SHAKAMBHARI ISPAT & POWER LIMITED

SHUTDOWN JOB LIST FOR CASTERS


DIVISION : SMS CCM 1 Date: 6/4/2021
Sr. No. Job Description Required Materials Availability of spare Time to completion Remarks
Parallel Beam 12 mtr
1 Tundish car trolly beam change 10 Hrs
length Yes
2 Appron Jam Cutting 3-4 days
1st Zone Riser Header pipeline Riser pipe ,130 sqmm
3 1 set Available 6 Hours
modification Ring,header
Steam Exhaust blower fan
4 6-8 Hours
repairing

Withdrawl arm pin & bush


Pin , Bush &
5 change and damaged portion Yes 3 Days
Aluminium Paint
repairand painting

Bearing not
6 Withdrawl centre roller change Withdrawl Roller 6 Hours
available

Civil foundation of DRT & extra


7 CIVIL foundation for speed 2 Days
modification of DRT

DRT Roller chain sprocket Roller,Duplex Chain


8 Yes 1 Days
change & roller allignment Sprocket,Duplex Chain

DIVISION : SMS CCM 2


Sr. No. Job Description Required Materials Availability of spare Time to completion Remarks

New ladle hanger change & rectify


1 Ladle Hanger Tomorrow get 6 Hours
the all hangers pin & Bush

Three strands DRT Roller Table


2 allignment & chain sprocket Yes 6 Hours
checked

3 Cooling zone proper allignment Yes 4 Hours

Allignment Roller,if
4 Allignment Roller check Yes 4 Hours
changeable

Withdrawl Roller bearing check & Bearing 22222 E No 5 Hours


5 centre roller bearing check
Hydraulic Pipeline of pusher total 4 Hours
6 checking

DIVISION : SMS CCM 3


Sr. No. Job Description Required Materials Availability of spare Time to completion Remarks

Withdrawl Hydraulic Powerpack


1 5 Hours
Heat Exchanger cleaning

Heat Exchanger installed in shearing


2 Yes 4 Hours
machine powerpack

Shearing machine hydraulic


3 powerpack heat exchanger new line 1.1/2" GI Pipe Yes 4 Hours
connection
Shearing machine St no 3 Rail line
4 Rail Line 40 mm Yes 8 Hours
Change
5 Ladle car platform repaire 6 Hours