You are on page 1of 1

5000-508 BUILDING CONSTRUCTION AND SAFETY CODE

1 layer of building
Door paper between
vestibule mantel
Opening and wall mantel

1 layer of building
paper between
Doors vestibule mantel
and wall
FIGURE A.8.3.2.8.3(a) Swinging Door and Sliding Door
Configuration for Egress Purposes in an HC Fire Wall. [221: Roll-up fire doors
Figure A.5.8.3(a)]
Fire door guide rails

FIGURE A.8.3.2.8.4 Double Doors on a Freestanding


Vestibule. [221:Figure A.5.8.4]

Direction of
Fire wall force on pipe
due to collapse
of structure

Elbow up
Steel sleeve
Close nipple
Listed firestop
material

Minimum 84 in.
9C Elbow to the
(2100 mm) right facing fire
wall so that
other elbow will
tend to loosen
during collapse
FIGURE A.8.3.2.8.3(b) Vestibule Arrangement for Egress of structure
Purposes in an HC Fire Wall. [221: Figure A.5.8.3(b)]

High hazard materials include flammable gases and combus‐


tible and flammable liquids used in piping systems and
combustible dusts used in air-conveying systems. [221: A.5.11] FIGURE A.8.3.2.9 Pipe Penetration. [221:Figure A.5.9]

A.8.3.2.12 Where a higher building or higher portion of a


building adjoins a lower building at an HC fire wall, the lower A.8.3.2.13 For existing construction where the roof strength is
building should always have a minimum 30 in. (760 mm) high not adequate to support gravel surfacing, the roof should be
parapet. A parapet can be omitted on the higher building if structurally reinforced to support the gravel. As an alternative,
there is at least a 15 ft to 50 ft (4.6 m to 15.2 m) elevation or for new or existing construction where the roof slope is
difference, depending on the severity of the fire exposure from excessive for gravel, the roof should be coated with an
the lower building (also see NFPA 80A). Where the parapet is not approved, lightweight, exterior grade, fire-resistant coating.
needed, the exterior fire-rated wall construction should extend [221: A.5.13]
at least up to the gravel stop. Gravel surfacing or equivalent is For single-ply roofs, where the roof is not adequate to
still recommended for at least 25 ft (7600 mm) from the HC support the specified weight of the ballast stone or paver
fire wall in each direction on the higher and lower roof. [221: blocks, it should be similarly reinforced, or the top surface of
A.5.12] the roof should be protected with an approved coating, as
A.8.3.2.12.3 For example: If the HC fire wall has a 3-hour fire described previously, if the roof membrane is totally adhered.
resistance rating, the structural columns, beams, and girders Mechanically attached, single-ply roof covers normally flex
have a fire resistance rating of 3 hours. (See Figure A.8.3.2.12.3.) between fasteners, which could cause cracking of a coating.
[221: A.5.12.3] [221: A.5.13]

2018 Edition Shaded text = Revisions. Δ = Text deletions and figure/table revisions. • = Section deletions. N = New material.