Kungsgatan 35A 451 30 UDDEVALLA SWEDEN

Ellevio AB
FAKTURA
XX2923
Datum: 2021-06-29 FE 312046
Organisationsnr.: SE-5560377326 737 83 Fagersta
Moms regnr.: SE556037732601 SWEDEN
Kundnummer: 6
Fakturanummer: 414
OCR: 41459
Betalningsvillkor: 30 dagar netto
Förfallodatum: 2021-07-29
Dröjsmålsränta: 8%
Valuta: SEK
Er referens: Jan Ranström/ZlatanGabela
Orderreferens: Ellevio 5 (130 kV
Tovåsen-Bodmyran)

Mer information:
Reverse charge for value added tax regarding supply for construction work is applicable.

Benämning Antal Enhet á-pris Summa exkl. moms Moms-%


ATA 2 1 st 598673,00 598673,00 0
Rock removal, Soil replacement

Slutsumma exkl. moms: 598673,00 SEK


Totalt att betala: 598673,00 SEK

DV SVENSKA Filial Organisationsnr.: 516411-0180 IBAN: NO52 1250 0849 175


Kungsgatan 35A Moms regnr.: SE516411018001 BIC : DNBANOKK
451 30 UDDEVALLA E-post: marijana.perisa@dalekovod.hr
SWEDEN Hemsida: http://www.dalekovod.com/se/
Godkänd för F-skatt
Attachment to Contractors Claim - Blastin, Rock removal, Soil replacement ÄTA 2, 130 kV Tovåsen-Bodmyran

Description:

Claim invoice specification

item activity unit qty unit price total


1. Dalekovod hours

Soil replacement under 2 bases on tower 36 (compacting with vibroplates). 1,5m depth, Two workers, one day (10h per day). 3 layers of compacting.
1.1. Montör h 20 508 10 160
50m2 surface

Total (1.1.-1.2.) 10 160

2. Material
Soil replacement under 2 bases on tower 36. 1,5m depth, 50m2 surface. Price of
2.1. Material (Makadam) m3 75,00 327 24 525
makadam is defined in the contract
2.2. Material pcs 0
Total (2.1.+2.2) 26 487

3. Additional works
3.1. Removal of the rock/Sprängning Blasting of the rock tower 40. More then 30m3 (price defined in contract) m3 30 2 780,00 83 400
3.2. Sprängning etablering 'Sprängning etablering'' on tower 40 (price defined in contract) pcs 1 18 000,00 18 000
3.3. Removal of the rock/Sprängning Blasting of the rock tower 35. More then 120m3 (price defined in contract) m3 120 2 780,00 333 600
3.4. Sprängning etablering 'Sprängning etablering'' on tower 35 (price defined in contract) pcs 1 18 000,00 18 000
Even this work needed to be done by blasting, as we could not wait that much for blasting team, and
quantity was lower and rock was suitable for hummering, Dalekovod decided to perform it on other
Removal of the rocks on tower 36. More then 18m3. It is done with usage big jakc
Removal of the rock m3 18 1 668,00 30 024 way. Thats why we count 60% of the blasting and no mobilization cost for blasting as this option was
hammer mounted on excavator. (60% of blasting cost and no mobilization cost)
little bit cheaper. Dalekovod chosed this option in order to avoid unnecessary blasting under energized
3.5. parallel line.

Even this work needed to be done by blasting, as we could not wait that much for blasting team, and quantity was
Removal of the rocks on tower 29. It is done with usage big jack hammer mounted on lower and rock was suitable for hummering, Dalekovod decided to perform it on other way. Thats why we count
Removal of the rock m3 43 1 668,00 71 724
excavator. (60% of blasting cost and no mobilization cost) 60% of the blasting and no mobilization cost for blasting as this option was little bit cheaper. Dalekovod chosed this
option in order to avoid unnecessary blasting under energized parallel line.
3.6.
0
Total 3.1-3.6. 554 748

4. Machinery
4. Dalekovod hours
Soil replacement under 2 bases on tower 36. 1,5m depth, 50m2 surface. Price of
4.1. Excavator h 6 1 213 7 278
excavator is defined in the contract
Total (4.1.) 7 278

5. Change of soil type

Total (5.1-5.3) 0

TOTAL SEK: 598 673

Ånge Ellevio 72,5kV (Package 4 - Part 3)


2021-04-28 Project manager: Zlatan Gabela