Original
Activity ID Activity Name Start Finish
Duration
ARENCO Building Plot #939 120 15-Jan-24 13-May-24

GROUND IMPROVEMENT BY LATERAL COMPACTION OF SOIL 32 18-Mar-24 19-Apr-24


INTERNAL AREAS AREAS 32 18-Mar-24 19-Apr-24
A1740 Lancer Placing and Injection 20 18-Mar-24 06-Apr-24
A1820 DCPT after soil stabilizing NA 28-Mar-24 09-Apr-24
A1741 Snag Rectification(If Required) 10 10-Apr-24 19-Apr-24
EXTERNAL AREAS (Pump Room Area 17 01-Apr-24 18-Apr-24
A1730 Lancer Placing and injection 10 01-Apr-24 10-Apr-24
A1820 DCPT after soil stabilizing 3 11-Apr-24 13-Apr-24
A1731 Snag Rectification if required 5 14-Apr-24 18-Apr-24

REINSTATEMENT OF FLOOR TILING

A1300 Floor Tile Installation(Slab repairing if required) 35 01-Apr-24 05-May-24