2) What are the general requirements for test manifold and fittings?
a) Pressure testing manifolds were separately pressure tested to at least 1.2 times system
test pressure
b) Pressure rating or design of test manifold components (isolation valves, pipe nipples,
fittings) exceed system test pressure by 20%.
c) A blow down valve of adequate pressure rating is installed to depressurize the
system safely.
d) All of the above.
3) What are the general requirements for test manifold and fittings?
a) Test piping, fittings and hoses are designed or have adequate pressure ratings that
match or exceed system class/ test pressure.
b) Paddles or spectacle blinds & other fabricated test items used to isolate test sections
are at least the same code class rating of systems under test.
c) Pressure testing manifolds were separately pressure tested to at least 1.2 times system
test pressure
d) All of the above
5) What types of inspections may be carried out when inspector suspects environmental
cracking
a) Radiography
b) Wet Fluorescent Magnetic Particle
c) Ultrasonic Examinations
d) All of the above
10) When two or more branch connections are so closely spaced that their reinforcement
zones overlap, the distance between center of the openings should be at least ___1 ½
times their average diameter.
a) 1 ½
b) 2.5
c) 3.0
d) None of the above.
11) Material used for reinforcement may differ from that of the run pipe provided it is
compatible with run and branch pipes with respect to
a) Weldability
b) Heat treatment requirements
c) Galvanic corrosion
d) Thermal expansion etc.
e) All of the above.
12) API 570 requires classifying piping systems according to the _______
a) consequences of failure.
b) As per proposal of Owner
c) Cost factor
d) All of the above
13) A miter bend that makes a change in direction at a single joint greater than 45 Deg may
be used only for _______Fluid Service.
a) Category D (ASME B31.3 para 306.3.2)
b) Category M
c) Category U
14) What are the general requirements for pressure gauges and recorders?
a) Pressure gauges and pressure recorders are calibrated within (1) month prior to test.
Stickers applied indicate latest calibration date.
b) Test gauge is located at bottom of any equipment/system under test to enable
reading test pressures inclusive of hydrostatic head.
c) All gauges have a range such that the test pressure is within 30% to 80% of the full
range.
d) All of the above
15) What are the general requirements for pressure gauges and recorders?
a) A minimum of two pressure gauges are required for test systems, with accuracy
within 5% of one another.
b) Pressure gauges and pressure recorders are calibrated within (1) month prior to test.
Stickers applied indicate latest calibration date.
c) Test gauge is located at bottom of any equipment/system under test to enable
reading test pressures inclusive of hydrostatic head.
d) All of the above
16) What are the general requirements for Filling & Pressurization?
a) Filling & pressurization is done upstream of check valves in system.
b) Test fluid enters (shall be drained) at the lowest point in the system.
c) All vents are open during filling. Minimize Trapped air.
d) All of the above
17) What are the general requirements for Filling & Pressurization?
a) On initial pressurization, pressure holds AFTER equalization at 50% test pressure.
Gauge drops indicate a leak (acceptable for efficiency) or "inefficient" test crews
leaving air in lines (unacceptable).
b) After venting, valves used for venting are placed in the partially open position and
plugged or blinded as applicable.
c) Preliminary check for leaks at 50% of the strength test pressure was performed. Test
crews were efficient in filling practices.
d) All of the above
18) For severe Cyclic conditions ____ radiograph of welds are required for welded wrought
fittings.
a) 100%
b) 50%
c) 75%
d) 10%
19) A miter bend to be used under severe cyclic conditions shall have an angle alpha ____
a) Less than or equal to 22.5 deg.
b) Less than or equal to 30 deg.
c) Less than or equal to 30 deg.
d) None of the above
20) After hot bending and forming, heat treatment is required for ___ in all thicknesses.
a) P-Nos 3,4,
b) P-Nos 5,6,
c) P-Nos 10A materials
d) All of the above
21) _______ shall not be used to help in closing the gap or overlap of piping because it
defeats the purpose of cold springing
a) Heating
b) Pressing
c) Shrinking
d) All of the above
22) No more than _____ shall be used between contact faces in assembling a flanged joint.
a) one gasket
b) one gasket
c) one gasket
d) None of the above
23) ___provides dimensions and tolerances for flanges in pipe sizes from 1/2" through 24"
a) ASME B16.5
b) ASME B16.40
c) ASME B16.9
d) None of the above
24) ________ provides in pressure classes from 150 lb through 2500 lb.
a) ASME B16.5
b) ASME B16.40
c) ASME B16.9
d) None of the above
25) _________ is related to Construction and in-services of Pipelines & related facilities.
a) API std 1104
b) API std 570
c) ASME Section IX
d) ASME Section VIII
26) Dimension of welded & stainless steel pipes are given in __________
a) ASME B36.19.
b) ASME Section VIII.
c) ASME B16.9
d) ASME B 16.48
27) Nominal Weights of steel pipes, Plane end are given in ______
a) ASME B36.19.
b) ASME Section VIII.
c) ASME B16.9
d) ASME B 16.48
30) Hot tapping is the technique of attaching a _______ to piping or equipment in service,
and _______in that piping or equipment within the attached fittings.
a) Mechanical fitting
b) welded branch fitting
c) creating an opening
d) All of the above
31) Hot tapping is usually performed when it is not feasible , or it is impractical, to take the
________
a) equipment or piping out of service
b) To purge
c) Clean it by conventional methods.
d) All of the above
32) If radiographic exam is used for qualification, the minimum length of coupon to be
examined is
a) 6in
b) 8in
c) 10in
d) All of the above
33) The pipe shall have all of the API marking specified in __________
a) API Spec 5L
b) ASME Section IIA
c) Both a& b
d) None of the above
34) If piping is insulated the inspection will be performed on the insulation as follows:-
a) Over all condition of the insulation should be recorded.
b) All rips, cuts, dents and missing sections be reported for repair
c) All locations of potential moisture ingress should be recorded for rectification
d) All of the above
40) All of the piping attached with the equipment with the settlement problem should be
evaluated for ______ due to displacement of the equipment .
a) over loading
For CBT training ( subject piping & welding) contact cbtnew302@gmail.com
Aramco CBT Model Question Paper with Answer –Piping No 009
For CBT training ( subject piping & welding) contact cbtnew302@gmail.com
b) under loading
c) both a & b
d) none of the above.