Professional Documents
Culture Documents
Established under
Submitted to
THE COMMISSIONER OF TEXTILES
Government of Tamilnadu, Chennai
Prepared by
MAGRO PROJECTS
PROJECT MANAGEMENT CONSULTANT
58/2 New Teachers colony Road, Erode 638011 India.
2
INDEX
Executive Summary
1 3
Background of the project
2 11
Special Purpose Vehicle (SPV)
3 16
Project Components
4 21
4.1 Land
21
4.2 Common Infrastructure
26
4.3 Common Facilities
28
4.4 Factory Buildings for Production purposes
30
4.5 Plant and Machinery
38
4.6 Consolidation of Project Components
40
Power and Water Requirements
5 42
Statutory Compliances
6 43
Means of Finance
7 44
Viability of the Project
8 47
Socio-Economic Benefits
9 53
Sustainability of the Project
10 55
Implementation Schedule
11 57
Other Details
12 58
Affidavit by SPV
13 59
Annexures ( Relevant Documents)
14 60
3
Name of the A Mini Textile Park to cater to the needs of four Entrepreneurs of
Project the Tiruvallur Textile Cluster has been planned to be established
to meet the Processing, Packing requirements of their Products like
Lungi, Churidhar and Sarees @ TIRUPATHI MINI TEXTILE PARK
LLP, in Tiruvallur Dt.
Name of SPV TIRUPATHI MINI TEXTILE PARK LLP
The above facility in MTP will enhance their Product quality and increase
their Production in green and clean environment and support to meet the
large demands in the domestic market.
As such, the location of the proposed Park is well placed in terms of Road,
Railway, Sea Port and Airport connectivity.
5
Land for the above park is proposed at an area of 2.22 acres and it has been
registered in the name of the SPV. The proposed Land use distribution pattern
for the park is presented in the Table below:
Land
THE LAND DISTRIBUTION %
LAND
% OF
NAME OF THE FACILITY REQUIRED IN
DISTRIBUTION
ACRES
The proposed land use pattern will be in line with the development guidelines
laid out by the Government of Tamil Nadu in the Directorate of Town and
Country Planning (DTCP) norms.
The value of the registered land is Rs. 3.96 Lakhs Lease Value For 33 Years
The market value of the land is Rs 2.22 Crores for 2.22 Acres
6
3 Drainage -- 06.00
5 Streetlights -- 03.00
Common Effluent
7 0.30 120.00
Treatment Plant
2. Common Facilities:
Amount
Common Building Land
S.No (Rs in
Facilities required required
lakh)
1 Testing Lab 250 0.03 10.90
2 Trade center 1000 0.07 23.60
3 Canteen 500 0.04 11.80
4 Office 250 0.04 5.90
5 Parking 0.15 5.00
Total 0.33 57.20
7
Land Amount
Name of the Building
S.No Activity required (Rs in
member unit Area
in Acres lakh)
SIVAKUMAR
1 DYEING 0.29 6000 90.00
TEXTILES
SIZING &
2 T.G.R TEX 0.29 6000 90.00
WARPING
YUVARAJA
3 0.15 3000 45.00
TEXTILES PACKAGING
4 ANNAMALAI TEX WINDING 0.15 3000 45.00
BOILER
5 COMMON UNIT 0.03 1000 08.75
UNIT
Total 278.75
Amount
Name of the
S.No Activity Capacity Units (Rs in
member unit
lakh)
SIVAKUMAR
1 DYEING 600 Kgs 90.00
TEXTILES
SIZING &
2 T.G.R TEX 7000 Mts 45.00
WARPING
YUVARAJA
3 PACKAGING 2000 Pcs 15.00
TEXTILES
BOILER
5 COMMON UNIT 27.00
UNIT
Total 222.00
8
Backup
Power
Transformer Power /
S.No Activity Requirement
Capacity Standby
in HP
Capacity
1 DYEING 120
SIZING &
2 40
WARPING
3 2 150 KVA 150 KVA
PACKAGING
4 WINDING 60
TOTAL 222
Statutory The status of the statutory approval for the proposed project is
Compliances given under:
S. Statutory Status
No Approval
Common
2 186.00 24.54%
Infrastructure
Project Cost
S.No Details % of Share
Eligible Project (Rs. In Lakhs)
Common
Cost 1 186.00 35.64%
Infrastructure
The Means of Finance have been estimated under the MTP scheme as below:
Means of Amount
S.N
Finance Means of Finance (Rs in % of Share
o Lakh)
Implementation SL COMPLETION
ACTIVITY DESCRIPTION STATUS START DATE
Schedule NO DATE
2. BACKGROUND
The project will primarily target Micro and Small Textile Enterprises who
engaged in unorganised sector and uplift them to organised sector with plug
and play infrastructure.
Tiruvallur Textile Cluster consists of more than 20,000 Weavers doing Job work
for Lungi, Saree and Churidhar Material Manufacturers and Master Weavers.
The district consists of more than 500 Master Weavers, who regularly engaging
the 20,000 Weavers across these three segments.
There are 43485 Micro enterprises and 3586 Small enterprises and 44 large
scale enterprises engaged in the manufacturing of various products like
Leather/ Textiles/ Chemical/ engineering. Some of the economic activities
undertaken by the rural artisans are manufacturing of jute, coconut shell
and palm leaf based products, paper cups, leather, Rexene works etc.
13
Tiruvallur district is situated on the North Eastern part of Tamil Nadu and is
surrounded by Kancheepuram district in the South, Vellore district in the
West, Bay of Bengal in the East and Andhra Pradesh State in the North. The
district spreads over an area of about 3422 Sq.km. This district consists of
1 Corporation, 9 taluks, 14 blocks, 4 Municipalities and 10 town Panchayats.
The Coastal region is mostly flat while certain areas in Tiruttani and
Pallipattu taluks are undulated and even hilly. The types of soil
predominantly found are red non calcareous and coastal alluvial.
Thiruvallur district ranked the 3rd highest population size in Tamil Nadu.
Thiruvallur district has the urban population share of 64.97%. In terms of
population density, Thiruvallur district has recorded 1098 persons per
sq.km. The district Sex Ratio is 987, lower when compared to the State Sex
Ratio of the State. The district has recorded higher literacy rate (84%) as
compared with State literacy rate of 80.1%. The decadal population growth
during 2001 - 2011 was 35.3%.
14
4.Packaging – After Weaving, the Lungi, Saree and Churidhar length ( Length
between 60 to 600 Mts) Fabrics will be cut into pcs as per their requirement like
Lungi, Churidhar, Saree and Packed into single and Multiple Pieces bag and bundled
as per their market needs to distribute to various Markets under various supply
chain mode.
15
The SPV members has more than 60 Years’ Experience collectively, in yarn
Sourcing, Dyeing, Sizing, Warping, Winding, Packing, Marketing and Sales of
Lungi, Saree and Churidhar Materials across Tamilnadu and various parts of
Southern & Northern States.
Based on their experience, and present market linkages, the SPV members don’t
see any challenge in Sourcing the Raw material for own consumption and Job
work, as well as Sales of finished products. The Members have wide market
linkages across Tamilnadu and various parts of Southern & Northern States to sell
their products directly as well as through marketing Agents.
The above facility in MTP will enhance their Product quality and increase their
Production in green and clean environment and support to meet the large demands
in the domestic market.
16
3.1 DETAILS OF SPV : A Mini Textile Park to cater to the needs of four
Entrepreneurs of the Tiruvallur Textile Cluster has been planned to be
established to meet the Processing, Packing requirements of their Products
like Lungi, Churidhar and Sarees @ TIRUPATHI MINI TEXTILE PARK LLP, in
Tiruvallur Dt.
The name has been blocked at ROC and Documents submitted to ROC for
Registration. The Acknowledgement of application for LLP has been
enclosed as Annexure 1
4 Members have expressed interest to participate in the Park and the List of Members are
as below :
1) Mr.K.G. Govindasamy – Engaged in Lungi manufacturing since 1980. Going to
establish Yarn processing unit in the MTP with Cheese dyeing Technology.
2) Mr.T.G. Ramakrishnan – He is a long term Saree manufacturer and Sales person ,
having more than 20 years experience
3) Mr.M. Yuvaraja – He is a Core Lungi manufacturer and distributer with more than 15
years experience
4) Mr.K.N. Annamalai – He is engaged in the Lungi and Dress material distribution and
sales coordinator since 2014.
Land EQUITY
Name of the Building
S.No Activity required CONTRI
member unit Area
in Acres BUTION
SIVAKUMAR
1 DYEING 0.29 6000 25%
TEXTILES
SIZING &
2 T.G.R TEX 0.29 6000 25%
WARPING
YUVARAJA
3 0.15 3000
TEXTILES PACKAGING 25%
Total 100%
All The 4 SPV members have been allocated with equal shares as mentioned
in the Table below :
ISSUANCE OF
Name of the
S.No SHARE
member
3 Mr. M.Yuvaraja
25%
100%
20
Since The SPV has only 4 members , they are responsible as per the for the
following table
Responsibility
Name of the
S.No
member unit
3 Mr. M.Yuvaraja
Finance & Admin
4. PROJECT COMPONENTS
4.1 LAND
Land for the above park is proposed at an area of 2.22 acres and it has
been registered as lease for 33 Years in the name of the SPV. The Copy of
the Land Document has been enclosed as Annexure 1
Location
The proposed Park is to be situated at 16/1 part, Nediyam Village Pallipattu taluk,
Tiruvallur District, Tamil Nadu. The connectivity details are tabulated below:
DISTANCE
DESTINATION (Major landmarks)
IN KM
National Highway NH 716 CHENNAI - KADAPA 12
Railway Station – TIRUTHANI 29
Nearest Metro City - Chennai 90
Nearest Airport Chennai 100
Nearest Sea Port Chennai 110
As such, the location of the proposed Park is well placed in terms of Road, Railway,
Sea Port and Airport connectivity.
22
The Land is situated in the State Highway and near to the Industries
cluster . Hence the Location is ideal for the industry development
The proposed land use pattern will be in line with the development
guidelines laid out by the Government of Tamil Nadu in the Directorate of
Town and Country Planning (DTCP) norms.
Land for the above park is proposed at an area of 2.22 acres and it has
been registered as lease for 33 Years in the name of the SPV. Hence the
Land is under the possession of the SPV.
23
Since the CETP and other manufacturing units has advantage over
other units outside the park in terms of Operation and Maintenance
Cost, capital cost advantage, maintaining the CETP and critical
Infrastructure of the park is not a challenging factor.
The Park SPV will collect the user charges from the Sizing, Warping
Unit and Dyeing unit as per their output water to CETP and with
reference to the input water. A flow meter will be fixed at both
Collection point at unit level and inlet point at CETP.
Other unit will be charged as per their Water and Power Consumption
and Watch and ward expenses.
Statutory clearances
S. Statutory Status
No Approval
Land Distribution
Land for the above park is proposed at an area of 2.22 acres and it has been registered
in the name of the SPV. The proposed Land use distribution pattern for the park is
presented in the Table below:
The proposed land use pattern will be in line with the development guidelines laid out by
the Government of Tamil Nadu in the Directorate of Town and Country Planning (DTCP)
norms.
26
3 Drainage -- 06.00
5 Streetlights -- 03.00
Common Effluent
7 0.30 120.00
Treatment Plant
ITEM OF AMOUNT
INFRASTRUCTURE LENGTH RS / SQ FT INR
COMPOUND WALL
HEIGHT 7 1640 130 1492400
ROAD
LENGTH WIDTH AMOUNT
175 7 1225 1500625
SWD
LENGTH 350 MTS 1450 507500
WATER SUPPLY
LITRES RS / LITRE
50000 40 2000000
STREET LIGHT
NOS RS
12 25000 300000
ELECTRICITY
75 KVA TRANSFORMER 300000
INTERNAL SUPPLY SYSTEMS 400000
700000
12 street lights at the side of the internal drive way and CETP
yard, RO plant, Boiler and parking area has been planned with
Solar lights with automatic on and off at regular time intervals.
Amount
Common Building Land
S.No (Rs in
Facilities required required
lakh)
1 Testing Lab 250 0.03 10.90
2 Trade center 1000 0.07 23.60
3 Canteen 500 0.04 11.80
4 Office 250 0.04 5.90
5 Parking 0.15 5.00
Total 0.33 57.20
Description
Area allotted : An area of 0.33 Acre has been allotted for the
above common facilities in the MTP.
The Office space will be a centre for managing the Finance and
Operations of the park with minimum staff workstation.
Amount
Facility Building
S.No Sq ft rate (Rs in
Description required
lakh)
1 Testing Lab 250 2360 10.90
2 Trade center 1000 2360 23.60
3 Canteen 500 2360 11.80
4 Office 250 2360 5.90
5 Parking 2000 250 5.00
Total 57.20
30
Land Amount
Name of the Building
S.No Activity required (Rs in
member unit Area
in Acres lakh)
SIVAKUMAR
1 DYEING 0.29 6000 90.00
TEXTILES
SIZING &
2 T.G.R TEX 0.29 6000 90.00
WARPING
YUVARAJA
3 0.15 3000 45.00
TEXTILES PACKAGING
4 ANNAMALAI TEX WINDING 0.15 3000 45.00
BOILER
5 COMMON UNIT 0.03 1000 08.75
UNIT
Total 278.75
Amount
NAME OF THE BUILDING RATE /
S.No (Rs in
UNIT AREA SQ FT
lakh)
SIVAKUMAR
1 6000 1500 90.00
TEXTILES
YUVARAJA
3 3000 1500 45.00
TEXTILES
278.25
32
OSR
903.20 SQM
Screening
chamber
1.2000 0.2284
secptic
RWH_CAPACITY_L=5000LTRS 115 thk. brick wall
tank
8.8738
36.8903
7.0600
INSIDE
17.8814
Building Line
S.T.P
1.8147
Slope 1 in 20
5 to 7.5 c.m.
rounded size pebbles
1.1998
WASTE
DISPOSAL
SECURITY
33.9759
2.45mx2.45m
ENTRY E
EXIT /
7.0m GAT
48.3336
21.1601
33.6111
PROPOSED FACTO
RY
BLOCK-III
25.2480
7.0m DRIVEWAY
ramp slope
SLOPE=1IN15
3.9867
1.8
parking 10
15
20
1.5M DRIVEWAY
1 Cycle 1.0
parking 10 1.0
1.8
15
1.8
20
ramp slope
SLOPE=1IN15
3.9867
parking
2.0000
10
15
20
1.5M DRIVEWAY
1 Cycle 1.0
parking 10 1.0
1.8
15
1.8
20
PROPOSED FACTO
RY
BLOCK-I
ramp slope
SLOPE=1IN15
PROPOSED FACTORY
SLOPE=1IN15
2.0000
7.0m DRIVEWAY
M
.0
10
3.
50 5
M
LORRY PARKING
M
.0
10
3.
50
M
M
.0
10
3.
50
1
M
0.30
GL SITE BOUNDARY
Plinth beam
EXISTING ROAD
RCC M25 Grade Concrete
3" 3" 6" tk.P.C.C. 1:5:10
Sewage
inlet
PROPOSED BUILDING
BAR
2.50 6" tk.Sand filling SCREEN
SECTION - 'AA'
EQUALIZATION FLUIDIZED TUBE CLARIFIED PSF ACF FINAL
As per design BED SETTLER WATER COLLECTION
BIO TANK TANK
ACTOR
BLOWER Sewage
SLOPE
outlet
SLUDGE LIQUID
COLLECTION TO
A A PUMP TANK FILTER EQUALIZATION
PRESS TANK
EDGE OF 10' PSF PRESSURE
SLOPE SLOPE
P.C.C SOLID
ACF ACTIVATED TO
0.30 CARBON
FILTER COMPOSIT
EDGE OF
R.C.C /DEPOSIT
SLOPE
2.50
PLAN
As per design
Typical Column Foundation Detail
As per design
0.15
0.40
Inlet
Scale -1:50
0.90
(1.05)
1500 HIGH
33
Winding
After being spun and plied, the cotton thread is taken to a warping room where the winding machine
takes the required length of yarn and winds it onto warpers bobbins
Warping or beaming
Sizing
This is the process of strengthening the
warp by adding starch to reduce breakage
of the yarns.
Ends and Picks: Picks refer to the weft, ends refer to the warp. The coarseness of the cloth can
be expressed as the number of picks and ends per quarter inch square, or per inch square. Ends
34
is always written first. For example: Heavy domestics are made from coarse yarns, such as 10's
to 14's warp and weft, and about 48 ends and 52 picks.
PROCESSING
Processing – The grey cloth, woven cotton fabric in its loom-state, not only contains
impurities, including warp size, but requires further treatment in order to develop its full
textile potential. Furthermore, it may receive considerable added value by applying one or
more finishing processes.
Processing is a broad term used for processing and finishing of fabric. A wide range of
products can be created by following different steps of activities/processes.
The flow chart of the process is as follows:
35
Processing
Grey Fabric
from Store
Singeing &
De sizing
The flow is for processing the
Batch Rotating Grey Fabric. An alternative is
& washing weaving Dyes Yarn. That
with enzymes involves dyeing the
Yarn before weaving
Mercerisati
on
Full Bleach /
Dyeing/ Printing?
Printing
Full Dyeing (Localized
Bleach
Finishing
Dispatch
/Store
Singeing
Singeing is designed to burn off the surface fibres from the fabric to produce smoothness. The
fabric passes over brushes to raise the fibres, then passes over a plate heated by gas flames.
De-sizing
Depending on the size that has been used, the cloth may be steeped in a dilute acid and then
rinsed, or enzymes may be used to break down the size.
36
Washing/Scouring
Scouring, is a chemical washing process carried out on cotton fabric to remove natural wax
and non-fibrous impurities (eg: the remains of seed fragments) from the fibres and any added
soiling or dirt. Scouring is usually carried in iron vessels called kiers. The fabric is boiled in
an alkali, which forms soap with free fatty acids. (saponification). A kier is usually enclosed,
so the solution of sodium hydroxide can be boiled under pressure, excluding oxygen which
would degrade the cellulose in the fibre. If the appropriate reagents are used, scouring will
also remove size from the fabric although de-sizing often precedes scouring and is considered
to be a separate process known as fabric preparation. Preparation and scouring are
prerequisites to most of the other finishing processes. At this stage even the most naturally
white cotton fibres are yellowish, and bleaching, the next process, is required.
Mercerising
A further possibility is mercerizing during which the fabric is treated with caustic soda
solution to cause swelling of the fibres. This results in improved luster, strength and dye
affinity. Cotton is mercerized under tension, and all alkali must be washed out before the
tension is released or shrinkage will take place. Mercerizing can take place directly on grey
cloth, or after bleaching.
Bleaching
Bleaching improves whiteness by removing natural coloration and remaining trace impurities
from the cotton; the degree of bleaching necessary is determined by the required whiteness
and absorbency. Cotton being a vegetable fibre will be bleached using an oxidizing agent,
such as dilute sodium hydrochloride or dilute hydrogen peroxide. If the fabric is to be dyed a
deep shade, then lower levels of bleaching are acceptable, for example. However, for white
bed sheeting and medical applications, the highest levels of whiteness and absorbency are
essential.
Dyeing
Dyeing is commonly carried out with an anionic direct dye by completely immersing the
fabric (or yarn) in an aqueous dye bath according to a prescribed procedure. For improved
fastness to washing, rubbing and light, other dyes such as vats and reactive dyes are
commonly used. These require more complex chemistry during processing and are thus
more expensive to apply.
37
The Park shall have modern production facilities for Warping , Winding, Processing as well
as Finishing and packaging of Finished Goods. Machinery proposed to be installed by unit
wise is presented in the Table below:
Amount
Name of the
S.No Activity Capacity Units (Rs in
member unit
lakh)
SIVAKUMAR
1 DYEING 600 Kgs 90.00
TEXTILES
SIZING &
2 T.G.R TEX 7000 Mts 45.00
WARPING
YUVARAJA
3 PACKAGING 2000 Pcs 15.00
TEXTILES
BOILER
5 COMMON UNIT 27.00
UNIT
Total 222.00
Amount
Name of the
S.No Activity Capacity Units (Rs in
member unit
lakh)
SIVAKUMAR
1 DYEING 600 Kgs 90.00
TEXTILES
SIZING &
2 T.G.R TEX 7000 Mts 45.00
WARPING
YUVARAJA
3 PACKAGING 2000 Pcs 15.00
TEXTILES
BOILER
5 COMMON UNIT 27.00
UNIT
Total 222.00
40
Common
2 186.00 24.54%
Infrastructure
Project Cost
S.No Details % of Share
(Rs. In Lakhs)
Common
1 186.00 35.64%
Infrastructure
1 DYEING 120
SIZING &
2 40
WARPING
3 2 150 KVA 150 KVA
PACKAGING
4 WINDING 60
TOTAL 222
6. STATUTORY COMPLIANCES :
The Project includes a 75 KLD CETP for which CTE and CTO are the
main Statutory requirements.
Apart from this The Masterplan and Building Plan approval required
to be obtained from the LPA of Tiruvallur Dt. The SPV has already
Finalised the plan and ready for submission .
The SPV doesn’t expect any difficulty in obtaining the Power and
Water supply form local panchayat , which is available nearest to
the site.
7. MEANS OF FINANCE :
The Means of Finance have been estimated under the MTP scheme as below:
Amount
S.N
Means of Finance (Rs in % of Share
o Lakh)
INFRASTRUCTURE &
TYPE OF MACHINERY FACTORY UNITS
Name of the SUB SUB COMMON FACILITIES SUB
S.NO MACHINERY TO
member unit TOTAL TOTAL TOTAL
BE INSTALLED
LOAN MARGIN LOAN MARGIN LOAN MARGIN
SIVAKUMAR
1 DYEING 67.50 22.50 90.00 22.50 67.50 90.00 43.56 14.52 58.08
TEXTILES
SIZING &
2 T.G.R TEX 33.75 11.25 45.00 22.50 67.50 90.00 43.56 14.52 58.08
WARPING
YUVARAJA
3 PACKAGING 11.25 3.75 15.00 11.25 33.75 45.00 43.56 14.52 58.08
TEXTILES
ANNAMALAI
4 WINDING 33.75 11.25 45.00 11.25 33.75 45.00 43.56 14.52 58.08
TEX
COMMON BOILER
5 20.25 6.75 27.00 2.19 6.56 8.75
UNIT UNIT
Total 166.50 55.50 222.00 69.69 209.06 278.75 174.24 58.08 232.32
The Process and Products being produced in the Park are familiar
with the current trend and all the SPV members are well
experienced and having long term experience in operating the
business.
Term Loan
The interest rate on Term Loan as well as on the Bridge Loan is considered
at 11% per annum and the repayment period is considered as 8 years with
a moratorium of 12 months.
RS IN
LAKHS
LOAN AMOUNT 161.05
INTEREST 11%
EMI PER MONTH 2.53
REPAYMENT 8 YEARS
OUTSTANDING
INTEREST
YEAR EMI/ MONTH PRINCIPAL PAID BALANCE
PAID
(in Rs)
2023 2,52,984.20 17,05,821.84 13,29,988.50 2,12,50,672.34
2024 2,52,984.20 15,51,917.11 14,83,893.22 1,82,14,861.94
2025 2,52,984.20 13,80,202.70 16,55,607.61 1,51,79,051.54
2026 2,52,984.20 11,88,617.72 18,47,192.59 1,21,43,241.14
2027 2,52,984.20 9,74,862.76 20,60,947.59 91,07,430.74
2028 2,52,984.20 7,36,372.30 22,99,438.05 60,71,620.34
2029 2,52,984.20 4,70,283.99 25,65,526.33 30,35,809.94
2030 2,52,984.20 1,73,404.28 28,62,406.05 NIL
TOTAL 2,42,86,483.20 81,81,482.70 1,61,04,999.94
50
TOTAL
OPERATING
FACILITY CHARGES / NET INCOME
QUANTITY UNIT INCOME = EXPENSES
DESCRIPTION UNIT (in Rs)
CHARGES /
MONTH
WATER
50000 LITRES 0.300 45,000.00
CHARGES 4,50,000.00 4,05,000.00
POWER
100 KVA 6.500 23,400.00
CHARGES 2,34,000.00 2,10,600.00
CETP
TREATMENT 75000 LITRES 0.300 1,68,750.00
6,75,000.00 5,06,250.00
CHARGES
TECHNICAL &
2
ADMIN STAFF 40,000.00
SECURITY STAFF 1
15,000.00
ON TOTAL
O & M EXPENSES @1%/YR
COP 42,587.50
ASSET ON
REPLACEMENT @5%/YR EQUIPMENT
62,500.00
COST & M/c
TOTAL
(B)
EXPENSES 15,34,937.50
The weighted average DSCR for the proposed repayment schedule works
out to 1.260, which indicates that the term loan serviceability is good.
Based on the forgoing analysis and study thereof and profitability envisaged
in the financial statements, the following observations are made in respect
of the proposed MTP at Tiruvallur District:
Ø The units set-up in the park are expected to have tremendous cost
advantages since the infrastructure comes at a substantially subsidized
cost due to availability of grant to the tune of Rs.2.50 crores from
Government of Tamilnadu.
Ø The promoters/participating units in the park are already well entrenched
in the business of Processing, Weaving and garmenting activities and
have requisite experience, competence & financial strength to establish
and manage the park.
Ø The location of the park is well placed in terms of availability of raw
material, trained manpower, road connectivity, Rail connectivity,
Seaport, Airport, electricity, water, etc.
Ø The common facilities proposed in the park are considered critically
important and have direct bearing on improving the viability of the
individual projects.
Ø The Park will provide employment opportunities to landless labourers &
women and therefore has strong socio-economical relevance.
Ø The State Government policies are observed to be favorable for this
sector.
Ø The financial parameters work out to quite reasonable levels.
Backward Linkages : The main raw material for the entire value chain of the park
is yarn approximately 600 Kgs per day for Processing and 7000 Mts for Sizing,
Warping and Winding.
The SPV members have wide network of Clients and continuous orders and having
capacity to store the required yarn for the Processing, Sizing, Warping and Winding
for minimum 15 days capacity.
Forward Linkages : The SPV members are having own orders and marketing the
Products across states.
All the members are well versed in Marketing and Sales of the Products being
produced in the TMTP. They have strong market linkages across all northern and
Southern states.
53
Exports : Since all the products are being produced for Domestic
market , Export is not envisaged in the park. However, the product
quality is at par with export standard with Environmental and
Social Compliances. Hence the MTP can handle Export orders
based on the market enquiry.
Revenue
Turnover
Name of the Generation
S.NO Activity Capacity Per Year
member unit Per Day
Rs In Lakhs
(Rs)
SIVAKUMAR
1 DYEING 600 Kg 105000 346.50
TEXTILES
SIZING &
2 T.G.T TEX 7000 Mts 42000 138.60
WARPING
YUVARAJA
3 PACKAGING 2000 Pcs 450000 1485.00
TEXTILES
ANNAMALAI
4 WINDING 1000 Kgs 10000 33.00
TEX
TOTAL 2003.10
54
Name of the
S.NO Activity Capacity EMPLOYMENT INDIRECT
member unit
SIVAKUMAR
1 DYEING 600 Kg 15 18
TEXTILES
SIZING &
2 T.G.T TEX 7000 Mts 12 70
WARPING
YUVARAJA
3 PACKAGING 2000 Pcs 15 15
TEXTILES
ANNAMALAI
4 WINDING 1000 Kgs 10
TEX
TOTAL 55 103
55
Ø The SPV will collect the required Lease rental charges from the
Unit holders on sq ft basis as per the their area of occupancy of
each factory.
Ø The Charges for Power and Water will be calculated at actuals +
10% for overheads.
Ø The Charges for waste water treatment will be collected from the
units discharging the Effluents .
Ø The Staff cost on Common facilities will be apportioned as per the
area of the occupancy of the units .
The SPV will collect the user charges based on the Sq ft of the Units
occupied on monthly basis and service the Expenses and Debts to the
bank.
The Maintenance charges will be collected 10% over and above the
actuals for future asset replacement cost for consumables and Spares
replacement.
56
TOTAL
OPERATING
FACILITY QUAN CHARGE NET INCOME
UNIT INCOME = EXPENSES
DESCRIPTION TITY S / UNIT (in Rs)
CHARGES /
MONTH
FACTORY 19000 SQFT 28.771 5,46,656.94
( 15 YRS AVERAGE) 5,46,656.94
COMMON 1750 SQFT 15.000 26,250.00
26,250.00
SECURITY STAFF 1
15,000.00
@1%/Y ON TOTAL
O & M EXPENSES
R COP 42,587.50
ASSET ON
@5%/Y
REPLACEMENT EQUIPMENT
R 62,500.00
COST & M/c
SUB TOTAL (A) 6,49,969.44
19,31,906.94 12,81,937.50
SL COMPLETION
ACTIVITY DESCRIPTION STATUS START DATE
NO DATE
Annexure 7.
58
a. The SPV will dovetail Industrial Policy / Textile Policy of State Govt
for obtaining grant for the Production machineries which is not
covered under this MTP scheme.
a. An affidavit to an effect that the SPV will abide by all the terms and
Conditions set forth in the Govt orders, General Financial rules and Scheme
guidelines and All the Information given are 100% correct, has been
enclosed as Annexure 3.
b. An affidavit to an effect that the SPV will incur the required margin money
from their own sources without any delay in implementation of the MTP has
been enclosed as Annexure 4.
60
14. ANNEXURES
GOVERNMENT OF INDIA
MINISTRY OF CORPORATE AFFAIRS
OFFICE OF THE REGISTRAR OF COMPANIES
Central Registration Centre
Indian Institute of Corporate Affairs (IICA), Plot no. 6,7,8, Sector 5, IMT Manesar, Manesar, Haryana, 122050,
India
NOTE - THIS LETTER IS ONLY AN APPROVAL FOR RESERVATION OF NAME FOR A PROPOSED LLP. THE
APPLICANT CANNOT START BUSINESS OR ENTER INTO ANY AGREEMENT, CONTRACT, ETC. IN THE NAME OF
THE PROPOSED LLP UNTIL AND UNLESS A CERTIFICATE OF INCORPORATION IS ISSUED BY THE REGISTRAR OF
THEREUNDER.
To,
PONNUSWAMY VITCHULI
Sir/Madam,
Yours sincerely,
Vikram Singh
Assistant Registrar of Companies/ Deputy Registrar of Companies/ Registrar of Companies
Registrar of Companies
Note: The corresponding form has been approved by Vikram Singh , Assistant Registrar of Companies/ Deputy
Registrar of Companies/ Registrar of Companies and this letter has been digitally signed by the Registrar
through a system generated digital signature under rule 36(3)ii of the Limited Liability Partnership Rules, 2009.
62
ANNEXURE 5.
CETP ESTIMATE
• M V R – 4 KLD
66
MF Inlet MF Outlet
S.No Description
1. PH 9 -11 7–8
2. BOD 20 - 30 PPM 25 PPM
COD 100 - 200 PPM 125 PPM
3.
Total Dissolve solids 8000 PPM 8000 PPM
4.
5. Total Suspended solids 50 PPM NIL
6. Silica NIL NIL
7 Chlorides 700 PPM 700 PPM
8 Sulfates 3000 PPM 3000 PPM
9 Total Hardness 100 - 150 PPM 100 - 150 PPM
MF Inlet MF Outlet
S.No Description
1. PH 7–8 7–8
2. BOD 30 PPM 25 PPM
COD 150 PPM 125 PPM
3.
Total Dissolve solids 4000 PPM 4000 PPM
4.
5. Total Suspended solids 50 PPM NIL
6. Silica NIL NIL
7 Chlorides 500 PPM 500 PPM
8 Sulfates 700 PPM 700 PPM
9 Total Hardness 100 - 150 PPM 100 - 150 PPM
68
RO PLANT
• Consisting low fouling brackish water membrane.
• 50% high pure reusable water confirming to processing industries water
requirement specifications.
PROCESS SEQUENCE
PRE AERATION
To liberate excess cl2 gas
MVR+CHILLER+ATFD
To handle RO reject
70
DESIZING + PRINTING
SCREENING
COLLECTION TANK
EQUALIZATION TANK
NEUTRALIZATION TANK
SCREW PRESS
ANAEROBIC (USBR)
SLUDGE DRYER
SETTLING TANK
AERATION TANK
SECONDARY SETTLING
FILTER FEED
SAND FILTER
MF
MVR + ATFD
71
ETP
Ø DYEING – 75 KLD
Ø DESIZING + PRINTING – 25 KLD
RO PLANT
Ø DYEING – 3 M3/HR
Ø DESIZING + PRINTING – 1 M3/HR
MF PLANT
Ø DYEING – 3 M3/HR
Ø DESIZING + PRINTING – 1 M3/HR
3. Pipe line fitting Accessories Bolt nut, Flanges, UPVC Flanges, Bend 1 lot
bend & gaskets –Supreme/Equalent
2. Pipe Line for Blowers UPVC Pipe Lines SS Header Line 1Lot
Internal - UPVC line
-Supreme/ Equalent
3. Diffuser Course SSI / Equalent As per
Bubble Design
Diffuser
2. SIZE 2 M2 AREA 2 No
3. LAMELLA PVC/SS 2
CLARIFIER MOC SUPPORT LOT
TECHNICAL SPECIFICATIONS
1. Process step
- Heating of feed & cooling of condensate
- Evaporation stage & Concentration stage
2. Technology Selection
SEDL has developed MVR based Evaporator to recover clean water by
concentrating Wastewater and reducing its mass/volume to negligible providing
environment friendly solution. This evaporator requires no boiler and external
steam input for operation and is capable of generating clean water at a minimal
cost.
Evaporation using steam is energy intensive when we burn fuel to generate steam.
Evaporationbased on MVR technology is a cost-effective alternative to concentrate
water-based solutions.
Booster/Blower System
Type : Rotary twin lobe type/ Twin Lobe
Root Blower type
Drive
Motor : ACVFD
Type : TEFC Sq. cage
Make : Everest / Swam
Distributors are used to distribute feed material uniformly from top end of plate
packs. Thus, feed material flows pack to pack in thin film form from the tube sides
of Heat Exchanger and trickles down pack to pack. Concentrated feed and vapors
produced in evaporation process exittogether from the bottom of plate pack. This is
then utilized in next effect.
78
INLET AND OUTLET PIPELINE (HDPP PIPE) = Rs. 10, 00, 000/-
ANNEXURE 6
S.No /
rate
BOQ Description Breath Depth Qty Unit Amount
/unit
Ref
TMTP ROAD DETAILS
B.1.3 Supplying and Laying good earth brought from
outside in layers not exceeding 300mm depth,
consolidating each deposited layer by ramming and
watering,etc.,(including all necessary
operations,)and as directed by engineer incharge
(Provisional Qty)
12.2 7.4 0.45 250
total qty 250 m3 990 247500
B.5.2 Providing and laying Granular Sub base with graded
materials confirming to specification,mixing in a
mechanical mix plant at OMC,carriage of mixed
materials by tipper to work site include all lead and
lift,spreading in uniform layers of specified
thickness with motor grader on prepared durface and
compacting with vibratopry roller to achieve the
desired density,complete as per specifications and as
directed by the Engineer incharge , and as per
drawing details.with material confirming to grade I
(seive range 75 mm to 0.075 mm ) having CBR
Value -30 well graded (GSB) Granular subbase 150
mm thick
10 5 0.15 200
total qty 200 m3 2250 450000
B.6.1 Providing and Laying Wet Mix Meccadam (WMM
) base course in layers 100 mm thick using well
graded un size stone aggregate ,of 40 mm -20mm of
approved quality mixing with quarry dust as per
specification.unit rate includes spreading metal and
rolling each layer by 10mt power roller all complete
ans as directed by Engineer incharge .
10 5 0.1 150
total qty 150 m3 2250 337500
B.7.1 Prime coat -Bitumen
Providing and applying primer coat with bitumen
emulsion on prepared surfaces,on granular
Base,including clearing of road surface and
spraying primer,at the rate 0.75 kg/m2 using
mechanical means.
10 5 1 150
total qty 150 m2 82 12300
80
10 5 0.045 63
total qty 63 m3 9990 629370
B.7.3 Bituminous carpet 25 mm thick
Providing and laying bituminous carpet layer of 25
mm thick ,Asphalt wearing course,with paving grade
biyumen, meetng the requirement, and laid to
required level,and slope,after cleaning the surface,
including providing anti-skid surface,with bitumen
precoated hard stone chip[pingof 13.20mm nominal
size at the rate .005 cumper 10sqm and at an approx
spacing 10 cm ceter to center,in both direction,rolled
etc…complete as directed by the Engineer incharge
.
10 5 1 150
total qty 150 m2 304 45600
B.7.4 Bituminous Seal coat 6 mm thick
Providing and laying slurry seal consisting of
amixture of fine aggrEgate ,portland cement
filler,bituminous emulsion,and water on
aroad,surface,icluding cleaning,of surface,mixing
slurry sealin asuitable mobile plant,laying &
compaction,to provide even riding surface.
10 5 1 150
TOTAL QTY 150 m2 144.65 21697.5
ANNEXURE 7
SL COMPLETION
ACTIVITY DESCRIPTION STATUS START DATE
NO DATE