204E-005
Sr. no Description Duration
1 Material collection Before S/D
2 Blinding of Exchanger Tube and Shell side 6 hrs
3 Removal of Channel head 4 hrs
4 Removal of Tube bundle 8 hrs
5 Deliver to washing bay for hydro jetting 2 hrs
6 Air blow of tubes 4 hrs
7 shifting from washing bay to site location 2 hrs
8 Installation of Tube bundle 8 hrs
9 Box-up Channel head 4 hrs
10 De-blinding of exchanger tube and shell side 6 hrs
11 leak test 4 hrs
Total Hours 48 hrs
Notes:-
Inspection and hydro jetting of tube bundle work duration not mention in above list.
Hot bolting and Material collection (Blind & Gasket) not mention in above list.