Activity Hazard Analysis

Note: Workers must review the requirements of the AHA prior to starting work.
The AHA must be available at the job site during work activities.

Activity: Painting and applying other coating products


Project: Renovation Project Building 102 Al Sayliyah Camp

HAZARDS
ACTIONS TO ELIMINATE OR MINIMIZE
JOB STEP HAZARDS
EACH HAZARD
Ensure all unassociated areas are covered and secured with
Protect adjacent areas Damage to property
plastic, drop cloths, etc.
Maintain current SDS for chemicals being used onsite.
When using chemicals, choose the proper PPE as per the SDS.
Respirators or dust masks may be required, depending on the
activity. Respirator use in accordance with Respiratory
Protection Program, including medical evaluation and fit
testing.
Chemical exposure
HEPA filtration may be required.
Adequate ventilation will be maintained.

Eye wash station will be available.

Use of products
Wash up after use of products.
Keep work area clear of clutter.
Trips/falls
Proper use of ladders and stepladders (i.e., will not be used in
closed position, etc.) according to OSHA 1926.1053.
Wear eye protection and gloves.

Keep paint container on level surface.


Splashes
Paint slowly.
PPE
MINIMUM PPE REQUIRMENTS FOR ALL JOB STEPS SPECIAL PPE REQUIREMENTS
NA
1) Hard Hats
2) Googles
3) Hand Gloves – Nitrile, latex, or neoprene
4) Respiratory Masks
Identify steps requiring special PPE: NA
5) Safety Shoes
6) Cover All’s

EQUIPMENT
TOOLS AND EQUIPMENT INSPECTION CRITERIA
Daily inspection of ladders for any sign of damage, wear or malfunction. Check for
1) Ladders cracks, dents or deformities that may affect performances or safety. Have inspection
tags placed on the ladders. Ensure that the hinges operate smoothly and securely.
Overall condition, Platform and guardrails, Controls and operations, Stability and
2) Scissor Lift/Man Lift leveling, Safety features, Tires and Wheels, Electrical System, Documentation and
Certification, Operators training and Manuals, Emergency Procedures.
Overall structure, Baseplate and foundation, Guardrails and Toe Boards, Access and
3) Scaffolding Egress, Platform Stability, Capacity and Loading, Ties and Bracing, Weather
Condition, Documentation and Certification, Training and Supervision,
Condition and Functionality, Cleanliness, Accuracy and Calibration, Safety Features,
4) Painting Brushes, Rollers, Paint Trays, Drop cloth or Plastic Sheets to protect
Compatibility and Suitability, Proper Storage and Maintenance, Ergonomics and
the surfaces, Paint Scraper, Extension poles for rollers, Sprayers if any, power
Comfort, Compliance and Regulation (e.g. OSHA regulation for electrical
cords and Plugs
equipment, VOC emission standards for Paint sprayer)

OSHA-RELATED TRAINING APPLICABLE TO THIS ACTIVITY i


Hazard Communication Training Ladder Safety Training
Respiratory Protection Training Electrical Safety Training
Personal Protective Equipment Training Fire Safety and Fire Extinguisher Training
Hazardous Waste Operations and Emergency Response
Fall Protection Training

Preparer
Name and signature of person who filled out this AHA: Anoop Anil Kumar Date: 28/3/2024

By signing this AHA, the preparer is certifying that the information provided is true, and that any change in the conditions described in this AHA or inadequacies found for
protecting employees during the activity may require a revision to this AHA.
Acceptance by V2X personnelii
Name and signature of Project Administrator: Date:

Name and signature of EHS POC: Date:

i
Copies of training certificates must be included with this AHA, with Project-Specific Plans, and/or with the contractor’s APP.
ii
This AHA and other applicable safety documents must be accepted by V2X prior to commencing project work.