PIPING CBT-JOYDEV-23 JUNE

1. What Is the minimum holding hours for Underground Process Piping as per b31.3
A) 0.5 Hours
B) 1 hour
C) 2 Hours
D) 24 Hours
2. If a longitudinal weld is intersecting a circumferential Weld than how much length of the
longitudinal weld shall be radiographed along with cir. weld
A) 1”
B) 2’’
C) 6’’
D) 1.5’’
3. What is the standard for Butt Welded Fittings for Piping
A) B16.9
B) B16.11
C) B16.20
D) None of the above
4. What is the Tightness test-
5. After Hardening of Which Heat treatment to be carried out
A) NORMALIZING
B) PWHT
C) ANNEALING
D) TMPERING
6. What is the Fillet size of Slip on Flange if Pipe Thk 5 mm and Hub Thk 9 mm
A) 9 MM
B) 6 MM
C) 7 MM
D) 8 MM
7. For SS material what is the PPM level acceptable for Hydrotesting-50 PPM
8. In Hydrotest calibration validity of Pressure Gauge-
A) 30
B) 45
C) 60
D) NONE OF THE ABOVE
9. How much temperature shall be reduced in Impact testing sub size specimen 5X5
A) 15 DEGREE F
B) 25 DEGREE F
C) 20 DEGREE F
D) NONE OF THE ABOVE
10. When Safety Valve release gas or Liquid then disposed should be –
A) Open atmosphere
B) System drainage
C) Anywhere
D) Human area
11. Which is not to qualify a owner inspector?
A) API 570 + 5 years experience
B) PE registration + 5 years experience
C) CWI/SCWI + 5 years experience
D) 5 years experience
12. Which one is false statement for Slip on Flange per B31,3
A) Slip on Flange can be used for severe service
B) Slip on Flange shall be double sided welded for severe service
C) Slip on Flane shall be used below -101 degree C
13. Preheat for A335 Gr. P-5 material is?
A) 10
B) 95
C) As per WPS
D) 175C
14. Crack acceptance in Cat-D fluid service?
A) 1mm
B) 1.5mm
C) 2.4mm
D) Not acceptable
15. When using old qualification from previous employer, Which is not true ?
A) Sign & endorse by employer
B) Verify data as per ASME IX
C) New Employer name shall be available
D) Welder old employer shall provide originals
16. For sensitive Leak test method the Pressure shall be at least the lesser of
A) 33%
B) 25%
C) 20%
D) 95%
17. What is the Logitudinal joint quality factor for API 5L Pipe
A) 1.00
B) 0.95
C) 0.85
D) 0.80
18. When the Test of piping exceed Vessel test pressure and it is not practicable also to isolate
the piping. Then vessel may be tested ---% piping test pressure
A) 25%
B) 77%
C) 85%
D) 67%
19. Which increases Hardness of material
A) Ni
B) Cr
C) Carbon
D) All of the above
20. What is tightness test-
21. Percentage accuracy between two pressure gage as per B31.3
A) 5%
B) 10%
C) 25%
D) none
22. As per B31.3 requirement for visual examination for category-D fluids
a. 5%
b. 10%
c. 25%
d. As per code and design
23. WPS for process piping to be qualified for the fabrication of fitting a joint as per ?
a. B31.3
b. Sec IX
c. Not required to qualify for the fitup
d. None
24. After hydrotest completion, when dew point temperature measure?
A) After 7 days
B) After 14 days
C) Immediately
D) 30 Days
25. Socket welds larger than NPS shall not be used under severe cyclic conditions?
a.3/4
b. 1
c. 1.5
d. 2
26. What is Package Equipment
27. What is the stringing length of Pipeline 900 M TO 1200 M
28. Standard for Surface Finish
A) MSS SP-25
B) MSS SP-6
C) MSS SP-51
D) NONE OF THE ABOVE
29. In Elevated temp service condition under which pressure or temperature or both, exceed
the design condition is known as
A) Design Condition
B) Operating condtion
C) An excursion
D) A duration
30. What is the example straight threaded joint-
A) Threaded of threaded piping
B) Threaded on threaded Valve
C) An Union Comprising male and female end joined with threaded union nut
D) None
31. In the Equation Tm=t+c, what is the value of ‘’t’’
A) Minimum required thk,including mechanical,corrosion & erosion allowance
B) Pressure design thk
C) Pipe wall thk
D) Minimum design temp of the pipe
32. What is the acceptable pH value of Water for Hydrotesting
A) 5.0
B) 5.5
C) 7.0
D) 4.0

E) 80
F) As per WPS