PERBENA EMAS SDN BHD SADONG

CURRENT WORK REPORT 12-03-2023

Handover documents

1) to submit warranty letter by Supplier for 3M reflective sticker on signage. Supplier Boon Seng informed will be
ready by 15-03-2023

2) Draft Design guarantee & guarantee bond is ready for submission.

3) Letter of undertaking on defects to accompany with the above documents is ready

EoT No.12 for slope failure

1) Minsar ‘s assessment of the EOT and our Work Programme & Time slice analysis had been submitted last
week.

2) JKR Samarahan had agreed and recommended to HQ EoT of 224 days from 10th June 2022.

3) Was informed by JKR that the EoT Committee will sit in the next 30 days.
PERBENA EMAS SDN BHD SADONG

CURRENT WORK REPORT (CONT.) 12-03-2023

OTHER MATTERS

1) Met up with JKR ARE and will confirm further on the final payment is RM1,487,085.39, which included the
recoupment of imposed RM600,000 LAD

2) Available fund in JKR is RM900,000.00. Will follow on EOT so that the final payment excludes LAD.

3) RSA Closing meeting done last week and RSA will send ‘Decision of meeting’.

4) JKR Samarahan had spoken to YB Aidel that a culvert is proposed to be constructed at CH1+500 as a mitigation
measure using the contract cost saving of RM1.4 million and out of our Contract.
PERBENA EMAS SDN BHD SONG

Site Activities for last week

• Construct temporary bearing pads and lock soil nails at Slope 1a, 1b & 2a

• Fill voids under existing shotcrete facing at Slope 1a

• Apply shotcrete facing at Slope 1a

• Slope cutting at Slope 1c


PERBENA EMAS SDN BHD SONG
LATEST PROGRESS AS AT 12-03-2023

Activity Name 29-01-23 05-02-23 12-02-23 19-02-23 26-02-23 05-03-23 12-03-23 19-03-23
Slope 1a
SNW2-1a-0000 Construct Temporary Staging
SNW2-1a-1000 Breakaway Concrete Capping of Existing Soil Nail 136 Nos. 48 Nos. 0 Nos. 0 Nos. 0 Nos. 0 Nos. 0 Nos 0 Nos
SNW2-1a-1010 Extend Existing / Install New Weepholes / Extend Existing Horizontal Drain 24 Nos. 0 Nos. 9 Nos. 0 Nos. 0 Nos. 0 Nos. 0 Nos 0 Nos
SNW2-1a-1020 Apply New Shotcrete on Top of Existing Shotcrete Facing 82m3 36m3 0 m3 0 m3 0 m3 0 m3 21 m3 0m3
SNW2-1a-1030 Fill the Void Underneath the Existing Shotcrete Facing TBA. 0 m3 4 m3 0 m3 2 m3 9m3 8m3 17m3
SNW2-1a-1040 Install New Soil Nail at Slope 1a 136 nos. 65 Nos. 36 Nos. 0 Nos 35 Nos. Completed Completed Completed
SNW2-1a-1050 Install New Horizontal Drain 18 Nos. 5 Nos. 4 Nos 0 Nos 9 Nos. Completed Completed Completed
SNW2-1a-1060 Construct Concrete Bearing Pads & Lock Soil Nails 136 nos. 0 Nos. 0 Nos. 0 Nos. 0 Nos. 0 Nos. 29 Nos 20 Nos
Slope 1b
SNW2-1b-1000 Breakaway Concrete Capping of Existing Soil Nail 73 Nos. Completed Completed Completed Completed Completed Completed Completed Completed
SNW2-1b-1010 Extend Existing / Install New Weepholes / Extend Existing Horizontal Drain 12 Nos. Completed Completed Completed Completed Completed Completed Completed Completed
SNW2-1b-1020 Apply New Shotcrete on Top of Existing Shotcrete Facing 90 m3 Completed Completed Completed Completed Completed Completed Completed Completed
SNW2-1b-1030 Install New Soil Nail at Slope 1b 73 Nos. Completed Completed Completed Completed Completed Completed Completed Completed
SNW2-1b-1040 Install New Horizontal Drain 10 Nos. Completed Completed Completed Completed Completed Completed Completed Completed
SNW2-1b-1070 Construct Concrete Bearing Pads & Lock Soil Nails 73 Nos. 0 Nos. 0 Nos. 0 Nos. 0 Nos. 0 Nos. 63 Nos 10 Nos Completed
Slope 1c - Upper
Half
SNW2-1c-1000 Remove Temporary Fill & Trimmed to Grade
SNW2-1c-1010 Cut Off Excess Length of Rebar ot Existing Soil Nail 135 Nos 0 Nos 0 Nos 0 Nos 0 Nos 16 Nos. 0 Nos 0 Nos
SNW2-1c-1020 Install New Weepholes / Extend Existing Horizontal Drain 30 Nos. 0 Nos 0 Nos 0 Nos 0 Nos 0 Nos 0 Nos 0 Nos
SNW2-1c-1030 Apply New Shotcrete Facing 90.67 m3 0 m3 0 m3 0 m3 0 m3 0 m3 0 m3 0 m3
Fill the Void Underneath the Existing Shotcrete Facing of Slope 1c (Where
TBA. 0 m3 0 m3 0 m3 0 m3 0 m3 0 m3 0 m3
SNW2-1c-1040 Applicable)
SNW2-1c-1050 Install New Soil Nail at Slope 1c 106 Nos 0 Nos. 0 Nos. 0 Nos. 0 Nos. 6 Nos. 0 Nos 0 Nos
SNW2-1c-1060 Install New Horizontal Drain 0 Nos. 0 Nos. 0 Nos. 0 Nos. 0 Nos. 0 Nos. 0 Nos.
SNW2-1c-1180 Construct Concrete Bearing Pads & Lock Soil Nails 106 Nos 0 Nos. 0 Nos. 0 Nos. 0 Nos. 0 Nos. 0 Nos 0 Nos
Slope 2a
SNW2-2a-1000 Construct Shotcrete Bench 1a 26m3 0m 7m3 19 m3 Completed Completed Completed Completed Completed
SNW2-2a-1010 Breakaway Concrete Capping of Existing Soil Nail 102 Nos. 51 Nos. 26 Nos. 13 Nos. 12 Nos. Completed Completed Completed Completed
SNW2-2a-1020 Extend Existing Weepholes / Extend Existing Horizontal Drain 15 nos. 0 Nos. 9 Nos. 0 Nos 6 Nos. Completed Completed Completed Completed
SNW2-2a-1030 Apply New Shotcrete on Top of Existing Shotcrete Facing 93.89 m3 0m3 10m3 49m3 34 m3 Completed Completed Completed Completed
SNW2-2a-1040 Install New Soil Nail at Slope 2a 100 Nos. 79 Nos 10 Nos. 0 Nos. 11 Nos. Completed Completed Completed Completed
SNW2-2a-1050 Install New Horizontal Drain 15 Nos. 0 Nos. 7 Nos. 8Nos. Completed Completed Completed Completed Completed
SNW2-2a-1200 Construct Concrete Bearing Pads & Lock Soil Nails 100 Nos. 0 Nos. 0 Nos. 0 Nos. 0 nos. 0 Nos. 94 Nos 6 Nos Completed
PERBENA EMAS SDN BHD SONG
Latest progress on 12-03-2023 updated on 9 months Work Programme
PERBENA EMAS SDN BHD SONG

PROGRESS REPORT AS OF 12/03/2023

PREVIOUS REPORT PREVIOUS REPORT PREVIOUS REPORT


VARIANCE
(26-02-23) (05-03-23) (12-03-23)

Physical
Progress
CUMULATIVE
37.76% 41.39% 43.82% 2.43%
SCHEDULE

CUMULATIVE
18.32% 19.99% 32.90% 12.91%
ACTUAL

DIFFERENCE +/- (%) -19.44% -21.40% -10.92%

NO. OF DAYS
49 46 40
DELAYED
Current Status
a) The variance of +12.91% was because the completed earthworks was not updated.
PERBENA EMAS SDN BHD SONG

OTHER MATTERS
1) On JKR Kapit scheduled meeting on 02-03-2023 in Kapit to discuss Work Programme with completion in 9
months – was informed to write in and explain on 9 months duration – STATUS QUO

2) Landstar informed will only carry out rectification work on SNW2 until complete and will seek assistance from
JKR head to not carry out rectification on SNW1 & 3 – STATUS QUO

3) Confirmation & Signing of Supplementary Agreement to be put on hold, PVITO No.8 to be discussed and re-
scoped to exclude the BQ quantities of SNW1 & 3 – STATUS QUO
PERBENA EMAS SDN BHD SONG
PROGRESS PHOTO

Completed Soil nails at Slope 1b and 2a


PERBENA EMAS SDN BHD SONG
PROGRESS PHOTO

Slope cutting at Slope 1c for soil nailing


PERBENA EMAS SDN BHD SONG
PROGRESS PHOTO

Dismantle formwork of bearing pads and lock soil nails at Slope 1a


PERBENA EMAS SDN BHD GEDONG

Activity Planned Actual Cumulative

Site
46.45%
Clearing

Cumulativ
Activity Planned Actual
e
Sand
4.87% 4.13% 17.05%
Blanket

Activity Planned Actual Cumulative

Geotextile 4.22% 4.39% 18.15%

Activity Planned Actual Cumulative

Filling 3.54% 0.99% 10.14%


PERBENA EMAS SDN BHD GEDONG

12-03-23 Cummulative Cummulative Upcoming Week


Description Qty
Planned % Actual % +/- work done work done % Planned %
Site clearing works (Ha) 19.00 8.83 46.45% 0.50 2.63
Ground treatment works
Geotextile (m2) 142,033.88 1,500.00 1.06 1,062.21 0.75 -0.31 25,772.62 18.15% 1,500.00 1.06
Sand Blanket (m3) 61,615.75 750.00 1.22 0.00 0.00 0.00 10,844.92 17.60% 750.00 1.22
Filling (m3) 169,511.01 1,500.00 0.88 1,053.58 0.62 -0.26 17,794.73 10.50% 1,500.00 0.88
Pile Embankment
SD 1 355.00
SD 2 336.00
Earthwork
Filling (m3) 89,646.00
Turfing (m2) 91,086.00
Gabion matteress (m2) 3,877.00
SD 1 Bridge
Spun Pile (nos) 24.00 17.00 70.83% 3.00 12.50
SD2 Bridge
Spun Pile (nos) 54.00
Bore Pile (nos) 22.00
Drainage work
Earth drain (m) 11,116.00
Culvert (Nos)/(m) 16/277.86
Road and Pavement
PERBENA EMAS SDN BHD GEDONG
Current report 12-03-2023

1) Work progress hampered by bad weather.

2) Harum Unimas will continue with site clearing for platform and installation of temporary
jetty/wharf this week.

3) 1 no. of Leadcon excavator will start with site clearing towards CH3+500 from today.

4) Spun piling at BS1 Abutment B will continue for the remaining 3 nos.this week when the
MS collars for pile jointing arrives.
PERBENA EMAS SDN BHD GEDONG
PROGRESS PHOTOS

Laying geotextile, sand filling & filling at from CH5+675 to CH5+575


PERBENA EMAS SDN BHD GEDONG
PROGRESS PHOTOS

Construction of temporary jetty at BS2


PERBENA EMAS SDN BHD GEDONG
PROGRESS PHOTOS

Site facilities preparation at BS2