1. (Suggested)
5. Impact Assessment (required): Should take less than 4-5 hours with minimal service impact
and low risk.
6. Requirements, Assumptions, & Best Practices (where applicable): Since the activities will be
done in customer’s existing site, the following procedure must be completed
5. Record existing configuration and alarm. The configuration and alarm must be
recorded via Moshell and RBS Element Manager.
7. Pre-check Procedures(required): Before start swap and installation, the following items
must be completed:
1. Site survey is a must before change out existing RBS and site survey
report must cover detail information related with site condition. It must
8. Configuration Procedures (where applicable): Integration RBS 6000 refers to CPI documents
“File Descriptions for Site
And MoP Method of Procedure Commissioning and Integration RBS 6000 EID-10:005062
Uen
9. Backout Procedures (required): In case of problem occurred in the change out activity which
prevents the new RBS to operate normally or functionality test NOT OK, all related party
involved in the activity must perform troubleshooting until the agreed down time limit is
achieved. The old RBS must be back in service before the down time limit is achieved. RBS
fall back action is performed when the new RBS failed to operate normally.
10. Post-Check Procedures (required): Before leaving the sites, ensure that the following action
have been performs
3. Tidy the site and leave it in the same condition as you found it.