You are on page 1of 7

PAGE 15

It is commonly believed that Visbreakers are also tower overhead receiver water one to two hours
adversely affected by high sodium content in the after the start of caustic addition. If the chloride
vacuum residue used as feedstock. Excessive sodi- content is less than 10 ppm, reduce the caustic
um content in the feed leads to higher off-gas pro- addition rate. If the chloride content is greater
duction and lowers the yields for more desirable than the target overhead chloride level, the caus-
distillates. A limit of 25 ppm is often quoted as a tic addition rate may be increased gradually to the
working maximum for sodium in the VBU feed. level needed to get within the targeted chloride
control range. For systems without a desalter, the
rate may be up to a maximum of 5 PTB NaOH. If
Some refineries are concerned about the sodium these limits are ever exceeded, the Inspection
content in the coker feed or have specifications for Department must be notified.
sodium in the produced coke. Sodium limits in the
Monitoring And Adjustment In Caustic
coker feed range from 50 ppm to no limit. Again,
Rate
each processing unit has to determine the sodium
specification for the coker feed. Normally, once the caustic injections reach a level
at which the unit is consistently within its targeted
Injection of caustic upstream of desalter is not rec-
OH chloride range, the caustic injection rate is
ommended because high desalter water pH can
then fixed and only adjusted if there is a step
results in the formation of Emulsions and can drive
change in performance.
amine compounds into the crude. Also, the caustic
will be unavailable to react where the salt hydroly- Overhead PH Control should be maintained by
sis takes place since it will typical be removed in adjusting Neutralizer Injection, not varying the
the desalter brine. This indirectly also means that caustic injection rates. Caustic injection rates
the demulsifier dosage requirement would become must be adjusted whenever the actual caustic so-
higher than normal. lution strength changes in order to maintain tar-
get ppm of caustic in crude. For example;
Caustic Injection Rates Calculation
In one incident, the crude tank that was about to
The theoretical Caustic Injection rate can be calcu-
be brought online had been reported as contain-
lated as;
ing a higher level of BS & W than the one current-
CAUSTIC PTB = (OH Chloride Reduction) x ly feeding the crude unit. As this tank was brought
(40/35.5) x 1000/ (OH water) online, desalter amps and interface levels rose
OH Chloride reduction: Measured OH water sharply indicating a water slug had hit the desalter.
chloride (ppm) – 10 ppm To mitigate this event, operators increased de-
mulsifier dosing and reduced desalter wash water
OH Chloride reduction: 15 ppm. rates. Shortly after, the overhead sour water pH
OH water: Atm Tower Steam + Desalted dropped quickly from pH 6.5 to 4.5 as it can be
Crude Water (lbs/Bbl Crude) seen below. In response to this reduction in pH,
the 3DTCOS online Analyzer significantly in-
OH water: 9.0 lbs/bbl of Crude. creased the neutralizer dose rate to increase the
CAUSTIC = 1.86 PTB (5.5 ppm) PH back to normal. Here it can be observed that
nobody talks about manipulating the caustic dos-
The calculated number is anticipated 100% Neu- age. There is a very important lesson here that
tralization efficiency for the caustic added. The the overhead chlorides are controlled through
lower the caustic strength used, the higher will be caustic and PH is controlled through Neutralizer.
the caustic efficiency. In no case should this quanti-
ty exceeds 5 PTB (15 ppm) of caustic or it could be
troublesome for the pre-heaters & furnaces if caus-
tic dosing results in less than 10 ppm chloride
measured in the overhead boot water.
Preliminary Caustic Rate
Start caustic addition to the crude charge at 50% of
the rate calculated to obtain the desired salt neu-
tralization as established above – but not more
than 1.5 PTB.
Determine the chloride content of the atmospheric
PAGE 16

Inspection Requirement increased too much due to bad performance of


Single stage desalter so against that the operation
The caustic injection point should be included in
team raised the caustic dosage in order to control
the injection point inspection program. This in-
the ppm of overhead chloride to normal 20-25
cludes setting up inspection locations in the piping
ppm. Therefore, on grounds things could be dif-
around the injection point and radiography of the
ferent but most of time verifies theories.
quill to ensure that it remains intact. The quill
should be pulled during each unit turnaround and Recommendations
visually inspected.
 It is highly recommended to maintain caustic
injection rates in the range of 5-15 ppm or
doesn’t exceed below 12 ppm in the over-
head chloride.
 Caustic to be dosed at the downstream of
desalter, not at upstream.
 Caustic solution should be made in conden-
sate.
 Caustic strength to CDU to be maintained at
3.0- 5.0 wt%. At a minimum, the caustic
strength should be verified using a hydrome-
ter at the storage tank each time a batch of
caustic is made and mixing is complete. A
chart relating NaOH wt% back to density
Case Study: Caustic Injection Rates (read from the hydrometer) should be used
for this initial verification. On systems with
This study was carried out in one of the oil refiner- the continuous on-line mixing system, the use
ies located in Asia in which the recently discussed of a meter to measure caustic strength should
rule was not instigating. What could be the main be seriously considered.
reason?
 These caustic strength numbers should be
recorded and available to operations and the
chemical vendor on the unit. They should be
used by operations to adjust the caustic solu-
tion injection rate to ensure sufficient flow to
maintain the same PTB injection, as it would
have been at the caustic strength of the previ-
ous batch of dilute caustic. This avoids over
injection of caustic and assists in maintaining
stable chloride levels in the overhead system.
References
SUEZ Recommended best practices – Process
parameters Impacting Reliability & Corrosion on
Crude units.
Refinery Injection and process mixing points,
NACE international Publication 34101, NACE
International, Houston Texas, March 2001.
Corrosion and Fouling Management Course, UOP
Process Division, Des Plaines, IL, November
1982.
Bagdasarian, A., Feather, J., Hull, B., Stephenson,
From the above Half monthly trends, it seems that
R. and Strong, R., “Crude Unit Corrosion and
the proven rule which is, increasing the caustic rate
Corrosion Control”, presented at NACE Corro-
lessens the chloride ppm in overhead boot water
sion/96, Paper No. 615.
fails here but it is not. Upon investigation it was
identified that the desalter outlet salts have Refinery Corrosion Control Handbook, Gulf
PAGE 17

Science and Technology Company, Pittsburgh, PA,


Report No.561RF058, September 1977.
Hausler, R.H. and Coble, N.D., “Corrosion Con-
trol in Crude Unit Overhead Systems”, presented
at API Refining Division 37th Mid-Year Meeting,
New York, NY, May 8-12, 1972.
Author

Shahzeb H. M. Ismail holds a master degree in


chemical engineering from NED Institute of Tech-
nology, Karachi, Pakistan. He is Chartered Chemi-
cal Engineer from IChemE & a Chartered Engineer
from Engineering Council UK. His expertise over 6
years of experience Covers Pakistan refinery Tech-
nical services, Operations & Process Safety. His
Major role is to provide Process simulation sup-
port, optimization, Crude Evaluations, Crude reci-
pe development, Supervise Catalyst regenerations
& Troubleshooting’s. Currently working as Lead
Process Engineer, Crude Distillation Unit.
PAGE 18

Partners to the Top


Summit Technology Management is a technical consultancy group, providing specialized
services and training to improve process plant operational efficiency, profitability and safety. We
provide engineering solutions by offering training, technical services, best practices, and equip-
ment to meet the specific needs of our partner clients.

 Basic Design Packages  Singapore & Malaysia Company


 Detailed Design Packages Registration & Set Up
 Commissioning of Process Units  Specialty Equipment: Distillation
 Process Engineering Studies Equipment, Filter Skid Packages,
 Bench Marking of Process Units Compressor Knockout/Scrubber
 Regional Training Conferences & In Skid Packages, Mercury Removal
-House Training Skid Packages

www.summit-tech-mtg.com
PAGE 19

Punch List– The Conclusive Specific


Comments Writing
Lalit Mohan Nainwal, C Eng. (India), MBA

Punch list writing is "No Monkey Business". II. What sense "deems a test pack, subsystem or
subsystem is complete" make
Most of us know that construction / pre-
commissioning punch list walk-downs on sim-ops For the construction team at the site many times
ongoing pipe racks and ISBL /OSBL areas are tiring the word complete is very common but what is
and frustrating works. It may be due to physical "complete"?
activities of going through many scaffolding ladders,
Let me explain, the client's EP/SME is always free
platforms, twisting body to get into places to see if
to comment but there are several phases of con-
a certain item is welded/installed or not. The work
struction and the EP/SME must keep in mind at
sometimes requires passing safely through areas
what phase of construction the contractor has
where welding, shot blasting, painting, fireproofing
invited him for walk-down.
or other works are in progress. During the pre-
commissioning phase, a construction / pre- Particularly in piping construction, hydro/
commissioning punch list originator has to pass pneumatic test pack level walk-downs starts when
safely near the area where he can find another line another piping spool has not yet been installed.
is under the signage of pressure test or blowing. Does it mean "we shall cancel the walk?'"
Significance of Punch, the cost of actual work and Answer is "No", if the test-pack limit is complete-
punch work, if compared, punch work are too ex- ly constructed for the pressure envelope, we can
pensive as the contractor has to mobilize a whole go ahead with the test, keeping a punch list of
lot of skilled manpower, equipments and accesso- items for the final installation of that test pack in
ries for correcting the left out bit and pieces. The the subsystem/system.
same work could have been done in a matter of III. Punch Listing Management
hours which sometimes takes days to obtain per-
mits during punch closing or punch killing phase. The management of the punch list is dependent
on Built-Method accepted between company
That is the reason, many companies promote management and contractor. The built method is
"Zero-Punch" workmanship. a written method statement about how the struc-
I. What is Punch-List ture, piping & E&I will be erected. The EP/SME
should always note that a particular spool or
A punch list, like almost every other list, sounds
structure he is finding missing right when he was
very simple to make, list down the things that need
invited to walk-down will be erected after some-
to be corrected/installed. Though it looks very sim-
time when another item is erected otherwise
ple, the task list is not always that easy. A punch
there will be no access or interference for that.
list most commonly has an explanation that gives
the purpose of the punch list followed by the actual IV. International Standards & Reading of Engineer-
list of tasks or missing items that need immediate ing Drawings
attention. Unless it is a trade secrecy, the symbols, nomen-
Punch lists or punch points are observations made clature and other drawing codes shall be kept to
by an experienced professional or subject matter international standards to the maximum extent.
expert (EP/SME) referring to a set of drawings, This will reduce misinterpretation issues in punch
procedures or specifications. This work carried out listing and create uniformity of understanding.
when the Installation contractor deems a test pack, V. The Punch Categories
subsystem or subsystem is complete and invites or
solicits his walk-down on a piping system, subsys- As mentioned earlier, in the beginning construc-
tem or a test pack. tion is a very dynamic process and so shall be the
punch list. EP/SME writes punch points in
PAGE 20

three (3) or four (4) categories- A Punches are normally written on observations
of critical items that are left to install/weld with-
A Punch
out those the pressure envelope can not be com-
B Punch plete. For example a welding joint not complete
in some cases, if commissioning philosophy allows or a test pack has a line item included in the test
limit. A Punch or Pink Pages are immediate action
C Punch items.
D Punch What if the test pack was not a pressure test
For example, In some companies it's a practice to pack - it was just an open to atmosphere vent or
write A punch in Pink pages having standard open to funnel drain line after trap or valve?
formed printed, B in light blue papers, C in white Many PE/SMEs choose to write visual test pack
paper printed forms and D in Yellow. Since the missing items in A category as the contractor may
technology has advanced and database systems are not invite reinstatement to walk-down in these
being used that color segregation is not that preva- kinds of items.
lent now.
B Punches marked are in most cases those items
So what are those categories in specific, let me ex- which can be installed after pressure test, through
plain, reinstatement activities and has no direct contact
with pressure envelope such as guide beside shoe,
PAGE 21

trunnion bases and guides or Anchors under shoe either piping team or painting team will find that
support. B Punch or Light Blue papers are second one side guide is removed and the pipe is lifted to
priority. paint the steel below the shoe support and yet
there was no punch during the initial walk that
Marking any observation as category A or B in the
guide to be installed. The installation contractor
punch list is an experience-based work.
may leave the damaged work as it never made its
There will always be technical arguments, the PE/ way to the punch list. Tricky situation, isn't it....!
SME has to be very clear, will this item need dis-
Now, mixing many items as punch in a single
mantling of line from its location? Will the contrac-
punch item. For example, the PE/SME marked,
tor disturb the alignments to critical equipment to
Piping support clamp to be tightened, contact
get B punch listed items closed?
point paint to be completed and guides to be
Unfortunately in many instances PE/SME finds at welded at so & so location in a particular drawing.
later phase the items which were marked as B Hang On..! This is complicated.
items to let the pressure test go has created more
You know the above example has so many activi-
work than it was thought of at the initial state.
ties, fasteners-related, welding-related & Painting-
C Punch/White Paper, in concurrence with com- related.
missioning manager, marked for few items or re-
No Punch shall be written based on assumptions
maining works that can be installed/completed after
and speculations, all punch-list comments shall
pre-commissioning during the commissioning
have a strong document-based or experience-
phase.
based justification.
D Punches/Yellow Paper are not common and user
VIII. A Valid Punch
-specific, normally for Lettering or QR tags, paint/
color band or flow arrows or few valves/specialties A valid punch is that can stand argument in case
that were kept closed for preservation reason the contractor who deems work was complete
need opening, etc. yet pointed by PE/SME that his work needs fur-
ther work. In short, the left out work which
VI. Punch List Forms, what it must ask for
against drawings or else, PE/SME can justify his
When a company develop it’s construction/pre- stand.
commission or any else punch list format, the fol-
A disorganized punch list will often be hard to
lowing clear details to be asked-
understand what purpose had originator thought
a. system no., b. subsystem no, c. drawing, d. item when commented, making potential dangers of
no in MTO which was observed incomplete, e. future argument.
punch description, f. originator details, g. date of
When writing a punch list, the writer needs to
observation, h. action by (Dept details, such as Pip-
make it so that the matters he or she is trying to
ing, Structure, Paint, Insulation), i. date closed sign
draw attention to will get the notice it needs.
column for contractor, j. punch close sign off by
company EP/SME. IX. What are the back-up documents for punch
list
VII. Punch writing
Normally PE/SME notes punch against drawings,
The punch writing is an experience-based skill ac-
standards, specifications, and good engineering
quired through the number of jobs someone has
practices. Having a set of standard drawings or
handled in construction.
else will be the back-up. In many cases, the expe-
In punch writing, someone should use the specific rience is also a key to quality punch listing.
terms and items marked in the drawing or else be-
X. Understanding the Phase of Project Execution/
ing referred and based on the current execution
Construction
status when the walk-down is invited. The PE/SME
shall not use ambiguous language that can lead to A good understanding of which walk down some-
confusion later. one is invited for is a major game-changer. One
item observed as left to install at an earlier test
Punched items if not PE/SME's department-specific,
pack phase can be marked as a B item on that
shall be discussed with other departments on how
instance, the same item can be a potential A item
to note those. For example, a Piping PE/SME sus-
if it appears incomplete at the pre-commissioning
pect that at a modular construction of piping steel
phase or during subsystem/system walk-down.
below the shoe is not finally painted and yet the
line is installed with guides in place..! One day

You might also like