TABLE OF CONTENTS
1. GENERAL
1.1 INTRODUCTION
1.2 DEFINITIONS
1.3 PARTIES AND REPRESENTATIVES
2. PROJECT MANAGEMENT
2.1 PROJECT ORGANIZATION
2.2 CORRESPONDENCES AND COMMUNICATION
2.3 MEETING
4. PROJECT REPORTING
4.1 INTRODUCTION
4.2 REPORTING DOCUMENT
4.3 OUTLINE OF REPORTING DOCUMENT
APPENDIX
APPENDIX #1 DELIVERABLE LIST
APPENDIX #2 NUMBERING PROCEDURE
APPENDIX #3 FORM OF DOCUMENT
APPENDIX #4 FORM OF DRAWING TITLE BLOCK
APPENDIX #5 DOCUMENT DISTRIBUTION
APPENDIX #6 CONTRACTOR’S PROJECT ORGANIZATION
APPENDIX #7 COMPANY’S PROJECT ORGANIZATION
ATTACHMENT
ATTACHMENT #1 DOCUMENT DISTRIBUTION MATRIX
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 3 of 59
Date : 22 Jul, 2014
1. GENERAL
1.1 INTRODUCTION
The purpose of this coordination procedure is to establish a flow of documents and response on this
project in order to direct the various forms of correspondence and to provide administrative guidance
for the exchange of information and to coordinate the activities effectively and correctly keeping all
concerned parties informed throughout the Engineering, Procurement, Construction, Commissioning
and Performance Test of ERC Refinery for Egyptian Refining Company (TAKRIR) S.A.E.
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 4 of 59
Date : 22 Jul, 2014
1.2 DEFINITIONS
The following words and expressions shall have the meanings hereby assigned to them.
"Contractor" means “GS Engineering & Construction Corp.” and “MITSUI & Co., Ltd.”, together
being Contractor.
"Sub-contractor" means any person to whom execution of any part of the Works, including
preparation of any design or supply of any Materials, is sub-contracted directly by the Contractor or
indirectly, and includes its legal successors, permitted transferees and permitted assigns.
"Licensor" means “Axens” and “Bechtel Hydrocarbon Technology Solutions” and “Tecnimont KT”
as the company to have the license.
"Contract" means this contract entered into between the Company and the Contractor comprising the
Contract Documents on Dated 29 August, 2007.
"Work" shall mean all of the Contractors' obligations under the Contract in respect of its delivery to
Company of a complete and operational Plant as specified in the Contract.
"Materials" means the supply of all Construction Equipment and Materials required for the Plant
and all services and labour needed for the design, engineering, procurement, construction, erection,
interconnection, supervision, training, pre-commissioning, commissioning, start-up, testing,
completion and delivery of the Plant in accordance with the requirements of the Contract; and all other
works, services and obligations to be carried out by the Contractor under the Contract.
"Construction Equipment" means all plant, facilities, temporary structures, equipment, machinery,
tools, apparatus, appliances and things of every kind used or required in or for the construction,
completion and/or maintenance of the Works, but does not include Materials;
"Site" means the land upon which the Plant is to be constructed under the Contract.
"Lay-down Area" means the land use rights of which Company will provide and suitable to be used
for the Project as a lay-down area by the Contractor.
“Party” means either the Company or the Contractor, as the case may be, and "Parties" means both
the Company and the Contractor.
“Project” means the financing, design, engineering, procurement, construction, completion, operation
and maintenance of the Plant.
“Plant” means the hydro-cracker plant complex (which is to meet the Unit Performance Guarantees,
the Plant Reliability Guarantees and the Plant Performance Guarantees).
If any of the above Contract’s definitions conflict with any part of the Contract, the Contract shall
govern.
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 6 of 59
Date : 22 Jul, 2014
Project authorized representatives and correspondence channels among each party are as follows ;
1) Mailing address : 31 Omar Bakeer St. 9th Floor From Osman Ebn Affan St.
Heliopolis-Cairo, Egypt
2) Telephone number : (20) 2 2634 1556/1557/1653
3) Telefax number : (20) 2 2634 1753
4) Attention : Min-Ho Song / Interface Manager
5) E-mail address : mhsong@gsconst.co.kr
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 8 of 59
Date : 22 Jul, 2014
1) Mailing address : 31 Omar Bakeer St. 9th Floor From Osman Ebn Affan St.
Heliopolis-Cairo, Egypt
2) Telephone number : (20) 2 2634 1556/1557/1653
3) Telefax number : (20) 2 2634 1753
19 4) Attention : Seongmin Kang / Construction Manager
5) E-mail address : smkang02@gsconst.co.kr
2. PROJECT MANAGEMENT
The project organization of each party is shown on the following chart respectively.
Refer to Appendix #6
Refer to Appendix #7
(1) The following Protocol for EGPC subsidiaries and most involved Egyptian institutions will be
applied:
Company Construction Manager will perform the initial introductions for PMC Interface
Manager and Contractor Interface Manager either together or stage by stage at senior and
working level
Working meetings and site visits can then be arranged through the interface coordinators, with
Contractor Project Manager, PMC Project Manager, and Company Construction
Manager copied on all correspondence, emails, and MOMs
(2) For initial site correspondence PMC Site Representative is PMC Interface Manager prior to
mobilization of PMC Construction Manager. Contractor Site Representative will act on behalf of
Site Manager until mobilization of its Site Manager.
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 11 of 59
Date : 22 Jul, 2014
2.2.1 General
(1) All parties are required to maintain their own log to record incoming and outgoing
correspondence numbers.
(2) All parties will be required to inform others when they find gaps in sequence numbering.
(3) All correspondences shall be in English Language and shall be addressed with only one subject
as far as practical.
(4) Dates shall be written in the following order : day, month, year.
(5) All Project correspondences (outgoing and incoming) should be reviewed, approved, and signed
by Representative or nominated deputy as appropriate. Author’s name shall be shown.
(6) If Contractor receives instructions from persons other than Company Representative, Contractor
shall immediately refer it to Company Representative.
(7) The receiving party shall use its best effort to reply to the correspondence within fourteen (14)
calendar days after the receipt. In matters of the documents listed in Exhibit 29 in particular
Company shall reply at least within fourteen (14) calendar days after the receipt.
(1) Letter
Parties can use their own letterhead for general and contractual correspondence. As far as
possible, letters shall be confined to one subject only.
Each Transmittal shall identify each document in the package showing at least the number of
copies, document title, document number, revision number, date of issue and size including
document name. It shall show for each document the purpose for sending it ; e.g. For approval,
comment, information, record or others.
Each Transmittal must cover only one such class of document and where practical one type of
document; e.g. Plot plans, PFD’s or isometrics etc.
Three (3) copies of Document Transmittal shall be sent, one of which shall be signed and
returned to the sender by the recipient acknowledging receipt and showing date and time of that
receipt. If documents are missing or incorrectly identified, suitable comments shall be made on
the returned Document Transmittal.
All matters of significance discussed and agreed by telephone or via informal discussion shall
be confirmed by formal correspondence within three (3) days of discussion.
For practical communication at the Site, all telephoned or oral instructions or agreements made
by the parties shall be confirmed in writing by the initiating party as a record of conversation.
However, oral instructions or agreements made in a formal meeting between the parties shall be
recorded in the Minutes of Meeting in related meeting.
(4) E - mail
The E-mail with a receipt request addressed of Project Manager for each party is to be used for
the correspondence between Company and Contractor.
However, E-mail communication is not considered as an officially or contractually recognized
means of communication.
When Contractor need to request any kind of contractual concession, Concession Request will
be raised as a separate correspondence. As far as possible, concession request shall be confined
to one subject only. For details, please refer to Concession Request Procedure, Doc. No. 7T04-
PM-00-PC-013.
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 13 of 59
Date : 22 Jul, 2014
All correspondences in above 2.2.2 shall bear the Project name, correspondence number, date of issue,
addressor, addressee and subject.
All correspondences shall be identified by the following numbering system.
Typical Example
1 = Letter
2 = From : ERC
3 = To : EPC Contractor
4 = Serial Number
Typical Example
1 = Letter
2 = From : PMC
3 = To : EPC Contractor
4 = Serial Number
Typical Example
1 = Letter
2 = From : GS(H) - GS Seoul office
GS(S) - GS Site office
3 = To : Company
4 = Serial Number
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 14 of 59
Date : 22 Jul, 2014
(2) The other correspondence except Letter between Company and Contractor
Example
GH - EZ - T - 0001
4) Serial Number
3) Kind of Correspondence
2) Receiver
1) Sender
Codes of addressor are composed of each two letters, namely company code and office
code.
Company code
- Company (ERC) :E
- Contractor :G (GS E & C) and M (MITSUI)
- WorleyParsons (PMC) :P
With regard to the execution of the Contract, GS E&C will act as the consortium
leader while MITSUI & Co., Ltd. will act as a consortium member. Primarily all the
correspondences to the GS Consortium should be addressed to the representative of
GS E&C.
- Licensor (Axens) :A
- Licensor (BHTS) :B
- Licensor (Tecnimont KT) :K
Office code
- Seoul Office :H
- Site Office (Mostorod) :S
- Cairo Office :Z
- France Office :F
- USA Office :U
- Japan Office :J
- Italy Office :I
2) Addressee (Receiver)
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 15 of 59
Date : 22 Jul, 2014
- Letter : L
- Telefax : F
- Document Transmittal : T
- Telephone Conversation : C
- E-mail : M
- Technical Query : Q
- Concession Request : R
For Example;
The numbering system for letter from Contractor’s Seoul office to the Axens’ France office of
this Project will be coded as GH-AF-L-0001, and the twentieth vendor print document
transmittal from Contractor’s Seoul office to Company’s Cairo office will be coded as GH-EZ-
T-VP-0020.
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 16 of 59
Date : 22 Jul, 2014
2.3 MEETING
Meeting shall be called whenever it is necessary for compliance with agreed contractual
obligations or as a special method of resolving a particular matter.
Meeting shall be convened by the Company or Contractor who shall invite all people concerned
with the subject matter and proposed agenda of the meeting. Unless otherwise specified in the
Contract, it shall notify them of the date, time, probable duration, place and the objective of the
meeting as early as possible, but at least two (2) days prior to the meeting.
The invitation shall, whenever possible, be in writing and shall be accompanied by an agenda
and any necessary background information not yet in the attendees’ possession to enable proper
decisions to be made.
It is the responsibility of Contractor, to assign capable person to prepare the MOM. The
Contractor shall appoint a member of Contractor staff to record and prepare the official Minutes
of Meeting within 2 working days of the meeting and submit for Company’s comments. The
Minutes of Meeting shall be limited to the proceedings of one meeting. They shall be typed. The
record shall be of statements and/or decisions made rather than the detail of comments
exchanged and shall clearly indicate;
If any participant(s) attend only part of a meeting, this fact shall be made clear in the minutes.
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 17 of 59
Date : 22 Jul, 2014
A meeting extending over several days on the same subject may be recorded in one set of minutes,
provided that the dates, the participants, and all other pertinent information are recorded.
Contractor shall prepare draft minutes of meeting within 2 working days of the meeting and
submit for Company’s comments.
Contractor shall prepare the final minutes within a day after receipt of Company’s comments
and secure signature of appropriate Company representative.
In the case of Meeting held at regular intervals, such as Monthly Progress Meeting, the Minutes
of the previous meeting shall be signed as a true record before the next meeting commences.
1) Discipline Code
Code Discipline
AR Architectural
CI Civil
ST Structural
CM Commissioning, Pre-Commissioning, etc.
CS Construction, Fabrication, Erection, etc.
EL Electrical
FF Fire Fighting
HV HVAC
GM GS India
IN Instruments
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 18 of 59
Date : 22 Jul, 2014
2) Location Code
- Seoul Office : H
- Site Office (Mostorod) : S
- Cairo Office : Z
- France Office : F
- USA Office : U
- Japan Office : J
- Italy Office : I
Meeting at which Company is not present but features in the distribution of the minutes (e.g. Meeting
with vendors or sub-contractors) may be numbered in accordance with Contractor’s in-house
procedures.
All Minutes of Meeting with Vendors and Subcontractors except what include commercial matter shall
be shared with Company.
At the Monthly Progress Meeting, progress during the previous month shall be discussed
together with plans for the next month. The agenda shall cover problem areas and discussion of
action plans to overcome or avoid difficulties.
Weekly Construction Meeting shall start at Site from the time the Contractor’s first personnel
move to Site. At the weekly construction Meeting, the relevant statistics, progress and HSE
performance of sub-contractors shall be covered. Discussion of the Contractor’s monthly report
shall be included in the agenda of the monthly meeting.
Contractor shall advise Company prior to making any contact with regulatory authorities. Company
will determine the extent to which it wishes to participate in discussions with such regulatory
authorities. Following the first meeting in which Company participates, and when routine discussions
are involved, Contractor shall undertake subsequent contacts, subject to Review. However, Contractor
shall record minutes of all such Meeting, and will forward a copy of these minutes to Company within
three (3) days of such meeting.
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 20 of 59
Date : 22 Jul, 2014
3.1 GENERAL
This is to describe the controls of the preparation, submission, distribution, change and filing of the
project documents.
3.2.1 Any drawings and documents issued by Contractor shall be clearly marked in the description block on
the document with one of the following purpose and issued according to Appendix #5 “Document
Distribution”
- For Approval
- For Comment
- For Information
- For Design
- For Execution
- For Construction
- Revised as Noted
- As-built
- For Inquiry
- For Purchase
The status above will be applied to case by case for the type and kind of drawings and documents.
“Issued for Construction” can be used after the relevant document are reviewed/approved with or
without comments by Company.
The Contractor will submit to Company deliverables, documents and drawings, for approval, comment
and/or information in accordance with the classification in Exhibit 29. The number of copy shall be
submitted as follows:
When the same documents and drawings are returned by Company, those documents and drawings
shall be coded as follows:
- Code 1 : Approved without comments Contractor to submit finals
- Code 2 : Comments as noted and resubmit finals. Work may proceed subject to compliance with
and incorporation of comments
- Code 3 : Comments as noted and Contractor to amend and resubmit. Work may proceed subject to
compliance with and incorporation of comments
- Code 4 : To resubmit, Contractor to revise and resubmit to Company for further review
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 21 of 59
Date : 22 Jul, 2014
All documentation, before their submission to Company, shall be checked and approved, within
Contractor’s Organization according to the QA System.
All documents shall be maintained in the gWorks and accessible to Company for easy reference and
retrieval.
Comment on all engineering documents as specified in Exhibit 29 Documents for Approval, Comment
or Information in Contract shall be reached Contractor within fourteen (14) calendar days after
Company has received the relevant documents. Otherwise, those documents shall be deemed to be
approved by Company.
All documents, stated in Exhibit 29 Documents for Approval, Comment or Information in Contract,
issued to Company shall be forwarded with a transmittal, and both the transmittal and the document
attached to it shall state the action to be taken, such as:
Company reserves the right to approve and comment on transmitted documents prepared by
Contractor.
Company firstly informs Contractor his comments by fax or E-mail, if any and returns one copy
with its comments or approval. During this approval period the Contractor shall not proceed
with next step of design, engineering or issue documents for fabrication or for construction.
The category 1 document or drawing can be issued with the purpose of “For Construction” only
after clearing any Company comments and getting approval with code 1 “Approved without
comments” from Company. However, Contractor is allowed to issue the deliverable with a
limited number of hold items upon the acceptance by Company before issue.
Company reserves the right to review and comment on the documents prepared by Contractor
and returns one copy of such documents with its comments.
Contractor will incorporate Company's comments into its next step of design, engineering or
documents for fabrication or for construction, when any comments made by Company assisting
Contractor's work shall be reached Contractor.
The Contractor shall submit documents and drawings in time to the Company for its reference
including all technical meeting notes, clarification with Vendors and their replies. Company
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 22 of 59
Date : 22 Jul, 2014
When Contractor communicate with Licensor for their review / comment, it shall be shared with
Company.
All transmittals will be issued and circulated as the work flow chart given below.
Transmittal Issue to
- Company/PMC/Licensor & the Distribute the copy of transmittal and
related discipline of Contractor Hardcopy to the related discipline of
(By GS DCT) Contractor (By GS DCT)
“Internal” revisions are only applicable until externally releasing the next revision
document.
For Example;
The first and second internal revision numbers with existing externally issued
revision number 1 document are 1A and 1B.
The changes shall be indicated on a document as a revision letter code enclosed with
cloud marks or color mark / strike-out. When new issue of any documents with new
revision is required, the previous changes indicated on a document shall be erased
and new changes shall be identified with next revision letter code. In addition to the
revision code, the revision date and the reason of the distribution with initials of
originator and checker shall be described in a revision box. One of the following
standard terms can be used in the “Description” column of the revision box;
- For Approval
- For Comment
- For Information
- For Design
- For Execution
- For Construction
- Revised as Noted
- As-built
- For Inquiry
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 24 of 59
Date : 22 Jul, 2014
- For Purchase
- Principally, Contractor will assign Rev. 0 for first submittal of all categories
(Categories 1, 2 and 3 – Exhibit 29) for issuance of documents to the Company.
- When the category 1, 2 &3 documents are issued at first, a numeric revision
indicator starts with Revision 0. The revision indicator will be incremented by 1,
Revision 2, 3, 4, etc, till those documents are assigned with Company Code-1 or
2 or 3 regardless of their categories.
If the category 1,2 &3 documents are assigned with Company Code-2 or 3, the
updated document shall be issued with the revision indicator 10. After that, if
the same document is still subject to Company Code-2 or 3, the revision
indicator will be incremented by 1, the revision 11, 12, 13 etc.
- The documents like Layout drawings and calculation sheets, etc closely related
with the construction activities shall be issued again with the revision indicator
C0 and the revision description “Issued for Construction”, even though any
comment is not given by Company and/or any revision does not occur after the
first issuance to Company. This issuance is required to make sure that
construction work may proceed.
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 25 of 59
Date : 22 Jul, 2014
When new issue of any documents with new revision is required, the previous
changes indicated on a document shall be erased and new changes shall be identified
with next revision letter code.
The data in revision box will be made on next column of previous revision records.
In addition to the revision letter code, the revision date and reason of the distribution
with initials of originator, checker and approver shall be described in a revision box.
One of the following standard terms can be used in the “Description” column of the
revision box;
- For Approval
- For Comment
- For Information
- For Design
- For Execution
- For Construction
- Revised as Noted
- As-built
- For Inquiry
- For Purchase
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 26 of 59
Date : 22 Jul, 2014
“External” revision shall be issued and distributed and recorded by document controller
according to document distribution matrix.
When a drawing or documents is revised and issued, the proceeding drawing and
document shall be marked in red on a document or title block with one of following
remark;
The obsolete and revised document shall be removed from working area and filed under
following heading;
Contractor shall maintain up-to-date indexes of all drawings and documents issued to
Owner.
A sample of drawing title block applied to the PROJECT is shown in the Appendix #4.
6) Drawings and documents prepared by Contractor for the PROJECT shall not be used for
any other purposes or disclosed to others without written permission of Contractor.
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 27 of 59
Date : 22 Jul, 2014
3.4.2 Upon receipt of Vendor documents by Document Control Team (DCT), Vendor documents are
registered with detailed following information in the gWorks.
(1) As soon as Vendor documents administration (by DCT) is finished as described under para.
3.4.1 and 3.4.2 above, the “Work Flow Sheet” is established with following information in
gWorks ;
1) Project number, discipline and P.O number, sequence number and revision number
2) Number of sheets or books
3) Date of starting routing cycle from DCT
4) Date of ultimate return to DCT, which is maximum three (3) weeks
(2) After routing parties are indicated, the set of vendor document attached with “work flow sheet”
is immediately distributed to the people indicated on the routing cycle through gWorks system,
in order to record the release date and to keep routing cycles under control by originator.
(3) The recipients in workflow check vendor documents and make comment through gWorks.
(4) After all the recipients have marked-up the Vendor documents, the originator collects all
comments from the disciplines concerned and make final commented vendor document with
action code on the “work flow sheet”.
At the same time or after Contractor’s review if the Company has comments on the vendor
documents, these also shall be incorporated in marked-up documents by discipline LE
concerned, which shall be agreed by Project Manager as well as originator.
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 29 of 59
Date : 22 Jul, 2014
19 For Company’s review, four (4) types of vendor document review process are applied as below.
a. Parallel Review – only for the ‘Critical Document’ of the ‘Critical Equipment’ as
specified below. The definition below is only utilized for the purpose of vendor document
review process. Refer to the figure-1 below.
Critical Document
Critical Equipment
1. Air Compressor
2. Boiler Package
3. Coker Furnace
4. Column-1
5. Demineralized Water Package
6. Raw Water Treatment Package
7. Reactor (HCU)
8. Reactor-2 (NHT)
9. Reciprocating Compressor-1
10. Waste Water Treatment
11. Centrifugal Compressor
12. Reactor-1 (DHT)
19
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 30 of 59
Date : 22 Jul, 2014
19
Vendor Document Receipt &
Registration (GS DCT)
Figure-1, Parallel Review – only for the ‘Critical Document’ of the ‘Critical Equipment’
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 31 of 59
Date : 22 Jul, 2014
d. Serial Review – all the rest of documents. Refer to the figure-2 below.
Distribution Instruction
(By Originator)
Review and Comment
(By Licensor)
(5) After completion of routing cycle, the DCT register final commented vendor document and
makes photocopies of the commented Vendor documents and provides the copies of the
document with the stamp for “Instruction” in Para. 3.6 and DCT designates action code on the
stamp on “Instruction” according to originator’s action code indicated on the “work flow sheet”.
In case of Code 1 & 2, Vendor can proceed with manufacturing.
(6) Vendor documents indicating “Instruction” stamp is returned to vendor and sent to Company
simultaneously with the standard “Transmittal”. DCT will register the transmittal no. and the
date of return to vendor in gWorks.
In case of a serial review, only electronic file of final commented vendor document will be
issued to Company unless any other comments are made from other party like Licensor.
(7) Final commented vendor documents will be distributed to design related discipline LE
(8) The original routing documents indicating all the discipline LE comments attached with “work
flow sheet” shall be filled in the relevant filling cabinets, which can be retrieved by P/O No.
(9) The vendor documents shall be returned by Company/Licensor within fourteen (14) days after
receipt of those documents. If the relevant vendor documents are not returned to the Contract
within the period specified above, it shall be considered that the vendor documents are accepted
without the comments by Company/Licensor.
19
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 34 of 59
Date : 22 Jul, 2014
For details, please refer to tentatively named ‘Final Documentation Procedure’ which to be submitted
separate procedure.
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 35 of 59
Date : 22 Jul, 2014
4. PROJECT REPORTING
4.1 INTRODUCTION
The project reporting is intended to present Company a concise progress and important features of the
Contractor's work for the project in uniform and consistent manner, and will also be utilized for
smooth execution of the project.
The reporting documents will consist of the following reports on the Contractor's work which will be
submitted to the Company periodically or on appropriate time.
(1) Date to be submitted : On eight (8) Day of each month as per the Contract
- Project Summary Report including executive summary, safety statistics, overall progress,
progress S curve, major milestone status, summary of project schedule, analysis including
proposed recovery where delay identified, overall project master schedule (level 1),
summary of PSR & MDR, subcontract registers (1 table each), summary histrogram,
planned & actual values, critical path with analysis and area of concern & proposed /
recommended actions
- Engineering Details including progress, summary of deliverable submission and approval
status and engineering document deliverable register.
- Procurement Service including progress, summary of purchasing status and PSR
- Manufacturing and Delivery including progress, MDR and expediting report
- Subcontracting Service including progress, subcontracting service status and subcontracting
service control log
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 37 of 59
Date : 22 Jul, 2014
(1) Date to be submitted: Within thirty (30) calendar days after final inspection and tests
(2) This report will consist of detail inspection report, inspection acceptance report and vendor's
inspection report with the following information.
Project Management
Project Master Schedule
Detailed Schedule
Project Execution Plan
Project Communications & Coordination Procedure
Invoice Procedure
Change Order Procedure
Planning & Schedule Control Procedure
Progress Measurement Procedure
Final Documentation Procedure
Asset Register
Project Close-out Report
Design Books
Safe Plan and Manual
Quality Control Manuals
Monthly Progress Report
Weekly Progress Report
Claims for Additional Payments Procedure
Spare Parts Control Procedure
Concession Request Procedure
Engineering General
Engineering Procedure
Engineering QC Procedure
Engineering Inter-Discipline Check Procedure
Standard Vendor Document Requirement
Design Change Control Procedure
3D Model Requirement
Engineering Coordination Procedure Between GS E&C and Design Partners
Specification for Criticality System
HAZOP Report
Process
Battery Limit Condition Summary
Catalyst and Chemical Summary
Cause and Effect Chart
Design Basis / Criteria
Environmental Specification
Equipment List
Instrument (In-Line) Data Sheet and Calculation
Mass and Heat Balance
Material Selection Diagram
Operating and Maintenance Manual
Operating Philosophy and Procedures
Overpressure Philosophy and Flare System Design
Process Control Philosophy
Process Datasheet
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 39 of 59
Date : 22 Jul, 2014
Process Description
Process Flow Diagram
Process Piping and Instrument Diagram
Process Specification
Psv Load Calculation
Relief Load Summary
Utility Flow Diagram
Utility Piping and Instrument Diagram
Utility Summary
Material Requisitions
Technical Bid Evaluation
Laboratory Equipment Studies
Stationary
Engineering Enquiry Drawing
Mechanical Data Sheets
Mechanical Specification and Procedure
Material Requisitions
Technical Bid Evaluation
Rotating
Mechanical Specification and Procedure
Mechanical Data Sheets
Material Requisitions
Technical Bid Evaluation
Piping
3D Modeling
General Arrangement Drawing
Isometric Drawing (A/G)
Isometric Drawing (U/G)
Key Plan For Overall Plot Plan
Line Index
Material Purchasing Specification
Material Take Off
Overall Plot Plan
Overall Site Plan
Piping As Built
Piping Information
Piping Material Specification
Piping Routing Study
Piping Special Item List
Piping Specification and Procedure
Piping Standard
Piping Stress Analysis Report
Piping Stress Calculation
Piping Typical Drawing
Plot Plan and Equipment Layout
Special Support Drawing
Steam Tracing Schedule
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 40 of 59
Date : 22 Jul, 2014
Electrical
BOM
Cable Connection Schedule
Cable Trench Layout
Calculation / Study-1 (Short Circuit)
Calculation / Study-2 (Load Flow)
Calculation / Study-3 (Motor Starting)
Calculation / Study-4 (Relay Coordination)
Calculation / Study-5 (Cable Sizing)
Calculation / Study-6 (Lighting)
Calculation / Study-7 (Earthing Resistance)
Cathodic Protection
Datasheet
Electrical Cable Schedule-1
Electrical Cable Schedule-2 (Drum)
Electrical Earthing Philosophy Diagram
Electrical Heat Tracing Layout
Electrical Load Summary
Electrical Specification and Procedure
Project Execution Plan
Elementary Diagram
Fire Alarm Layout
Hardware Configuration Diagram
Hazardous Area Classification
IPCS / LMS / IO LISTS
Lighting Fixture Schedule
Lighting Panel Board
Motor List
Power Layout
Project Specification For Telecommunication
Single Line Diagram
Substation Equipment Layout
Symbol and Legend
Telecommunication Layout
Typical Installation Detail
Typical Protection Drawings
Material Requisitions
Technical Bid Evaluation
Instrument
BOM
Cable Tray Layout
Control Room Layout
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 41 of 59
Date : 22 Jul, 2014
Architecture
Building Foundation
Building Plan
Building Specification
Design Drawing
Material Requisitions
Technical Bid Evaluation
Civil
Cable Trench Drawing
Civil Standards
Concrete Structure
Design and Construction Specification For Civil
Dike Detail Drawing
Equipment Foundation Drawing
Foundation Location Plan
General Layout
Miscellaneous Foundations Drawing
Pile Location Plan
Pipe Rack Foundation Drawing
Pipe Sleeper / Support Foundation Drawing
Platform Foundation Drawing
Road & Paving Drawing
Structure Foundation Drawing
Sump, Basin, Manhole Drawing
Underground Plan
Material Requisitions
Technical Bid Evaluation
Structure
BOM
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 42 of 59
Date : 22 Jul, 2014
Environmental Engineering
Air Dispersion Modeling Report
Environmental Specification
Noise Study Reprot
Fire Fighting
Cause and Effect Matrix
Datasheet
Fighting & Safety Equipment Layout
Fire & Gas Equipment Layout
Fire Alarm Block Diagram
Fire Fighting Piping and Instrument Diagram
Fire Protection Philosophy
Material Requisitions
Technical Bid Evaluation
HVAC
Design Load Calculation
HVAC Control Cable Plan / Layout
HVAC Control System Logic Diagram
HVAC Piping and Instrument Diagram
HVAC Plan / Layout
HVAC Plumbing Plan / Layout
HVAC Standard Drawing
Project Specification For HVAC System
Material Requisitions
Technical Bid Evaluation
Process Safety
Hazardous Area Classification
HAZOP Report
Lighting Panel Board
Passive Fire Protection Diagram
QRA Report
SIL Classification Report
SIL Study Procedure
SIL Verification Report
Procurement
Procurement Procedure
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 43 of 59
Date : 22 Jul, 2014
Packing Instruction
Transportation Procedure
Procurement Status Report
Expediting Reports
Inspection Status Report
Unpriced Copy of Purchase Order
Inspection Release Reports (for Shipping)
Shipping Status Report
Copy of Bill of Lading
Construction
Risk Assessment in CORC
Project Environmental Protection Plan
Subcontracting Plan and Procedure
Coordination Procedure For Construction Work
Temporary Facilities Plan
Environmental Aspects and Impacts Control AT Site
Construction Procedure For Field Pressure Testing Of Piping
Construction Procedure For Carbon Steel Piping
Construction Procedure For Piping Construction Works
Construction Procedure for Coating & Wrapping of UG Piping
Construction Procedure For Alloy Steel Piping
Construction Procedure For Cleaning Of Piping
Construction Procedure For Piping Prefabrication
Construction Procedure For Socket and Seal Welding Small Piping Component
Method Statement For Topographic Surveying Works
Method Statement For Soil Investigation Works
Field Material Control Procedure
Constructability Program
Rigging Procedure
Project Specification For Painting
Project Specification For Hot Insulation
Project Specification For Pipe Welding and Welding Inspection
Construction Specification For Cold Insulation
Specification For Piling Works
Specification For Road & Area Paving
Specification For Drainage and Sewers
Project Specification For Structural Steel Fabrication and Erection
Specification For Earth Work
Specification For Concrete
HSE Plan for Soil Investigation Works
Topographic Survey Work Report
QA/HSE
Project Quality Plan
Project Quality Audit Program and Scheduling Procedure
Shop Inspection and Test Plan
PMI Procedure
Field QA QC Procedure
Procedure Of Inspection, Measuring & Test Equipment Control
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 44 of 59
Date : 22 Jul, 2014
NCR Procedure
Corrective and Preventive Action Procedure
Project HSE Plan
Project Quality Audit Plan
Note – Mechanical Data sheets and TBEs for the major/critical equipment and materials below to be Category 1
with others Category 2.
Rotating Equipment
1. Compressors
a. Centrifugal Compressors:
K-1201, 1502& 2201
b. Reciprocating Compressors:
K-1101 A/B, 1202 A/B, 1401 A/B, 1402 A/B,1501 A/B/C,K-1301 A/B, 1302 A/B&1303 A/B
c. Screw Compressor
K-3501 A/B/C& X-2102-P1/P2
2. Pumps
a. Speed over 3600 rpm:
All Sundyne Pumps
b. Temp over 225 degree C:
P-1502 A/B, 2103 A/B, 2104 A/B, 2105 AQ/B, 2106 A/B, 1204 A/B, 1205 A/B, 1404 A/B, 1511 A/B,
1512 A/B, 1513 A/B, 1514 A/B, 2202 A/B, 2204 A/B, 2218 A/B, 2201 A/B, 2203 A/B&2217 A/B
c. Pressure over 180 bar:
P- 2214 & P-1501 A/B
d. Multi Stage Pumps:
P-1401 A/B, 1504 A/B,1521 A/B, 1501 A/B,1502 A/B& P-2214 (Covered also above under points b&
c), P-1101 A/B, 1405 A/B, 2101 A/B, 2102 A/B, 2709 A/B, 3303 A/B, 2103 A/B, 2104 A/B&2106 A/B
(Covered also under point b)
e. Cooling Water Pumps:
P-3201 A/B/C/D
3. Others:
a. Coker Bridge Crane
b. Coker Handling System
Static Equipment
1. Reactors (HCU) (7T04-ME-00-RQ-001)
2. Coke Drums (7T04-ME-22-RQ-001)
3. Column – 1 (7T04-ME-00-RQ-003)
4. HP Heat Exchangers (7T04-ME-15-RQ-002)
5. Automated Unheading Valve (7T04-ME-22-RQ-011)
6. Reactors – 2 (Axens) (7T04-ME-11-RQ-001)
7. Reactors – 3 (Axens) (7T04-ME-00-RQ-010)
8. HP Vessels (7T04-ME-15-RQ-001)
9. Spherical Tanks (7T04-ME-51-RQ-002)
10. Packinox Heat Exchanger (7T04-ME-12-RQ-001)
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 45 of 59
Date : 22 Jul, 2014
1. Letter or Facsimile
2. Transmittal
3. Notes of Meeting
4. Technical Query
5. Concession Request
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 48 of 59
Date : 22 Jul, 2014
Sample
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 49 of 59
Date : 22 Jul, 2014
Sample
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 50 of 59
Date : 22 Jul, 2014
Sample
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 51 of 59
Date : 22 Jul, 2014
Sample
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 52 of 59
Date : 22 Jul, 2014
Sample
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 53 of 59
Date : 22 Jul, 2014
Sample
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 54 of 59
Date : 22 Jul, 2014
Sample
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 55 of 59
Date : 22 Jul, 2014
Sample
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 56 of 59
Date : 22 Jul, 2014
SEOUL, KOREA
Name of Drawing
Please refer to the attachment #1 (Document Distribution Matrix) as a sample. As DDM is a live document, it
will be updated whenever there is a change in the organization and maintained with its own revision tracking
separately from Project Communication & Coordination Procedure.
Doc No : 7T04-PM-00-PC-002
PROJECT COMMUNICATION & Rev. : 19
COORDINATION PROCEDURE Page : 58 of 59
Date : 22 Jul, 2014
Project Quality
Manager
Project
Coordination
Manager
Inspection
Contract
Manager Area’s Senior Discipline Eng’g Manager(PIM)
Project LEs
Engineers (SPE)
Doc No : 7T04-PM-00-PC-002
Rev. : 19
PROJECT COMMUNICATION & COORDINATION PROCEDURE Page : 59 of 59
Date : 22 Jul, 2013