Professional Documents
Culture Documents
HSE-SAF-PRO-00-0018
SAFETY MANUAL
REV. 1
17 Feb 08
Nitrogen Connection Turnaround Procedure
Page 1 of 8
TABLE OF CONTENTS
1. SCOPE……………………………………………………………..2
2. PURPOSE…………………………………………………………2
3. RESPONSIBILITY………………………………………………...2
4. REQUIREMENTS …………………………………………………2
5. CONNECTION SEQUENCE……………………………………..4
6. DISCONNECTION SEQUENCE…………………………………4
7. ATTACHMENTS
Attachment 7.1
Attachment 7.2
1/8
HSE-SAF-PRO-00-0018
SAFETY MANUAL
REV. 1
30 Nov 07
Nitrogen Connection Turnaround Procedure
Page 2 of 8
1.0 SCOPE
This interim safety procedure applies to the safe connection of nitrogen purge hoses
from the plant header & provides safe work practices in nitrogen use during TA.
Nitrogen is a dry, inert gas used throughout Q-Chem Complex for a variety of purging
and drying operations. The nitrogen system is relied on to be hydrocarbon and moisture
free.
CAUTION
Nitrogen is an extreme asphyxiation hazard and extreme care
should be taken when working in vessels which have been
purged with Nitrogen (refer to confined space entry procedure).
Back to top
2.0 PURPOSE
The purpose of this interim procedure is to provide a safe and uniform method for the
connection & removal of nitrogen purge hoses.
Back to top
3.0 RESPONSIBILITY
Back to top
4.0 REQUIREMENTS
2/8
HSE-SAF-PRO-00-0018
SAFETY MANUAL
REV. 1
30 Nov 07
Nitrogen Connection Turnaround Procedure
Page 3 of 8
Turnaround Permit Trailer as required. The Production Team shall issue this
permit.
4.2 Only Production Team shall be allowed to hook up temporary nitrogen hoses.
Though it may be permitted that the Maintenance staff install the check valves,
string out hoses, etc., the final connection of the hose to the process and the
opening of any valve shall only be performed by the Production team.
4.3 Approval of Shift Supervisor is required for installations of continuous nitrogen
purges into systems operating above 0.35 Kg/Cm2.
4.4 Nitrogen should not be used to "pressure out" liquids from vessels, unless the
system is verified to be below 3.5 Kg/Cm2.
CAUTION
Nitrogen should not be introduced below a liquid
hydrocarbon level. If Nitrogen is used to pressure out
liquid, nitrogen connection should be in vapor space
4.5 Only blue nitrogen hoses with Dix-Lock steel couplings (see Attachment 7.1)
with size ¾ “ to be used. Only hoses in good physical condition, free of frays and
cracks shall be used.
4.6 A check valve shall be located at the process end of the hose (see Attachment
7.2). The check valve must be a piston check valve type (sometimes referred as a
"lift check").
4.7 Ensure check valve allows flow in correct direction. In order for the piston to
function correctly, the check valve must be positioned in the horizontal upright
position only.
CAUTION
All systems that have pressure ratings below the nitrogen
system operating pressure shall have suitable and
adequate protection against overpressure, prior to nitrogen
being introduced into the system
4.8 The use of a pressure regulator as the only method of overpressure protection
shall be authorized by the Shift Supervisor prior to the nitrogen connection being
used.
4.9 Regulators are not required to be used on nitrogen hoses when high volumes are
needed for gas or air freeing operations provided that there is no physical
3/8
HSE-SAF-PRO-00-0018
SAFETY MANUAL
REV. 1
30 Nov 07
Nitrogen Connection Turnaround Procedure
Page 4 of 8
maintenance activity in progress and that relief protection or some other means
of escape such as vents / drains must be in service on any vessels included in the
purge system.
CAUTION
Nitrogen exiting manholes and nozzles also present
exposure hazard and caution must be taken to prevent over
exposure. On equipment that can hold large volumes of
nitrogen, consideration should be given to fresh air purging
to displace the nitrogen.
Back to top
7.0 ATTACHMENTS
Back to top
5/8
HSE-SAF-PRO-00-0018
SAFETY MANUAL
REV. 1
30 Nov 07
Nitrogen Connection Turnaround Procedure
Page 6 of 8
ATTACHMENT 7.1
FIGURE 1
6/8
HSE-SAF-PRO-00-0018
SAFETY MANUAL
REV. 1
30 Nov 07
Nitrogen Connection Turnaround Procedure
Page 7 of 8
FIGURE 2
ATTACHMENT 7.2
FIGURE 2: EXAMPLE OF A TYPICAL NITROGEN
PURGE ASSEMBLY
Line, equipment,
or vessel to be
purged
Typical bleeder
valve
Standard nitrogen
"Dix Lock"
connection
Nitrogen hose
Standard nitrogen
"Dix Lock"
connection
To Nitrogen
supply
7/8
HSE-SAF-PRO-00-0018
SAFETY MANUAL
REV. 1
30 Nov 07
Nitrogen Connection Turnaround Procedure
Page 8 of 8
NITROGEN PERMIT
Note: A regulator is not to be used as the only source of over pressure protection without the approval
of the Team Leader. In case of a continuous N2 purge into a system operating above 0.35 kg, Team
Leader approval is also required
Note: This form shall be posted in FIC. During Turnarounds, this form should be posted in the FIC or
Turnaround Trailer as applicable.
* - Overpressure Protection: a) Existing Relief Valve b) Open Vents c) Open Manhole d) Parted Flange
! - Shift Supervisor approval is required if a regulator is the only source of overpressure protection or if continuous N 2 purge is introduced into a
system operating above 0.35 kg/ cm2
8/8