E-22-VN-KL-ABC_ABC VN (Airport operating company)
Kickoff Acceptance Server and 1st Workpackage 2nd Workpackage 3rd Workpackage Final GoLive Phase1
XX/XX – XX/XX Specifications Touchpoints Install Happy Flows Exception Flows Final Release Acceptance
(HW) (SW) (SW) (SW)
• VN provide IT Infra and Booth workstations, and • Phase1 : 15 December 2022 • IT procurement for servers/workstations from VN after
site infra (cabling, power, network) • Phase2 : February 2023 (estimated) Vision-Box deliver the equipment list
• Vision-Box provide touchpoints and software • Availability of the External Services (Watchlists)
• In the SoW is clear the responsibilities of each part
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
1 . 0 . 0 - beta1
MAJOR . MINOR . PATCH - LABEL
Breaking Feature Fix
Incompatible add backwards- backwards- pre-release
Changes compatible compatible bug label to indicate
feature fix a build
•
•
•
•
Detected bugs, not installed in STG
All scope implemented All scope tested No trial version, all playbacks done
•
•
•
•
•
•
•
•
•
•
•
•
•
•
• • • •
• • •
(bug fixes)
1.1.0 Release Candidate
• • • • • •
• •
• •
•
•
• •
• •