Feasibility
Feasibility
Partner Coordinator at Circle Level and Central Level is completely responsible for
closing feasibilities on-time and with 100% accuracy.
Below are points:
(a) Partner coordinator to ensure timely allocation of Field Survey to Engineer.
(b) Survey Engineer to complete Site visit and share report to Partner Coordinator on same
day or next day morning.
(c) Survey Report should be completely filled by Engineer only and with 100% accuracy.
(d) Snaps to be captured from Maximum Possible Height from BTS as well as Customer
end. No Survey from ground.
(e) Survey has to be done from Minimum 3 BTS and can be extended in case of Not
Feasible on account of LOS/Backhaul.
(f) It’s mandatory for Field Engineer to capture existing link details available at customer
premises.
(g) Partner Coordinator to maintain Database of Survey Done and all Survey Reports
s hould be first checked by Partner Coordinator before submitting to Circle Planner.
(h) Database of all Survey done locations should be updated on tool provided by
customer
(i) Partner has to re-visit in case of any Report rejection or incorrect BTS
Selection.
(j) Partner Coordinator should share Daily Plan vs Achievement to Circle Planner.
(k) All Reports to be uploaded on space provided.
(l) SPO tool should be used for BTS
Selection.
(m) BTS Database management which
includes
(i) Correct coordinates of BTS Nodes.
(ii) Capturing details of Azimuth/Sector Make/Height for all Links (BTS+CPE).
(iii) Fiber/Microwave Path details for all Links.
Steps to be followed:
Reporting activity:
1. Daily Progress Report to be shared with Circle Planner.
2. Support Circle Planner in coordination with inter-functional teams like
Microwave Planning/Deployment for Backhaul availability & constraint cases.
3. Support Circle Planner in validating feasibilities by accessing tools like Google
Earth/Link Planning tools.
4. Support Circle Planner in Inventory Management, Planning and Reconciliation.
SLA (03 Days):
Assigned feasibility should be completed End to End within 3 Days from allocation date with
report submission, which includes Field Survey/Microwave BH Check and Plan release.
Note:
24.1. Feasibility Coordinator has to be provided by Partner at Circle Level to Planner for
managing activities being carried by Own team. No separate Commercials applicable.
24.2. Penalty applicable based upon per month/per team productivity and SLA, which
will be deducted during monthly manpower & WCC Signoff.
24.3. Commercial impact during deployment stage of link due to incorrect feasibility inputs,
will be beared by partner who had closed Feasibility.(Applicable for both Own team and
ASP).
1. Customer confirmation
1.1 Taking customer appointment for link deployment.
1.2 Updating respective Project Manager/Deployment Lead/Coordinator in case of
Customer
Related issues. Capturing local customer contact details.
1.3 Follow-up with respective Project Manager’s in case of links going ON HOLD post
reaching customer location and updating respective SPOC’s.
Return:
2.5 In case of customer Access issue, Material has to be returned to Warehouse and has
to be updated in records.
2.6 Same material can be re-issued for other location post CAM Approval from team.
4. Metasolv process.
4.1 For New BTS: Responsibilities include
(a) New Backhaul (BH) RA login.
(b) Follow-up with stakeholders like MPLS Provisioning team.
(c) Follow-up with stakeholders (MPLS Planning) for constraint orders like
Card Constraint/Ring choking other related
activities. (d) Sharing details to field team post
provisioning.
4.2 For customer RA: Responsibilities includes.
(a) Updating BH RA’s in customer RA’s.
(b) Pushing RA’s in MPLS Bin for provisioning.
(c) Updating all mandate Label & Values in ANGW line Item.
(d) Follow-up with Project manager’s in case of any rejection for LAN
IP/WAN IP
correction/updation.
(e) Follow-up with respective team for provisioning.
4.3 Sharing Provisioning Pending/Completing dashboard’s to respective stakeholders
on daily basis.
4.4 Closing respective tasks in Metasolv Order post link Completion.
4.5 Updating all mandate Labels of Metasolv for ANGW. Includes updation of Circuit
ID’s/WAN IP Ping Snaps post link delivery.
5. Konnect- Automation.
*Partners will be using Konnect tool for activities
(Manpower tracking and controlling field activities)
Note:
(i) RF Link installation i.e. P2P/P2MP or New Sector/Existing Sector should
be as per Plan release and any change should be first approved by Circle
Planner.
(ii) Partner team has to re-visit customer location in case of any
compliance issue.
(iii) Rendering of services which are not in Standard Scope, should be after prior
approval from
Circle team(Planning & Deployment)
*Partner team has to re-visit customer location in case Router termination/testing not
done. No commercial impact on Beetel.
*Partner team has to re-visit customer location in case of any compliance issue.
*Partner team has to re-visit customer location in case of any compliance issue.
*In case of Non-Compliance, Beetel reserves right to issue debit Note to Partner.
Every Partner has to provide consumption report on monthly basis.
And any Material with Partner for more than 60 days without capitalization
will lead to Debit from Monthly WCC.
*Non-Compliance if any will be liable for Legal action and may lead to Contract
Cancellation”
*In case of Non-Compliance, Beetel reserves right to issue debit Note to Partner &
Partner Invoicing can be put ON HOLD.
Note:
• Circle & Central Signoff should be closed within 1-5th date of every
month.
• Invoices to be raised only post getting signoff.
Performance Report has to be shared with respective SPOC on monthly basis and
has to be evaluated by Circle Deployment Head, post which Approval for Manpower
billing will be given. owns complete responsibility to ask for team replacement in
case of any performance or incompetency or skill set issues.
Partner has to provide replacement on immediate basis.
*Team allocated for Project, should not be involved in any other Project within
and outside organization.
*Team allocated should not be involved in any Illegal Activity.
*Team movement/replacement if any should be done only after getting Approval from
Circle & Central
team (Approval should be taken from both teams).
* Reserves right to discontinue with Partner in case of performance issue (Consecutive
2 Months failure on Performance parameters).
*Delivery timeliness, Performance measurement parameters may change based upon
requirement and
Partner has to abide and honor the same.
* reserve rights to discontinue Partner Services with 1 Month Notice.
20. Mandate requirements for all field resources (Includes Engineer &
Technician).
20.1 ESIC No. (Applicable for Coordinators/Project Manager also)
20.2 Group Insurance policy. (Applicable for Coordinators/Project Manager also)
20.3 Medical insurance. (Applicable for Coordinators/Project Manager also)
20.4 Tower climbing certificate.
20.5 Complete safety kit for climbing towers and with Standard Helmet & shoes.
20.6 Smart phones(4G Handset with Data enabled SIM)
20.7 Toolkit with Standard Tools(As per Guidelines)
20.8 Company ID Card & Authorization Letter.
20.9 Motor-Bike mandatory for local travel with valid driving license and complete
documents as per LMV policy.
*Above is per team requirement.
Its responsibility of Partner to ensure safety of Field Engineer/technician Onsite and
Off-site and Beetel will not be responsible in case of any incident.
*Partner Project Manager to do field audit of at least 10% of sites delivered within a
month across circles and provide report to with complete Snaps and other justifications.
*Partner team has to do re-visit, in case of any downcall or performance issue reported
within
1 month of link delivery or “Repeat Fault Cases”.
*Audit Report of all audited sites within a month has to be shared with Circle SPOC
and need Acceptance confirmation from Circle Deployment Head.
Site Audit Report has to be submitted to Central team and should be attached with
Monthly
Work Completion Certificate.
23. NSDC Design process and Maintaining Network Utilization database for
active element which includes timely up gradation/addition/shifting activities.
This includes:
• Design of all New Link. Like defining line Items required for link design.
• Sharing Line Item information to respective Project Manager’s for Metasolv Customer
RA generation process.
• Creating designs for BH RA’s in case of New P2MP BTS nodes.
• Maintaining L2 POI utilization
• Triggering Circle team for addition of New L2 POI’s when existing POI utilization
reaches 75%.
• Follow-up with Circle team for integration of new L2 POI’s.
• Triggering Circle team for addition of New Egates.
• Logging RA for New Egates and sharing details with Circle team for
immediate implementation.
• Follow-up with Circle team for New Egate Integration.
• Getting Acceptance testing for New Egate’s and L2 POIs as per process.
Qualification:
• Engineer should be B.E or B.Tech in Electronics & Communications with minimum 2-3
Years of relevant Experience.
• Technician should be having Diploma or ITI with 2-3 years of relevant experience.
*Educational qualification proof has to be shared with Circle & Central team.
• Team should be having Smart Phone with 4G SIM.
• Laptop with Data Card and SERIAL or Console Port.
• Laptop should have licensed & Original updated Anti-virus file. (f) Bike with Driving
License and valid Identification proof.
• Medical insurance & ESIC
• Tower climbing certificate. Applicable for both Engineer &
Technician.
• Valid Medical Fitness certificate.
• Skills with basic knowledge of RF Installation/tuning and troubleshooting.
Note:
1. Team assigned for Project cannot be used for any other Project.
2. No Equipment/Resource/accessories can be used for any other project.
3. Information Security need to be maintained and in case of any breach, Legal
clause applicable on respective Partner Organization.
4. Team assigned should not be involved in illegal activities or Schemes.
5. Any additional team requirement should be full filled within 15 days of go ahead.
*Post 3000 Km, Convenience can be claimed as per current Rate contract, which has to
be approved by
Beetel SPOC.
*Clusters/Zones are pre-defined for Operations team only and in case of any special
requirement or exception team may have to complete activities of other nearby zone also
(as per allocation by customer).
*Deployment team will be located based upon Workable Funnel and team movement
should be done on immediate basis within same circle and in other circle within 7 days. No
Movement/other charges applicable.
*Re-clustering can be done by end customer and specified teams should be relocated
within 7 days of communication.
*team movement will be based upon actual Work load and can be intra Circle, without
any commercial obligations on .
Note:
Any Non-compliance on Invoices submitted or process will be considered under Code of
Conduct
Violation and legal actions applicable.
Requirement below:
(a) Maintaining current Stock available with teams.
(b) Maintaining current Stock available in Circle Warehouse in coordination with
Warehouse team and local SCM.
(c) Proactive alerts to respective teams in case of Shortfalls.
(d) Separate Stock Maintenance for Deployment & Operations.
(e) Timely reporting to Circle & Central team in case of any Quality issue with Stock or
mismatch
(f) Material issued from Warehouse should be send immediately to Customer location
and in case of HOLD, has to be taken back and either should be returned to
Warehouse or should be kept in Partner Warehouse.
(g) It’s mandatory to report Stock Availability in Partner Warehouse on regular intervals.
(h) Partner Circle Project Manager should visit their Warehouse on Monthly basis and
should ensure that Material is kept in proper Hygienic condition.
(i) Monthly Report should be provided to Circle Head and Planner on Material available
in Field and in Partner Warehouse.
Note:
PO issued and valid only for current financial year only and unused PO’s will be
automatically closed at the end of year closure.
Beetel reserves complete rights to cancel any PO at any point of time, in case of issues
related to performance/quality of supplied material.
Beetel will not entertain any Bills after 180 days of WCC/Signoff.
End Customer will measure performance of each partner Circle-wise bases on below:
Productivity:
(a) No of links deployed by team in a month should be 15.
(b) No of feasibilities closed by team in a month should be Minimum 15 per team.
SLA:
(c) 3 Days for deployment per team upto 3m & Infra ready/existing cases including
Circuit ID generation.
(d) 4 days for deployment per team >3m upto 6m including Circuit Id generation.
(e) 2 days for completing feasibility from date of allocation with Survey Report submission.
Fault within 30 days*
Fault within 30 days/60 days are 2 parameters which will be monitored for team
performance measurement of Quality installation.
Penalty calculation will be as per below and Invoice/WCC Signoff should be done accordingly.
Penalt
KPI' Parameters y Value Remarks
s
<90 2%
%
SLA* <80 5%
%
<60 10% Penalty will be on
%
<50 20% Circle Deployment
%
<90 2% Manpower Billed for
month
%
<80 5%
Productivity** %
<60 10%
%
<50 20%
%
>5 5%
Fault within 30 days*** %
>10 10%
%
*SLA for Feasibility & Deployment will be counted separately and accordingly above
penalty liable.
*** Fault will be calculated based upon O&M Performance report as per Central.
Note: Beetel reserves right to Cancel Partner contract, in case of performance issue for
consecutive 2 Months.
Reward
KPI's Parameters Reward Values Remark
SLA* >95% 2% s Circle Manpower Billing
*Reward will be on
95-100% 1% for month.
Productivity >100%
2% *SLA will be calculated separately for
Deployment & Feasibility
Appended below is “Overview of Process Work flow” & detailed “Scope of Work”.
Complete Scope:
Step 1: Go ahead to partner for Feasibility.
Step 2: Field Feasibility and report submission to Circle Planner.
Field Engineer completes RF Site Survey.
During Customer Site Readiness survey, check Rack space available for Router
Installation. Check AC Power Source with earthing parameters. Mandatory for both RF
devices and Router.
(RF Devices and Router to be install with AC Power source only. Exceptions to be
highlighted to Circle Planner & accordingly approved).
UPS should be available with separate power supply for both
devices. Site Readiness parameters to be captured with at most
accuracy. Submit report to Circle Planner.
Circle Planner validates input received & release plan accordingly,
Push order for deployment.
Step 3: Material issuance and dispatch.
Partner Coordinator to check if Order is “RF+Router” or “RF only”.
(Router scope will be applicable only for Managed links)
Circle Coordinator to raise request for Locator Id generation.
Locator ID can be common or different for both Material and Customer end Router.
Material to be picked from Warehouse as per requirement.
(Warehouse can be common or separate for both Router and RF Material).
Dispatch material to Customer location only post permission confirmation.
(In case of permission issue post reaching customer site complete material should be
picked up from Customer location and to be updated in Metasolv with proper remarks).
Material reconciliation is under partner scope.
Step 4. E2E Link Installation.
E2E Link installation= RF+ Router Installation.
Post RF Installation and link testing on laptop, Field Engineer install CPE
Router. Scope includes: Installation/Power ON/Commissioning/testing &
Maintenance. Proper labelling to be done on all devices.
Router’s to be installed on RACK Space provided by Customer.
In case of RACK Space unavailability during deployment phase, proper communication
to be shared with Circle team and Project Manager.
Link integration to be done only after getting confirmation from Circle team. Circle
team or Project Manager Follow-up with end customer for resolution.
Post Installation and integration, Field Engineer to take signoff from end customer on
Work Completion.
Installation & router commissioning is completely under partner
scope. Router Configuration includes:
(i) Login to router using Console cable.
(ii) Configuring WAN IP and other service profile creation as per
requirement.
(iii) E2E reachability test.
(iv) Following-up with Customer contact for link testing and
acceptance.
(v) Resolve customer technical challenges if any.
(vi) Take support from Backend team.
(vii) Following up with inter-functional teams
(MPLS/SDH/NPT/EPT/CIENA/Others/Router OEM & support team).
(viii) In case of configuration issues related to OEM, to be taken up with respective
OEM and should be closed.
(ix) Replacement any on account of device failure/malfunctioning during Deployment
Phase or Operations phase will be under partner Scope.
(x) Partner to inform customer team in case of device failure and replace device
with available spare.
Signoff includes:
RF Installation & testing
Router installation at CPE.
Complete Circuit details to be updated in signoff sheet.
Device Serial Nos and MAC address to be updated in signoff sheet and Metasolv
against
Customer RA.
Management IP’s and WAN IP’s to be updated in signoff sheet.
Signoff valid should be taken from end customer with their complete details like
Name/Contact
No/Email ID.
RMA:
Partner will be responsible for E2E inventory management which involves:
• Replacing faulty hardware from Customer place.
• Sending fault reported hardware for RMA
• Follow-up with OEM for resolution.
• Testing replaced hardware
• Spare management.
Revisit:
Re-visits if any on account of “Quality of installation/link failure during handover stage/link
failure/flapping within 1 month of Circuit Id release/any kind of communication gaps
reported” will be done by partner. No commercials applicable.
Operations
5. Network Optimization
Network Optimization activity is to have better customer experience and simplification of
network. Below activities will be under scope of Operations team.
(E) IP Pool Extension.
(F) Backhaul shifting from Electrical to Ethernet.
(G) Backhaul Upgradation i.e. Fiber/Microwave.
(H) Link shifting from Highly Utilized Routers.
(I) RF device Optimization i.e. Frequency change/Height increase or decrease/Sector
replacement. (J) Link shifting from P2P to P2MP.
Penalty & Rewards
Penalty calculation will be as per below and Invoice/WCC Signoff should be done accordingly
Penalt
KPI's Paramet Valuy Remarks
er s e
<90% 2%
<80% 5%
SLA*
<60% 10%
Penalty will be on Circle Operation Manpower
<50% 20% Billed for month
>10% 5%
>20% 10%
Fault Rate**
>40% 20%
>50% 40%
>5% 10%
Repeat Fault within 30
>10% 20%
days***
*Fault Rate Calculation is based on attributed Fault i.e. in relation to .
Rewards:
Performance will be measured on basis of overall team available in a Circle
Reward
KPI's Parameters Reward s Remark
SLA* >95% Value2% s
<5% 2% *Reward will be on Circle Manpower Billing
Fault Rate <2% for month.
5% *SLA will be calculated separately for Deployment &
Feasibility
*Partner team has to re-visit customer location in case Router termination/testing not
done. No commercial impact on Customer.
RMA:
Partner will be responsible for E2E inventory management which involves:
2. Replacing faulty hardware from Customer place.
3. Sending fault reported hardware for RMA
4. Follow-up with OEM for resolution.
5. Testing replaced hardware
6. Spare management.
53. Penalty
Penalty calculation will be as per below and Invoice/WCC Signoff should be done
accordingly.
For Large projects penalty and SLA will be as per timeline and penalty
agreed with customer.
Data Security is under Zero Tolerance and any non-compliance issues will be taken on serious
notes.
It’s primarily responsibility of Partner to take care of Customer Site Database. Same should
not be shared in any form and in any case to any un-authorized person in any ways
Price Consideration
Item Code Unit of
Item/Service Description Unit Rate-INR
Measure