Standard Times

Cutting / Forming / Welding / Machining / Assembly

Ref: Realistic Cost Estimating for Manufacturing


The Society of Manufacturing Engineers –USA
Vemon I.R. MI-1968

Slide # 2 – to - 16
Description Standard Time Remarks
1)Bolts/Screw, Washer and nuts 1.40min
A 2)Bolts / Screw, Washer, nuts and collar key 1.50min
3)Spline Nuts 0.80 min
4)Bolts to nut plates 0.50 min
Description Standard Time Remarks
includes arrangement of
1)Set up time tools/fixtures and welding
equipment etc.
B 2)Handling time
i)Two 1.80 min
ii)Three 4.20 min avg.
iii)Four 6.0 min avg.
iv)Each additional Parts Over 4 11.80 min avg.
Description Standard Time Remarks
Includes part handling, cleaning,
1) Set up time 18-MINUTES part positioning & part alignment.

D 2) 1.5MM Stock 0.10 min/1CM


includes normal pre-heating for
3) 3.175MM Stock 0.16 min/1CM aluminum, steel or magnesium
4) 6MM Stock 0.30 min/1CM
OVEN or Using a heat treatment furnace
5) STRESS RELIEVING
FURNACE TIME which includes handling of parts
Description Standard Time Remarks
Spot welder requires installing & adjusting
contact points, current and timing,
1) Set up time 24-MINUTES positioning and adjusting the welding
fixture which holds the parts included
E
2) Part handling time / operation 0.20 Minutes Includes time for parts handling and the
3) Spot weld run time / Operation 0.20 Minutes moving of the assembly from spot to spot
4) Welding time / Cycle 0.05 min/cycle and depressing the foot paddle to activate
the machine weld cycle at each spot.
Description Standard Time
1) Set up time 9 minutes
2) Part handling time
0.45 minutes
G 3) Machine Run Time
i)25mm thick stock
0.30 minutes
ii)75mm thick stock
2.55 minutes
iii)150mm thick stock 9.50 minutes
Description Standard Time Remarks
without changing dies, positioning must be set
27 minutes and space between ram and bed must be
1)Set up time
adjusted for material thickness and die size.
12 minutes Additional time if die changed
2)Sheet Forming
i)Small size parts 12 minutes handling and machine time (includes individual
H
ii)Medium size parts 18 minutes parts handling to and from the forming dies)
iii)Large size parts 30 minutes
3)Bending
i)Setup time 27 minutes
handling and machine time (includes individual
ii)Small size parts 2 minutes
parts handling to and from the forming dies)
iii)Medium size parts 3.5 minutes
iv)Large size parts 10 minutes
Description Standard Time Remarks
Includes obtaining necessary tools and gauges,
installing the collets and or chuck setting in or
1)Set up time 30 minutes
squaring off the length of bar stock plus time to
J check the first piece.
which includes pickup the piece of cut-to-length
tube or bar stock, installing and aligning it in the
2)Handling time 0.55 min./part
chuck, securing, checking concentricity making the
trail cut and than checking the setup.
Description Standard Time Remarks
Includes obtaining necessary tools and gauges,
installing the collets and or chuck setting in or
1) Set up time 30 minutes
squaring off the length of bar stock plus time to
check the first piece.
Includes the pickup and placement of the part in the
vise or fixture, release of the part after work is
2) Handling time 0.40 minutes
performed, checking of the part, part aside to tote
pan and fixture cleanup for the next part.
3) Table adavnce, back off or adjustment
0.20 min./cut
K time
4) Set table at poper position for work by
0.20 min/cut
moving up or down
5) Index dividing head 0.150 min/cut
Beginning with rough profile (0.5-in depth x 0.75-in
6) End milling 0.12min./inch with cutter) followed by finished profile (same size
cutter)
7) Surface or Surface Milling 0.90 min./inch Using plan, helical, slab, shell etc. end mills
Straddle milling and slotting with side, half side and
8) Side Milling 0.070min./inch
staggered tooth milling cutters.
9) Corners, grooves abd slots 0.060min./inch
Description Standard Time Remarks
Includes obtaining necessary drill, tape, counter sink,
gauges etc. & time to return them when job completed,
also included time to handle jig, fixtures vises, make
1) Setup time 18min/lot of parts adjustment to the drill press including changing feed &
speeds, make feed stop adjustment install drill in spindle
and check the first piece.
2) Handling time / hole
i)Medium drill press includes time for moving the parts from hole to hole and
0.30min/hole lowering the drill bit to the part surface. The cutting time
spindle RPM 500 - 2000
/inch of depth should be added to the handling time per
ii)Heavy duty drill press hole.
0.20min/hole
spindle RPM 1- 1000
De-Burring standard time “ Handling”

Machine Parts Tools


Forging – Casting – Extrusions - Shims – Plates – Hand and motor operated burring devices
Regular and irregular forms (aluminum, Magnesium and Steel) (abrasive wheels, drums, belts rotary and hand files)

Type of burring methods and tools are listed below with their respective time standards.

I - Chart – ‘A’ Setup time: Task


0.15 hours Sign in study, obtain tools clean bench and first piece inspection.

I Handling time per part : P.U. and aside after each burr operation Chart ‘B’
Complexity ‘S’ ‘A’ ‘C’
Weight of part ½ - lbs ½ to 3 lbs 3 to 10 lbs
Length of part per job 0-6” 6” to 24” 24” to over
A - IN-HAND
Toss aside 0.0008 0.0010 0.0018
Stack 0.0010 0.0014 0.0022
Pack in box 0.0019 0.0024 0.0030
B - In-Vise
P.U. and aside 0.0014 0.0022 0.0024
C - Clamped to table
Remove and aside 0.0020 0.0042 0.0060
De burring Standard Time (type of Operations)

Burring Time: includes burr edges and turn to next edge.


( code, S= simple, A= average, C= complex)

III Chart –C. Time for each 10 liner inch (edges)


Complexity code S A C S A C
Weight of parts
½-lb ½ to 3 /lbs 3 to 10-lbs ½-lb ½ to 3 /lbs 3 to10-lbs

Length of parts
0-6” 6” to 24”

Material Aluminum and Magnesium Steel


A Burr Tools: Sanding drum 0.0009 0.0012 0.0016 0.0012 0.0015 0.0021
Burr knives 0.0009 0.0014 0.0018 0.0014 0.0018 0.0021
Files-hand 0.0018 0.0023 0.0035 0.0023 0.0029 0.0046
B Drill Motor Split rod & Emery
0.0012 0.0014 0.0019 0.0014 0.0017 0.0023

Wire brush threads – 10”


0.0028 0.0035 0.0046 0.0028 0.0035 0.0046

Lane cloth Burr


0.0006 0.0007 0.0008 0.0009 0.0012 0.0014

C Bch. Press – ‘No Burr’ Tool – Pac web


0.0007 0.0009 0.0012 0.0009 0.0012 0.0014

Web –each 0.0005 0.0007 0.0009 0.0007 0.0009 0.0012


Form 1/32 radius Sand drum
0.0030 0.0036 0.0057 0.0036 0.0048 0.073

Form 1/32 radius Hand files


0.0060 0.0072 0.0096 0.0144 0.0168 0.0180
De burring Standard Time (type of Operations)

S.No Description Time per square inch Time per square inch
A Length of Part 0”to6” 6”to24” Over24” 0”to6” 6”to24” Over24”

Material Aluminum and Magnesium Steel


01 Surface clean up
Drill motor & split rod
250/ to 125 0.0016 .0.0016 0.0016 0.0020 0.0020 0.0020
02 Sand casting surface
Sanding drum 0.0014 0.0014 0.0014 0.0016 0.0016 0.0016
03 Hand scraper
Extrusion / surface 0.0012 0.0012 0.0012 0.0016 0.0016 0.0016
De burring Standard Time (type of Operations)

S.No Description Time per square inch Time per square inch
A Material Aluminum and Magnesium Steel
Lengths 0”to6” 6”to24” Over24” 0”to6” 6”to24” Over24”

01 Removing, forging, flash


Sand drum 14 and 24 ST 0.0072 0.0072 0.0096 0.0080 0.0100 0.0120
02 Remove forgings, flash
Rotary and hand file 75 ST 0.0140 0.0140 0.0180 0.0150 0.0160 0.0200
03 Drill press burr # 40
Hole to 3 inch diameter 0.0005 0.0006 0.0008 0.0009 - -
04 Machine burr-large
Hole per circular inch 0.0007 - - 0.0009 - -
05 File (rotary file or wheel)to straight
line after 0.0015 - - 0.0018 - -
Sawing 0.0006 - - 0.0009 - -
After shearing
06 Burr ends (rotary file or wheel) after
sawing flange or leg 0.0005 - - 0.0009 - -
07 Hand file or wheel after
Milling or pro-filing 0.0005 - - 0.0009 - -
DE BURRING STANDARD TIME (TYPE OF OPERATIONS)

Calculation of time per part:

Burring 1)- Determine length of part and type of burring operation


2)- Multiply the burr operation from –III
(chart ‘C’ by standard per edge, inch, square inch or hole)

Handling: Add handling time per length of part from –II(chart-B)


to burr time to obtain unit time.

Example:

Sand drum burr, part-8” long one edge up o 10” ½ to 3lbs


Burr time = 0.0012
Handling time per job
Clamped to table = 0.0042
-------------------------------------------------
Time per part= 0.0054
Setup from chart –I = 0.15
-------------------------------------------------
0.1554
Description Standard Time
1)Set up time 21-minutes
2)parts handling time 0.35min/part
F 3)Wash surface with solvent 0.05min/30CM²
4)Spray paint (double this for 2-passes) 0.5min/30CM²
5)Brush Painting 0.25min/30CM²
6)Apply Masking Tape 0.12min/25CM
7)Removing Masking Tape 0.26min/25CM