1) Prior to Installation of pipe:
a) All pipes shall be internally cleaned by air
blowing.
b) All prefabricated pipe spools shall be visually
inspected for cleanliness
c) The piping ends shall be covered after inspection
d) All of the above
b)
c)
d)
15) Minimum number of pressure gauges required
during hydro test?
a) 1
b) 2
c) 5
d) Based on availability