For Jethmah Water Fields with 1.

02 MWp Capacity
Sayoun - Hadhramout
Bid No.: IUS-AF-UWS-SAY-001
BOQ:
Item Unit Price Total Price
Item Details Unit Qty.
No. [USD] [USD]
Bill: 1 # ELECTRICAL WORKS
1 Solar PV Module:
Supply, install, test, and commissioning of solar PV modules, the capacity is not less than 625W
should be comprising of either mono-crystalline or polycrystalline;
- Conformity with CE and IEC 61215, IEC 61730 or equivalent standards;
- Conversion efficiency should be not less than 20 % under STC;
- The PV module shall perform satisfactorily in temperature between – 40 oC to +85 oC;
- The rated output power of any supplied module shall have tolerance of 0~5 W; Pcs 2016 --
- The module shall be provided with a junction box with at less IP67;
- The supplied module DC voltage should be not less than 1000 VDC;
- PID resistance .

2 Solar Inverter
Supply, install, test, and commissioning of three phases pure sine solar inverter meet the follwoing
specifications:
- Input DC open circuit voltage not less than 1000 V;
- Maximum input DC power shall not less than 150 KWp;
- Lower level of MPP voltage shall not greather than 590 V;
- Upper level of MPP voltage shall not less than 1000 V;
- Maximum input current shall not less than 180 A;
- Rated output AC Power shall not less than 100 KW;
- Nominal AC voltage and frequency shall be 400 V / 50 Hz;
Pcs 9 --
- Maximum efficiency shall be not less tham 97.5% ;
- Shall be certified to meet CE and UL marking and complaint with IEC 62109;
- Degree of protection shall not less than IP65;
- Protections required: AC overload , short circuit, overvoltage and overheating;
- Shall allow internet connection for remote monitoring;

3 DC Combiner Box (DCCB)


Supply, install, test, and commissioning of DC Combiner Box
- Not less than 22 inputs, 1 output DC Combiner Box;
- The DCCB to be provided for termination of connecting cables.
- Suitable for outdoor installation, IP67 , waterproof and anti dust;
- All wires/cables must be terminated through cable lugs;
- DC fuse rating for each string:1000V,not exceed 25 A; Pcs 9 --
- Built in DC circuit breaker or DC load isolation switch;
- Built in surge protection device;
- Product warranty shall be 2 years.

4 DC Cabling
Conductor :-Soft annealed tin-coated flexible stranded copper per ASTM B-33 and EN 60228 , TUV
certified, Insulation:-Halogen-free, thermoset polyolefin specifically designed for maximum
flexibility, and Jacket :- Black/Red, low smoke non-halogenated, flame retardant, oil, abrasion,
chemical and sunlight resistant cross-linked compound meeting UL 44, UL 854.
- All cables shall be marked properly according to approved design so that cable can be easily traced
and identified;
Cable ends connections are to be made through suitable lugs or terminals, crimped properly & with
use of cable glands; Note
This item is including the cables , cable trays and cable trenches, as site required.
Cable Tray :-Perforated type Galvanized steel cable trays, cable tray covers, clamping bolts and other
cable tray
accessories such as coupler plates, bends, tees, reducers, vertical elbows in manufactured accordance
with ASTM A653 SS, Grade 33, coating designation G90.

4.1 Cable between PV module strings and Combiner box: 1.5kV (1C*10 sqr.mm) (Red& Black) L.m 12,168 --
4.2 Cable between combiner boxes and solar inverters 1.5kV(1C*185 sqr.mm) (Red& Black) L.m 1,046 --
5 AC Cabling
Supply, install, test, and commissioning of AC Cabling Stranded type, double insulationg material
XPLE/PVC/CU
- All cables shall be marked properly according to approved design so that cable can be easily traced
and identified;
- All outdoor exposed wiring to be protected from UV radiation and physical damage, all cabling
above ground should be suitably mounted inside cable trays with proper covers;
- XLPE insulated and PVC seathed single or multi core flexible copper cables meeting IEC 60227 and Note
IEC 60502 or equivalent;
- Cable ends connections are to be made through suitable lugs or terminals, crimped properly & with
use of cable glands;
This item is including the cables , cable trays and cable trenches, as site required.

5.1 4C*150 sqr.mm 1kV include remove tiles and excavation trench as per site condition L.m 90 --
5.2 1C*630 sqr.mm 1kV include remove tiles and excavation trench as per site condition L.m 760 --
5.3 3C*50 sqr.mm 11kV include remove tiles and excavation trench as per site condition L.m 100 --
6 Earthing Sysem
Supply, install, test and commissioning Earthing System as per technical specifications and drawings
including cabling, cable lugs, earthing rods and all required acccessorries
- Each array structure of the PV modules should be grounded properly;
- All metal casing/shielding of the system and its components should be thoroughly grounded;
-Earthing pit
- Earth resistance should be tested by calibrated earth tester, the earth resistance should not be more
than 5 Ohm. system 42 --
- Earthing installation in accordance with the IEE Wiring regulations, BS 7671
- All conductive materials shall be copper.
- The size of conductor shall be according to table 54.7 of IEE – BS 7671 – IEC 60365-5-54. (see
Annexe : 07 & 08).

7 Lightning System
Supply, install, test and commissioning Lightening Protection System As per technical specifications :
- lighting arrester shall be copper.
- All metal casing/shielding of the system and its components should be thoroughly grounded;
-Earthing pit
- Earth resistance should be tested by calibrated earth tester, the earth resistance should not be more
than 5 Ohm.
- Earthing installation in accordance with the IEE Wiring regulations, BS 7671 system 24 --
- All conductive materials shall be copper.
- The size of conductor shall be according to table 54.7 of IEE – BS 7671 – IEC 60365-5-54. (see
Annexe : 08 ).

8 Control & Monitoring System


Contractor is responsible for providing a proposal for the location of control and monitoring
equipment with layout of the control cables as required by the proposed topology and manufacturers, Note
and responsible for installation of such network.
8.1 Data Manager
Supply, install, test and commission of Data Manager for monitoring and controlling solution as per
technical specifications :
- Shall include all required Switches/ Hubs, connectors, adapters, fittings, accessories, connections and
configurations.
- All measurements are to be logged locally, and available from a remote location through an internet
connection.
- The Data Manager shall support PV inverters, Hybrid Controller, energy meters, I/O systems, sensor
modules, weather stations, charging stations up to the maximum nominal system power Data. LS 1 --
- The monitoring shall cover all devices status, PV power (current, historical), and generators power
values.
- Product warranty shall be 5 years.

8.2 Hybrid Controller


Supply, install, test and commission of hybrid controller complete system with all accessories as per
technical specifications :
- Should be provided to manage energy production from the solar inverters to preserve grid stability
during Diesel Generators operation and guarantee a minimum loading factor on the generators.
- MODBUS communication should be used, or any other equivalent configurations .
- The controller should also be able to actively control the reactive power output from the PV inverters
to keep the DG running in its optimal power factor range.
- The controller is to be avoide exporting PV Power to the public grid when the Facility is powered.
- All operating parameters from the controller should be fully logged in the dedicated logger It should
be placed in a protected enclosure. It should be protected from surges and power fluctuations.
- Shall provide zero export controller to avoide exporting power to the public gride. LS 1 --
- Shall provide Uninterrupted Power Supply system .
- Includes all required accessories as wirring and holding materials.
- Product warranty shall be 5 years.

9 CCTV System
Supply, install, test and commission of CCTV system as per technical specifications :
- Contractor shall provide it with whole required data as specification and drawing.
- Shall include all required Switches/ Hubs, connectors, adapters, fittings, accessories, connections and
configurations.
- Should be controlled locally, and available from a remote location through an internet connection.
- A Combination of speed dome cameras (D1 resolutions, min. 36x optical zoom) and fixed IP
cameras (min 29 x optical zoom) to protect continuously the perimeter of the fence when no activities
on the Buses. LS 1 --
- 30 days recording memory of all images on which motion has been detected.
- Camera monitoring screen to be installed in the control room and switchgear room , it has to be
monitored at the same time.

10 Transforming system
Supply, install, test and commissioning of Setp-Up Transformer , which shall be sutiable to use with
solar energy as these specifications : 1250KVA, 0.415/11kv, ONAN, Off LTC, (±3×2.5%), 50HZ,
3phase distribution transformer with copper winding. The transformer should be suitable to be used
together with solar energy. The transformer should be provided with cable boxes on both 11KV &
10.1 0.415KV sides cables box on low voltage side should be suitable to receive cables as per drawings. Pcs 1 --
Conformity with CE and IEC 60076,BS148,BS 171 or equivalent standards;

11 TOTALIZER BOARD
Supply, install, test and commissioning of distribution board, (TOTALIZER BOARD) should be
suitable to accommodate:
- Rated Busbar Current : not less than 2500A.
- Sutibale to recive at less 12 feeders
- Main Breaker: 2000A, 4 poles circuit breaker Adjustable Setting Tp .
- 9 RCBOs : 200A,4 poles circuit breaker with differential device
- 1 MCCB : 40A,4 poles circuit breaker
- 1 MCB : 16A,2 poles circuit breaker
- Indoor PVDB with protection not less than IP55
11.1 - Rated voltage not less than 1000 V AC Pcs 1 --
- Rated frequency 50Hz
- The dimensions should be according to latest issue IEC & BS standardsfor size.
- Breaking capacity at all rated current is not less than 120 KA.
- Limits of time current characteristics according to latest issue IEC & BS standards.
- Cut-off current characteristics according to latest issue IEC & BS standards.
- It characteristics according to latest issue IEC & BS standards.

12 Automatic Transfer Switch


Supply, install, test and commissioning , meduim voltage automatic transfer switch (ATS) 2000KVA -
11KV , as per technical specifications :
- RATED VOLTAGE : 12KV
- SERVICE VOLTAGE : 11 KV
- SHORT CIRCUIT LEVEL : 31.5 KAmp. Pcs 1 --
- DEGREE OF PROTECTION : not less than IP 42
- RATED POWER FREQUENCY WITHSTAND VOLTAGE ( 1 min ) : 28KV
-AUXILIARY CONTACT SUTIBLE FOR 24VDC

13 Weather Station
Supply, install, test and commission of weather station for Solar system compatible with Data
Manager and Controller, includes all sensors required to monitor the Solar PV Plant, Irradiance
Sensor, Humidity and Ambient Temperature Sensors,.etc , as per technical specifications :
- Two Pyranometer must be included one horizontal and second tilted, with measurement range
0~2000W/m
- Wind speed sensor shall has a measurement range not less than 0 ~ 70 m/s and starting wind speed
not less than 0.3 m/s
- A pair of wind direction shall have measurement range not less than 0 ~ 360 deg and starting wind Pcs 1 --
speed not less than 0.5 m/s
- Environment and PV module temperature sensor shall have measurement range not less than -50 ~
+100 C .

14 Ventilation and ligthing System


Supply, install, test and commissioning ventilation and lighting system for transformer & control
14.1 rooms which is include electrical wiring requirements and civil work per drawing . Pcs 1 --

Supply, install, test and commissioning ligthing System as per technical specifications :
-It shall be All in One Solar Street Light.
- 3 lighting modes with PIR motion sensor.
- Lumens not less than 10000lm.
- Protection not less than IP 65.
- Discharging temperature -20℃~60℃
14.2 - Charging temperature 0℃~55℃ Pcs 4 --
- Switch light sensor ≥50 Lux, OFF. ≤10 Lux, ON.
- Power Li-ion battery, support 1500 cycles

Exhaust Air Fan:


Supply, install, test and commission exhaust air fans, window /wall mounted, 230 volts, 50 Hz, fan
shall include self opening and closing shutters. Work shall include, but is not limited to: opening the
glass of the window, any required materials or fabrication to fix the fan, installation of electrical
switch, 2 x 1.5 +1.5 mm cable, conduits, civil works, terminations and all materials required to
14.3 complete the job, fan shall be connected to the nearest electrical point installation shall be done Pcs 3
according to high prevailing engineering standards and instruction of project engineer.
EXA- 1500 CFM

15 Trenches
"Excavation (in all types of soil, tiles , concrete,stone, Asphalt and Asphalt pavement, etc) and backfill
of cable trench with cross section size of 90cm depth and 80cm width including all required civil
works as per drawings.
15.1 The items include disposal of surplus excavated materials outside to any unobjectionable place to be LS 194
identified by contractor at his own cost , The item includes reconstruction the top layer with approved
materials to its original condition.

Supply, install, test and commission of Manholes 1mx1m including all required civil works as per
15.2 Pcs 14
drawings
16 Other Components
Supply, install, test and commission of Fire alarm system including all requirements from
16.1 fire resistant cable, trunkeys ,metal conduit pipes , termination, testing and proper labeling note
with complete Diagrams & documentation.
Supply, install, test and commission of one LOOP Addressable Fire alarm system panel
including all requirements from fire resistant cable, trunkeys ,pipes, termination, testing and
proper labeling with complete Diagrams & documentation.
Technical Specifications:
16.1.1 - 2 LOOP panel No 1
- Each LOOP support to install at least 15 detector.
- 2 sounder circuits
- Include back up battery
- EN54 Approved from LPCB

Supply, install, test and commission of Flame Detector including all required fire resistant
cable
Technical Specifications:
- Operating voltage: 24 VDC nominal (18-32 VDC) - regulated
- Detects hydrocarbon and non-hydrocarbon fuel fires in all environmental conditions
- Alarm Current ≤ 32 mA
16.1.2 - Dual microprocessors for reliable performance No 1
- Sensitivity according to EN 54-10
- Field of view: 90° full 100% core of vision, ± 45° from on axis.
- Sensitivity: Very high, high, medium and low - switch selectable.
- Humidity range: 5 to 98% relative humidity, non-condensing
- Test lamps for manual testing.
- EN54 Approved from LPCB

Supply, install, test and commission of smoke and heat Detector including all required fire resistant
cable
Technical Specifications:
- Operating voltage: 24 VDC nominal (18-32 VDC) - regulated
- Alarm Current ≤ 32 mA
- Dual microprocessors for reliable performance No 9
16.1.3 - Humidity range: 5 to 98% relative humidity, non-condensing
- Test lamps for manual testing.
- EN54 Approved from LPCB

Supply, install, test and commission of Addressable bells(sounders) including all required
fire resistant cable
Technical Specifications: No. 3
16.1.4 - Nominal voltage 9 - 28 Vdc
- Purpose-made weatherproof range.

16.2 Supply, install, test and commissioning 5kg Carbon Dioxide (CO2) Extinguisher Pcs 5 --
16.3 Supply, install, test and commissioning 6kg Powder Extinguisher Pcs 5 --
Supply, install, test and commissioning of Spilt Air Condition inverter type include alternate
operation and temperature control unit and all wiring requirements
- Adjustable fan speed.
- Split unit inverter type.
- Capacity: 24,000 BTU (2 Ton).
- Voltage: 220-240.
- Frequency: 50 Hz.
16.4 - Single phase. Pcs 3 --
- Noise level shall not exceed 45 db.
- Star rating 3 star or above.
- Full inverter versions
- Suitable for wall mounting
- Outdoor unit shall be housed inside metal gage made of mild steel

Supply, install, test and commissioning of LED lighting fixture (20 W) 1200 mm length include its
16.5 Pcs 12 --
switches as per drawing, include all accessories and installation requirement (PVC Pipe, Wiring,…etc.)

Supply, install, test, and commissioning of 13A electrical socket as per drawing, including all
16.6 Pcs 6 --
accessories and installation requirements (PVC Pipe, Wiring,…etc.)
Supply, install, testing and commissionining of Wall mounted exit sign luminaire with 1x8W, led lamp and with
16.8 single sided pictogram including all conductors, conduits, boxes, switches and all related accessories as the pcs 2.0 --
technical specifications and shown on the drawings.

Supply, install, testing and commissionining of wall mounted emergency lighting fixture not less than 90Lm ,not
16.9 less than 9W, LED lamp with 3HRS NI-CD batteries backup including all conductors, conduits, boxes, switches No 4.0 --
and all related accessories as the technical specifications and shown on the drawings

17 Maintenance Tools
Supply, test and commissioning of a Maintenance Tools as per technical specifications include the
following :
- Measuring devices that using for maintaining purpose as: Multi-meter, I-V Curve tracer, earth
resistance tester and Insulation meter.
- Inspection tools as: Infrared Camera (Two IR Cameras should be provided) .
- Two sets of special tools and gauges required for the maintenance of the Plant; Bidder shall sunmit a
detailed list.
17.1 - One set of special lifting and handling appliances required for the maintenance of the Plant. LS 1 --
- The Bidder shall quote his price for tools as specified and recommend any additional tools that may
be required.
- Each tool or appliance is to be clearly marked with its size and/or purpose.
- The tools and appliances supplied shall not be used for erection purposes by the Contractor and shall
be handed over in new condition.

18 System Maintenance
18.1 2 years of preventive maintenance for all facilities. LS 2 --
19 System Training
The contractor will be responsible for providing training course focusing on system operation,
19.1 maintenance and management, the scope of training and schedule shall be proposed by the contractor LS 1 --
and approved by UNOPS engineer.

Sub-Tota: 1 # -
Sayoun - Hadhramout
Bid No.: IUS-AF-UWS-SAY-001
BOQ:
Item Unit Price Total Price
Item Details Unit Qty.
No. [USD] [USD]
Bill: 2 # CIVIL AND STRUCTURAL WORKS
1 Site Preparation
Survey and identify all obstructing components for removal and relocation. Provide protection, temporary utilities, chemical toilets,
scaffolding as required for the implementation of the works and take all measures needed to implement health, safety and security
on site . The item includes removal and relocation of all obstructing components, the planning and implementation for any works
LS 1 --
needed to continue the electricity . It also includes laying a small white stones all around the site to improve the system efficiency
and improve site drainage system

2 Steel Mounting Structure

Steel Mounting Structure:


Supplying, delivering, fabricating and installing, hoisting and fixing in place, including all temporary staging and
supporting work, and making all structural steel work in accordance with shop drawings for columns, beams, purlins,
bracing, brackets, etc. with connections using plates, channels, angles, gusset plate, anchor bolt, cleats, fasteners, etc., hot
galvanized steel (min galvanized 120mic)) with minimum yield strength as specified in the technical specifications The
cost of steel work must include assembling, jointing, and fasteners (nuts, bolts, and washers), among other required
2.1 Note
accessories. The price shall also include all necessary bolts and washers for fastening, including bolt grouting, and all
other requirements to complete the work including materials and labor, at all heights and locations, all in accordance with
the technical specifications, drawings and to the complete satisfaction of supervisor engineer.
Note:
Works shall be in accordance with EC3 std., and all bolts shall be Anti-thief high strength bolts (Grade 8.8), as per the
technical specifications and drawings.

GROUND LEVEL MOUNTING STRUCTURES


The item shall include the following:
• Surveying and conducting all site levelling.
• Supplying, fabricating, delivering at site, hoisting and fixing in position, including all temporary staging and supporting
work and making all structural steel work as per in the shop drawings and technical specifications of mounting
structures.
• Supply and implementation of reinforced concrete C25 for all mountings foundations, including anchor bolts, the
excavation works and all necessary related works according to the shop drawings, technical specifications and the
2.1A instructions of the supervising Engineer. m2 6300 --
• Fabrication and erection in position structural steel sections for base plates, columns, rafters, eaves, bracing, galvanized
purlins and others made out of plates, IPE Sections, L and UPE sections and other structural steel sections complete as
per drawing and as per the direction of supervising engineer in Charge including grouting, cutting, welding, grinding,
drilling, hoisting, fixing in position at all heights and levels. The rate includes all connections nuts, bolts, washer plates,
welds required for fabrication and erection and all necessary related work according to the shop drawings and the
technical specifications.
• Providing and applying a coat of approved zinc chromite primer and two coats of synthetic enamel paint over all as
specified and directed.

3 Control Rooms
Excavation
A-
All excavations are measured net, with no allowance for timbering, blanking or increase in bulk after excavation, nor for
any working space, all of which the Contractor shall include in his Tender price for excavation.

B- Excavation for foundation, trenches, etc. shall be measured from the reduced level not from the existing level when site
leveling is below the natural level and measured from natural ground level not from site leveling when existing leveling is
over natural level.
C- Excavation for foundation of retaining walls has to be measured net according to previous preamble and to be
calculated from the lower reduced level and not from the higher reduced level and from the natural ground level when
this level is lower than the lower reduced level (from both sides).
3.1 General and foundations Excavations:

Carry out general site leveling and foundations excavations of all types, tie beams and underground structures for areas
where needed in all types of soil, concrete and any pavings, the price include demolishing and removing concrete tiles,
concrete slab on grade curbstone crushed stone base course , all asphalt layers , subbase , base course , wearing
course , gabion stone wall and all the layers under it to reach the levels needed according to execution drawings.and
remove materials from site.
The Contractor's unit price shall include excavation to all depths as required and according to the levels and dimensions
in Drawings, support and protection offside of excavation from falls, backfill, compaction,and removal from Site of all
surplus materials, and all necessary plant and its mobilization to and from Site including maintenance and labour. and
the price include back filling with a suitable materials imported from outside the site and at the contractor expense, to
reach the level of subgrade and as specified in special technical specifications with 200 mm thick layers watering and
compacting to 95% of standard Proctor according to the field density test for the suitable fill materials and the removal of
the extra and unsuitable materials.The price include removing the agricultural soil of group classification (A6, A7) and if
the soil of the excavation is not suitable for back filling the contractor must improve the soil by adding selected fill
materials from outside the site without any extra payments, and if the soil of the excavation is not sufficient for back
filling, the contractor must import selected granular fill from outside the site and at the contractor expense, and without
any extra payments.The price of this Section include Making a soil inspection by the contractor after excavation at
extension area and compare the actual optained bearing capacity with the design bearing capacity , the inspection
must be achieved by a specialized and skilled office. The contractor should submitt the results of the inspection to the
UNOPS Engineer officially befor any work.

3.1.1 a- Bulk excavation For site leveling for internal and external works. ( to the bottom of base course level) m3 22
3.1.2 b-For foundation m3 18
3.2 Crushed stone base course:
Supply , lay and compact crushed stone base course, 95 % dry density after compacting of 15 cm . thickness over the
compacted soil for internal works. m2 65
3.4 Build up Control Room completely with supplying all required materials. It covers all civil engineering and building works
required for the construction of control room and the necessary accessories as technical specification and drawing details (see
drawings S007 to S011 ).
Concrete works:
concrete shall be measured net as executed according to Drawings and / or the UNOPS Engineer's instructions, but no deductions
shall be made for the following:
-Volume of steel reinforcement.
- Electrical and mechanical conduits and pipes embedded into concrete.
-Voids not exceeding 0.1 m in area and 0.05 m in volume.
Unit price for concrete as inserted for each Section shall include the following unless otherwise mentioned:
-All labor, materials, and plants necessary to execute the Section as described included all carriage handling, cutting and waste and
all incidental charges and expenses.
-work to all sectional areas and all thickness forming all holes and mortises, chases, grooves chamfers, etc., according to Drawings
or the UNOPS Engineers instructions, dowels, bolts in pipe sleeves, plugs hold fasts, pipes, ducts tucks.
-Forming slopes, falls and the like and leaving surfaces with the proper finish to exposed surfaces, or ready for screeds and paving.
-Forming the necessary construction joints in the normal course of the works including the suitable water stops and other materials
needed.
3.4.1 -All grading, tamping and trawling.
-Curing as specified and as needed.
Protection of concrete surfaces.+
-Form work scaffolding, strutting and propping for all types of concrete unless otherwise mentioned, including materials and
workmanship, supporting regardless of height, design of form work, and all cuttings of forms to profiles and shapes.
-Solid, fair face, waffle and through slab soffits be considered as ordinary form work for which no extra over shall be paid.
-Concrete works in this section are applicable where needed as drawings.
Blinding unit rate shall cover all excavation, removal of debris, and backfilling works costs.
-Slab on grade unit rate shall cover the cost of [Supply , lay and compact crushed stone base course, 95 % dry density after
compacting of 15 cm . thickness over the compacted soil for internal works]

Supply and cast in situ plain concrete under footings (Cube Fc'=20MPa), conformed to ACI-318M codes requirments.
The works include supply and execute:_ Cement (ASTM C 150), Aggregates (ASTM C 33), Clean water, _ Formworks._ Curing.The
3.4.1.A rate includes all material,equipments,labor..etc, and doing every temporary or Permanent necessaries to finish the item as per m2 35
drawings,specifications and instruction of Engineer in charge.

Reinforced Concrete Class'20' for Slabs, FCU= 200 kg/cm2 for ground slabs, on grade internall works, Price shall include all
3.4.1.B required constructions joints. m3 11.25
a- 15 cm thick.
Supply and provide Reinforced concrete , (Fc'=25MPa), conformed to ACI-318M codes requirements.
The works include supply and execute:_ Cement (ASTM C 150), Aggregates (ASTM C 33), Clean water, _ Formworks._ G40
(fy=280Mpa) Deformed steel bars as drawings ._ Curing._ Bituminous insulated layerThe rate includes all material, equipments,
3.4.1.C labor..etc, and doing every temporary or Permanent necessaries to finish the item as per drawings,specifications and instruction of m3 11.5
Engineer in charge.
a) for footings, ground beams,neck columns, walls under S.O.G and where needed.

Supply and provide Reinforced concrete , (Fc'=25MPa), conformed to ACI-318M codes requirements.
The works include supply and execute:_ Cement (ASTM C 150), Aggregates (ASTM C 33), Clean water, _ Formworks._ G40
(fy=280Mpa) Deformed steel bars as drawings ._ Curing._ Bituminous insulated layerThe rate includes all material, equipments,
3.4.1.D labor..etc, and doing every temporary or Permanent necessaries to finish the item as per drawings,specifications and instruction of m3 18
Engineer in charge.
a) for slabs beams ,Lintel beams, above S.O.G , and where needed.

Supply and provide Reinforced concrete , (Fc'=25MPa), conformed to ACI-318M codes requirements.
The works include supply and execute:_ Cement (ASTM C 150), Aggregates (ASTM C 33), Clean water, _ Formworks._ G40
(fy=280Mpa) Deformed steel bars as drawings ._ Curing._ Bituminous insulated layerThe rate includes all material, equipments,
3.4.1.E labor..etc, and doing every temporary or Permanent necessaries to finish the item as per drawings,specifications and instruction of m3 2.85
Engineer in charge.
a) for columns , walls, above S.O.G , and where needed.

Supply and install insulation layer for reinforced concrete roofs.


The works include supply and execute:_ Clean the roofs and repair cracks in concrete using suitable Epoxy materials._ Supply and
install bitumen (2coats) and bitumenous polymer layer (4mm thick)_ Supply and cast in situ (5 cm) avr. thick concrete (cube
Fc'=25 Mpa) as topping inclinde concrete, with good finishing and curing._ Bitumenous expansion joints where needed._ Supply
3.5 and install (7.5cm) dia. PVC pipe downspouts with fittings and strups.where needed.The rate includes all material, accessories, m2 50
equipments,labor..etc, and doing every temporary or Permanent necessaries to finish the item as per standards, specifications and
instruction of Engineer in charge.

Provide and construct automatic-made hollow concrete blocks (20*20*40)cm for room walls. The rate includes all material,
equipments, labor..etc, and doing every temporary or Permanent necessaries to finish the item as per drawings,specifications and
3.6 instruction of Engineer in charge. m2 764

Supply and laying internal plastering for walls and ceiling . The work includes metal meshes, metal edges, plastering composed of
2 coats, a rough bond coat (1cement:1coarse sand), and a finishing coat using cement mortar consist of (1cement : 3sand),The rate
includes all material, equipments, labor..etc, and doing every temporary or Permanent necessaries to finish the item as per
3.7 m2 810
drawings,specifications and instruction of Engineer in charge.
Supply and laying external plastering for external RC elements and parts of walls . The work includes metal meshes, metal edges,
plastering composed of 2 coats, a rough bond coat (1cement:1coarse sand), and a finishing coat using cement mortar consist of
(1cement : 3sand),The rate includes all material, equipments, labor..etc, and doing every temporary or Permanent necessaries to
3.8 finish the item as per drawings,specifications and instruction of Engineer in charge. m2 857

Supply and apply water-based paint for ceiling (2 coats)


The works include supply and install:_ Substrate preparation, cleaning surfaces of dust, dirt, stuck, ... Etc,, priming, puttying 2
faces and polishing.The rate includes all material, equipments, labor, .etc, and doing every temporary or Permanent necessaries to
3.9 m2 46
finish the item as per standards, specifications and instruction of Engineer in charge.

Supply and apply oil paint (High Quality) for internal walls (2 coats).
The works include supply and install:_ Substrate preparation, cleaning surfaces of dust, dirt, stuck, ... Etc,, priming, puttying 2
faces and polishing.The rate includes all material, equipments, labor, .etc, and doing every temporary or Permanent necessaries to
3.10 m2 764
finish the item as per standards, specifications and instruction of Engineer in charge.

Supply and apply weather resistant Paint (High Quality) for external Plaster (2 coats).
The works include supply and install:_ Substrate preparation, cleaning surfaces of dust, dirt, stuck, ... Etc. priming The rate includes
all material, equipments, labor, .etc, and doing every temporary or Permanent necessaries to finish the item as per standards,
3.11 m2 857
specifications and instruction of Engineer in charge.

Supplying and implementing galvanized stacking iron doors, D1 (2.0m*2.2m) of thickness 1.5mm stacking and welding in an
excellent way without lower or upper joints ,The price includes sanding, welding and rust-resistant paint,Three thick sides, then the
3.12 approved external color, provided that the supply and installation takes place according to the drawings and instructions of the m2 4.4
supervising engineer

Supply and implementation of aluminum windows, W1 (1.0m*1.5m) (1.2 mm thick) with a throat section of 4.5 cm * 5 cm, a
section
The door is 4 cm wrapped, including the hidden locking handles, large hinges, glass rails and rings.
The shutter, and that the installation is done on an iron spreader of 2 mm thickness at the installation areas, and the space around
the throat is filled with material
3.13 The silicone is of a German quality according to the color, and it must be taken into account that the water drainage holes are m2 1.5
placed in the middle of the lower throat of the shutter
And that the supply and installation takes place according to the drawings, technical specifications, and the instructions of the
supervising engineer

Supply and Installation of Security Shutters for windows:


supply, installation , and finishing Galvanized Steel tube 20x20x1.4 mm for windows, Steel tube spacing shall be not more than
8cm. the work and price include, providing all required parts and accessories, fixing with anti- rust anchors, sanding, priming with
3.14 m2 1.5
rust resistant paint, and metallic paint with the required color, and doing all it takes and needs to finish the work according to
standards, drawings, and specifications.

PERIMETER SIDE WALK WORKS


Supply, install, and finishing of Perimeter Side Walk with a minimum width of 100 cm and construct from Precast concrete Curbs
15cm thick and 50cm height C25/30. filled in layers with good compacting. The rate shall include supply and install of cement tiles
30x30 cm and 3cm thick of high quality and approved, for the sidewalks/sideprotection pavement for the buildings laying on (1:3)
cement mortor layer 2.5 cm thick. The work and price shall also include excavation works, sand fill, mortor, including all necessary
3.15 fill layers with good compacting basecourse, and 10 cm thick plain concrete layer under the tiles, 1000 gauge polyethylene sheets, m.l 29
curing with water properly for no less than seven days with all necessary related works, and doing all it takes to finish and complete
the work according to the drawings, technical rules, and the engineer's instructions.

A 12 kg fire extinguisher
by number: Supply and installation of a 12 kg fire extinguisher with a sensitive hose of excellent quality, and it must be installed in
the back wall of the room, and the number of one extinguisher for each room
3.16 The price includes everything necessary to implement the item according to the drawings and instructions of the supervising NO 2
engineer

A 12 kg powder fire extinguisher


by number: Supply and installation of a 12 kilo powder fire extinguisher with a thermostat with a sensitive hose of excellent
quality, and it must be installed in the ceiling above the transformer, with a distance of not less than .-- and one fire extinguisher
per room NO
3.17 The price includes everything necessary to implement the item according to the drawings and instructions of the supervising 2
engineer

Steel fixed ladder with walk-thru handrails and safety cages.


Supply and install fixed ladder with walk-thru handrails and safety cages, Cages and walk-thru handrails extend 42 inch above
landing surface. Cages have flared bottom opening for easy entry.
Cage begins 7 feet from bottom of ladder. item include Side members are 1/4″x2″x2″ steel angle. 3/4″ corrugated steel round
3.18 climbing rungs on 12″ centers. Stand-off mounting brackets are 7″. Lump sum 1
Walk-thru handrails extend 42 inch above landing surface. Mounting brackets included. welded one-piece, pedestal. The work also
includes fabricating, welding, painting and all accessories. All according to design drawings, specifications and the instructions of
UNOPS Engineer.

4 TRANSFORMER AND ATS ROOM - CIVIL WORK

Measures to mitigate the environmental


impact: The contractor must follow the measures to mitigate the environmental impact and safety and security procedures at the
work site through: Taking safety and security procedures for the work site 2- Taking safety and security measures for individuals Lump sum
4.1 working in the workplace 3- Taking measures to reduce the escalation of dust , which leads to pollution Air 4 - Take measures to 1
reduce the high noise resulting from the operation of equipment, drilling machines, winches and others 5 - Follow the instructions
of the supervising engineer
Land excavation:
In cubic meter: Excavation in any type of soil, including fragile, medium and rocky, requires the work of the ground tank
until reaching the design depths specified in the drawings and dewatering, if any, while maintaining the sides of the
excavation and extensions (electricity - telephone - water) with the transfer of all waste to the approved sites From the
4.2 local authority, excavation is carried out in accordance with the drawings, specifications and instructions of the m3 54
supervising engineer. The contractor shall bear any damages that may occur to services or homes due to excavation.

Filling by soil:
In cubic meter:Backfilling with good soil free of organic matter. It is necessary to backfill the sides of the ground tank
either from the excavation product or imported from outside the site on layers not exceeding 30 cm with tamping and
4.3 spraying until obtaining a compaction rate of not less than 90% according to the levels specified on the drawings and m3 44.5
transferring the soil in excess of Backfilling outside the site according to the drawings, specifications and instructions of
the supervising engineer.

Reinforcement Concrete - RC Foundation


In cubic meter: supply and implementation of reinforcement concrete for the necessity of implementing the RC
foundations and necks of the generator room using cement that is resistant to salts and sulphates with a cement
content of not less than 350 kg / m3 to reach a concrete resistance of not less than less than 300 kg / m2 and a
4.4 percentage of reinforcement according to the plans and the price includes All that is necessary to implement the item, m3 2.3
supply, cut and form iron, casting and spraying, and do everything necessary according to the drawings, specifications
and instructions of the supervising engineer.

Reinforcement Concrete - RC Plinth


In cubic meter: Supply and implementation of reinforced concrete for the need to implement the RC plinth of the
generator room using cement that is resistant to salts and sulphates with a cement content of not less than 350 kg / m
3 to reach a concrete resistance of not less than 300 kg / m 2 and a reinforcing ratio according to the plans. The price
4.5 includes everything necessary for the implementation Class, supply, cut and form iron, casting, spraying and doing m3 1.7
everything necessary according to the drawings, specifications and instructions of the supervising engineer.

Plain Concrete - ground floor slab


In cubic meter: Supply and implementation of regular concrete for the necessity of executing the floor slab of the
generator room with the thicknesses specified in the drawings using cement that is resistant to salts and sulphates with
a cement content of not less than 250 kg / m3.
4.6 The price includes All that is necessary to implement the item, supply, cut and form iron, casting and spraying, and do m3 31.8
everything necessary according to the drawings, specifications and instructions of the supervising engineer.

Reinforcement Concrete - RC Column


In cubic meter:supply and implementation of regular concrete for the necessity of executing RC columns for the
generator room using cement that is resistant to salts and sulphates and with a cement content of not less than 350
kg / m3 and a percentage of reinforcement according to the plans
4.7 The price includes All that is necessary to implement the item, supply, cut and form iron, casting and spraying, and do m3 1.2
everything necessary according to the drawings, specifications and instructions of the supervising engineer.

Reinforcement Concrete - RC roof slab


In cubic meter:supply and implementation of regular concrete for the necessity of executing RC roof slab for the
generator room ,with a cement content of not less than 300 kg / m3 and a percentage of reinforcement according to
the plans
4.8 The price includes All that is necessary to implement the item, supply, cut and form iron, casting and spraying, and do m3 6.2
everything necessary according to the drawings, specifications and instructions of the supervising engineer.

Cement brick buildings


In square meter: Supply and implementation of solid concrete block buildings with automatic printing around the walls of the
ground tank, size 20 * 20 * 40 cm, approved quality using cement mortar (3:1) (sand: cement) and that the construction is regular
and level (building by qidda
and the scale), provided that the mortar thickness is not less than (2 cm) according to the sizes specified in the drawings. The price
4.9 includes the materials m2 64
and workmanship and all that is needed to finish the item in accordance with the drawings, specifications and instructions of the
supervising engineer

Galvanized iron cover - Cable Trench


In square meters:Supplying and implementing a cover of galvanized steel of excellent quality for the need for a cover,
The price includes everything necessary to implement the item according to the drawings, specifications, and the instructions of
4.10 the supervising engineer m2 12

galvanized iron mesh


In square meters:Supplying and implementing galvanized iron mesh of excellent quality, with a thickness of not less than 4 mm,
for the southern facade of the room
4.11 The price includes everything necessary to implement the item, according to the drawings, specifications, and the instructions of m2 7.8
the supervising engineer

galvanized stacking iron doors D1 (2.0m*2.2m):


In square meters:Supplying and implementing galvanized stacking iron doors of thickness 1.5mm stacking and welding in an
excellent way without lower or upper joints
4.12 The price includes sanding, welding and rust-resistant paint 2
Three thick sides, then the approved external color, provided that the supply and installation takes place according to the NO
drawings and instructions of the supervising engineer
windows works W1 (0.5m*0.5m):
by number :Supply and implementation of Saudi aluminum windows (1.2 mm thick) with a throat section of 4.5 cm * 5 cm, a
section
The door is 4 cm wrapped, including the hidden locking handles, large hinges, glass rails and rings.
The shutter, and that the installation is done on an iron spreader of 2 mm thickness at the installation areas, and the space around
the throat is filled with material
4.13 The silicone is of a German quality according to the color, and it must be taken into account that the water drainage holes are NO 4
placed in the middle of the lower throat of the shutter
And that the supply and installation takes place according to the drawings, technical specifications, and the instructions of the
supervising engineer

Suction fan
4.14 by number: Supply and installation of Suction fans of excellent quality and the price includes all that is necessary to implement 4
the item according to the drawings, specifications and instructions of the supervising engineer. NO

plaster work
In square meter: supplying and implementing cement with a thickness of 3 cm due to the necessity of plastering the internal &
external walls of the room. Price includes spatter, rough base coat and smooth finish. Excellent cement mortar with a mixing ratio
of 1:3 (sand:cement) with water sprayed three times a day for a period of time. not less than five days
4.15 The price includes everything necessary to implement the item according to the drawings, specifications, and the instructions of m2 128
the supervising engineer

Tile workers
In square meter: Supply and installation of Mosaic tiles(25*25*3cm) marble of homogeneous color
White cement more than half the thickness and free of defects shall be installed using cement mortar with mixing ratio
1:3) (sand: cement) over a layer of sand or helix, adjusting the weight and straightness using the crosses and the price)
Includes materials, workmanship, grouting, cleaning, polishing, and everything needed to finish the item according to the
drawings
4.16 and specs. m2 18

Isolation works
By square meter: Supplying and implementing an insulating layer for the room floor slab, ceiling and all concrete surfaces directly
4.17 exposed to soil or any place specified by the engineer. It consists of two perpendicular layers with the necessary tests according to m2 70
the drawings, specifications and instructions of the supervising engineer.

A 12 kg fire extinguisher
by number: Supply and installation of a 12 kg fire extinguisher with a sensitive hose of excellent quality, and it must be installed in
the back wall of the room, and the number of one extinguisher for each room
4.18 The price includes everything necessary to implement the item according to the drawings and instructions of the supervising NO 2
engineer

A 12 kg powder fire extinguisher


by number: Supply and installation of a 12 kilo powder fire extinguisher with a thermostat with a sensitive hose of excellent
quality, and it must be installed in the ceiling above the transformer, with a distance of not less than .-- and one fire extinguisher
4.19 per room 2
The price includes everything necessary to implement the item according to the drawings and instructions of the supervising NO
engineer

5 Fence Structure
Supply and install Chain Link Metal Fence with Barbed wires as per in the drawings and the technical specifications, the work
includes the following:
• Survey and conduct all site settlement and levelling such as cut and backfill in any type of soil, and clear all planned areas for the
work from materials, debris, trees, chairs and disposal of debris to authorized area prior to the commencing of work.
• Provide materials and construction of 2.50-meter-high chain Link Fence made from hot dip galvanized coated with pvc coated
Post that shall be embedded in (50X50X50 cm3) reinforced concrete footings and pressed at end. The panels width is 4 meter. The m 486 --
chain link comprise 50mmx50mm openings. the work includes installing of three lines of Barbed Wires above.
• Provide materials and construction of 6m wide double leaf gate as shown on the drawings and according to the technical
specifications and instructions of the supervising Engineer includeing 600X50X20 cm3 reinforced concrete beam.

6 Cleaning System
Supply, install, test and commissioning of a Solar Panel Cleaning System as per technical specifications include the following :
- Contractor shall provide a details drawings and specifications for the system including piping , distribution networks and water
tanks.
- The system shall have an Automatic Double Head Solar Panel Cleaning Brush.
- The brush Shall be a dual power model, which can powered from lithium battery and source of 220V. LS 1 --
-Brush's Pole shall manufacture of carbon fiber arbitrary expansion length up to 7.5 m.
-At least Ten of Automatic Double Head Solar Panel Cleaning Brush should be provided .

7 Project Sign Board


Supply, install and commissioning of project metallic signboard as instructed by site engineer. LS 1 --
Sub-Tota: 2 # -
Supply, Installation and Operation of Hybrid Solar System
For Jethmah Water Fields with 1.02 MWp Capacity

Sayoun - Hadhramout
Bid No.: IUS-AF-UWS-SAY-001
BOQ:
Total Cost
# Bill: No. Description
[USD]

1 Bill : 1 ELECTRICAL WORKS #REF!

2 Bill : 2 CIVIL AND STRUCTURAL WORKS #REF!

# GRAND TOTAL #REF!