UPDATE AS OF 9-11-2023
Work Package Progress
Activity ID Activity Name Original BL1 Start BL1 Finish Start Finish Budgeted Total Cost Earned Value Cost Schedule % Performance %
Duration Complete Complete
Total 1249 30-May-22 26-Nov-25 21-May-22 A 04-Jul-26 SAR3,209,743,463.09 SAR473,270,652.89 50.49% 14.74%
GENERAL ARRANGEMENT 441 12-Jul-22 16-Aug-23 03-Jul-22 A 18-Feb-24 SAR14,458,672.44 SAR12,805,309.30 100% 88.56%
GEO-TECHNICAL INVESTIGATION 742 02-Jul-22 03-Dec-23 02-Jul-22 A 03-Dec-24 SAR1,961,971.35 SAR1,602,459.05 98.02% 81.68%
EXCAVATION 728 27-Jun-22 14-Apr-24 07-Jun-22 A 03-Dec-24 SAR269,634,882.34 SAR189,345,500.20 94.44% 70.22%
SOIL IMPROVEMENT 679 29-Aug-22 22-Apr-24 06-Dec-22 A 11-Dec-24 SAR88,278,482.18 SAR40,740,097.81 94.44% 46.15%
DEWATERING 884 09-Aug-22 14-Nov-24 05-Oct-22 A 30-Jun-25 SAR40,290,269.77 SAR7,301,396.70 69.61% 18.12%
CONCRETE 1208 27-Jun-22 19-Oct-25 27-Jun-22 A 14-Jun-26 SAR1,544,419,000.61 SAR124,943,850.70 53.33% 8.09%
UTILITIES 1141 10-Sep-22 06-Sep-25 21-Sep-22 A 17-Jun-26 SAR403,602,499.62 SAR5,445,793.59 46.2% 1.35%
GENERAL 1249 30-May-22 26-Nov-25 21-May-22 A 04-Jul-26 SAR202,145,430.00 SAR91,086,245.54 46.64% 45.06%