Machines/Components
Section Machine Name Total M/C Breakdown Duration Category of Breakdown
under breakdown
Soft Winding Winding M/C 25 12 Spindle (head) 24 hr Mechanical +Electrical Problem
Yarn Dyeing Dyeing M/C F 42 22 hr Main Tank Drain Problem
Yarn Dyeing Dyeing M/C 108 F 108/3 11 hr MainTank Level Problem
Yarn Dyeing Dyeing M/C GF 1020/2 25 min Lid Lock Problem
Yarn Dyeing RF Dryer
Yarn Dyeing RF Dryer 4
Yarn Dyeing RF Dryer
Yarn Dyeing Hydro 8
Hard Winding HD Winding M/C 30 6 Spindle (head) 24 hr Mechanical +Electrical
Hard Winding Doubling 1
Hard Winding Twisting 7
Warping & Sizing Warping Rabatex M/C 4 1hr 30 min Electrical +mechanical
8
Warping & Sizing Warping
Warping & Sizing Sizing 3
Dyeing Lab Lab Machines 27
Dyeing Lab Verivide Light Box 10
Bobbin Machine
Weaving 5
Knotting Machine
Weaving 5
110 loom stopes at Power,Air Pressure,AC Plant
Weaving Loom 376 1 hr 14 min
various times Problem
Pretreatment Singeing Osthoff Singeing M/C 5 hr 10 min
2
Pretreatment Singeing
Pretreatment Bleaching 2 Bleach Machine 01 45 min
Pretreatment Mercerizing 1
Solid Dyeing C.P.B 3
Solid Dyeing Padsteam machine 1 Pad Steam Machine 9hr 20 min
Solid Dyeing Jigger oven dyeing 1 Jigger M/C 2 month 112days Programming Problem
Solid Dyeing Thermosol 1
Solid Dyeing Batching machine 1
Solid Dyeing Lab S/D Lab Machines 17
Finishing Stenter Stenter 02 1 hr 50 min Wheel brush belt problem
Finishing Stenter
Finishing Stenter 4
Finishing Stenter
Finishing Stenter
Finishing Sanforizing 3
Finishing Brush M/C 4
Finishing Biancaloni (AIRO) 1
Finishing Folding Machine 1
Grey & FI Inspection Grey & FI Inspection M/C FI 09 40 min Switch Problem
19
Grey & FI Inspection Grey & FI Inspection M/C GI 01 3 hr 45 min EL Guider Problem
Lift Lift 7
Sample Warping Machine
R&D 4