BILL OF ITEM

PEMBANGUNAN BUS SHELTER


PT KAWASAN INDUSTRI KENDAL

HARGA SATUAN JUMLAH HARGA


NO VOLUME
HARGA SATUAN JUMLAH HARGA
NO ITEM PEKERJAAN VOLUME

Rp. Rp.

A Pekerjaan Konstruksi Baja

1 Kolom & Rangka Atap


a Besi Hollow 150x150 kg 525.00 17,000.00 8,925,000.00
b Besi Hollow 100x100 kg 195.00 17,000.00 3,315,000.00
c Besi Hollow 50x50 kg 1,927.00 17,000.00 32,759,000.00
d Besi Hollow 40x40 kg 610.00 17,000.00 10,370,000.00
e Wiremesh M5 kg 29.00 15,000.00 435,000.00
f Siku dudukan Besi kg 25.00 15,500.00 387,500.00
g Angkur M20 bh 32.00 92,000.00 2,944,000.00
h Plat strip kg 31.00 15,500.00 480,500.00
i Zincromate + Cat finish kg 200.00 3,000.00 600,000.00

B Pekerjaan Finishing, Tampak & Atap


1 Atap Galvalum m² 11.00 145,000.00 1,595,000.00
2 Tanaman Gantung ls 1.00 3,000,000.00 3,000,000.00
SubTotal 64,811,000.00

Fee kontraktor 8% 5,184,880.00

Ppn 10% 6,999,588.00

JUMLAH 76,995,468.00