ‐
TABLE 4
TABLE 5
TABLE 6
TABLE 8
TABLE 9
16% calcite
24% clay 18% smectite
22% chlorite
9% illite
51% quartz
16% calcite 51% kaolinite
Well B Well A
Well C
Well X
Well D
Well E
Do nothing
RF 9.3%
Injection 17 wells
RF 12.5%