You are on page 1of 1

HUNGARY GLASS PACKAGING FACTORY INVESTMENT SANİTARY İNSTALLATİON

WORKS
Scope Sanitary İnstallation Works Document no HSCM-QC-ITP-013
BOQ no 14.03.000.0000 Inspection and Test Plan for Sanitary İnstallation Works Revision 00
ITP No ITP-004 Submittal Date
Control Category
Activity Inspection
Description Inspection Method References Acceptance Criteria
no Frequency Sub- Project
Contractor Employer
Contractor Director
1 MATERIALS
1.1 Control of pipes and insulation products to be used. 100% H Certificate Check Material Submittal,Project Specification Material Submittal,Project Specification

1.2 Pipe Fitting Equipment (Bolt, DObel, Rod, Profile, Clip). 100% H Certificate Check Material Submittal,Project Specification Material Submittal,Project Specification

1.3 Sanitary Equipment (Drainer, Closet, Armature, Accessories,Pump,Water tank). 100% H Certificate Check Material Submittal,Project Specification Material Submittal,Project Specification

2 INSTALLATİON
2.1 Pipe Installation as per approved drawings. 100% W Visual Check-Drawings Check Approved Drawing,DIN Standards Approved Drawing,DIN Standards

2.2 Valve and Accessory Assembly Control. 100% W Visual Check-Drawings Check Approved Drawing,DIN Standards Approved Drawing,DIN Standards

2.3 Hangers and support installation support spacing,ducting route,reinforcement & hangers. 100% Visual Check-Drawings Check DIN Standards,Project specification,Approved DIN Standards,,Project
W Drawing,MOS specification,Approved Drawing,MOS

2.4 In-wall pipe installation control. 100% W Visual Check-Drawings Check DIN Standards,Project specification,MOS DIN Standards,,Project specification,MOS

2.5 Control of in-wall equipment installation. 100% W Visual Check-Drawings Check DIN Standards,Project specification,MOS DIN Standards,,Project specification,MOS

2.6 PVC pipe slope control. 100% Visual Check-Drawings Check DIN Standards,Project specification,Approved DIN Standards,,Project
W Drawing,MOS specification,Approved Drawing,MOS

2.7 Pipe insulation installation as per drawing,check the insulation band spacing as per drawing. 100% W Visual Check-Drawings Check DIN Standards,Project specification,MOS DIN Standards,,Project specification,MOS

3 EQUIPMENT INSTALLATİON
3.1 Equipment Foundation Location Check as per Approved Drawing. 100% H Survey check-Drawings Check Approved Drawing,Project specification Approved Drawing,Project specification

3.2 Sanitary Equipment (Drainer, Closet, Armature, Accessories,Pump,Water tank) Check as per Approved Drawing. 100% W Visual Check-Drawings Check Approved Drawing,Project specification Approved Drawing,Project specification

3.3 Verify unit Installation is as per approved Drawing, Check Vibration pad Place Beneath the Package Equipment installation. 100% W Visual Check-Drawings Check Approved Drawing,Project specification Approved Drawing,Project specification

4 FINAL INSPECTION
4.1 Calibration of test equipment. 100% H Document Review Accredited Firm / Site Verification As Per Report

4.2 PVC pipe fullness test. 100% W Visual Check-Drawings Check Approved Drawing,Project specification,MOS Approved Drawing,Project
specification,MOS

4.3 PPRC ande Galvanize pipe check for leak test for pipe installation. 100% W Visual Check,Sealing Check Approved Drawing,Project specification,MOS Approved Drawing,Project
specification,MOS

4.4 Control of Tightness Tests of Pipes (Hydrostatic Test, 1.5 times the operating pressure 24 hours). 100% W Visual Check,Sealing Check Approved Drawing,Project specification Approved Drawing,Project specification

4.5 Insulation Control of Test Completed Pipes. 100% H Form Check,Visual Check Approved Drawing,Project specification Approved Drawing,Project specification

Preparared by Reviewed by Approved by

H= Hold Point
W= Witness point
S= Surveillance Point
T= Test point
R= Review of Records

_x000D_ Bu dokümanda HASSAS bilgi bulunmamaktadır. / This document does not contain SENSITIVE information.
#

You might also like