Capacity Building on
Pump Hydro Energy Storage
Potential in Southeast Asia
Jakarta, 19-20 March 2024
Identified of Renewable Energy Potential
Legend :
PLTA/M : 31.4 GW
PLTP : 18.1 GW
PLTB : 17.6 GW
PLTS* : 19.7 GW
PLTBio : 0.4 GW
Total : 87.4 GW
*) Termasuk Potensi PLTS Bendungan
PUPR sebesar 13,8 GW
PLTS PLTS
(Ground PLTS (Ground
Provinsi PLTA/PLTM PLTP PLTB PLTBio Total Provinsi PLTA/PLTM PLTP PLTB PLTS PUPR PLTBio Total
Mounted + PUPR Mounted +
Non PUPR) Non PUPR)
Aceh 3,680.39 1,154.00 265.00 2.00 374.49 5,475.88 Maluku 72.00 487.00 40.00 88.68 687.68
Bali 1.00 510.00 330.00 59.00 900.00 Maluku Utara 409.00 409.00
Bangka Belitung 46.00 510.00 556.00 Nusa Tenggara Timur 698.00 56.00 2,000.00 254.29 3,008.29
Banten 21.54 506.00 1,300.00 100.00 373.90 2,301.44 Nusa Tenggara Barat 86.00 145.00 675.85 906.85
Bengkulu 81.06 550.00 631.06 Papua 2,000.00 50.00 2,050.00
Gorontalo 16.00 160.00 122.94 298.94 Papua Barat 75.00 58.00 133.00
Jambi 16.00 863.00 137.35 440.00 1,456.35 Sulawesi Barat 1,562.10 356.00 60.00 73.83 2,051.93
Jawa Barat 231.49 2,786.00 1,430.00 650.00 3,429.35 8,526.84 Sulawesi Selatan 1,119.00 525.00 535.00 985.00 1,241.18 4,405.18
Jawa Tengah 59.65 1,260.00 4,060.00 530.00 3,480.49 9,390.14 Sulawesi Tengah 3,634.72 771.00 200.00 4,605.72
Jawa Timur 23.30 1,135.00 6,871.00 350.00 1,288.69 9,667.99 Sulawesi Tenggara 480.00 318.00 130.00 145.57 1,073.57
Kalimantan Barat 1,924.00 65.00 162.00 2,151.00 Sulawesi Utara 42.25 568.00 63.00 41.00 48.15 762.40
Kalimantan Selatan 332.00 50.00 70.00 50.00 215.81 717.81 Sumatera Barat 1,402.60 914.00 2,316.60
Kalimantan Tengah 1,048.13 2.90 1,051.03 Sumatera Selatan 271.30 1,032.00 500.00 93.60 1,896.90
Kalimantan Timur 1,282.00 17.00 440.00 450.14 2,189.14 Sumatera Utara 1,381.61 1,460.00 67.00 49.36 2,957.97
Kalimantan Utara 10,720.00 43.00 10,763.00 Yogyakarta 10.00 350.00 31.40 391.40
Lampung 24.00 1,304.00 1,000.00 100.00 1,193.49 3,621.49 Riau dan Kepulauan Riau 10.38 71.20 4.00 85.58
Jumlah 31,426.14 18,158.00 17,693.00 5,817.38 13,898.76 446.90 87,440.18
For achieving Net Zero Emission on 2060 or sooner, PLN has launched the greenest
RUPTL to develop new Renewable Energy capacity 20,9 GW until 2030. Nowadays the
project is already at the procurement pipeline ~15 GW
ITEM REMARKS
• Package 1: Daelim-Astaldi-Wika JV
Lot 1A (Upper & lower DAM)
Lot 1B (Waterways, Powerhouse, Switchyard)
Contractor
• Package 2: Electromechanical
• Package 3: Procurement ProcessTransmission Line
• Package 4: CGGC (Hydraulic Metal Works)
Owner PLN
WB – 380 M USD
Source of
AIIB – 230 M USD
Fund
APLN – 145 M USD
Package 1A & 1B
2023
2023 2024
2024 2025
2025 2026
2026 2027
2027 2028
2028 2029
2029 2030
2030
J F M A MM J J AA SS O
O N
N DD JJ FF M
M AA M
M JJ JJ AA SS OO NN DD JJ FF MM AA MM J J J J AA SS OO NN DD J J F FMMAAMM J J J J AA S SOONND D J J F FMMA AMMJ J J JA AS SO ON ND DJ JF FMMA AM MJ JJ JA AS SO ON ND DJ JF M
F MA MA MJ JJ A
J AS O
S ON ND DJ FJ M A A
F M
Project Implementation
1 2 3 4 5 6 7 8 9 # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # # #
Schedule Pre-Cons Construction Phase Services Services during Guarantee Period
▲ ▲ ▲ ▲
Package 1 - Lot 1A Upper and Lower Dams 45 + 8 = 53 months
1 Upper Dam 31.5 months
1.1 Dam Excavation 16 months P1A Completion Summary
1.2 Consolidation & Curtain Grouting 15 months 12 November 2027 Excarvation
1.3 Dam Concrete 12.5 months Concrete Work
2 Lower Dam 50 months River Diversion
2.1 River Diversion 17 months 3 months Mobilization/Demobilization
2.2 Dam Excavation 22.5 months Design, Manufacturing & Deliver
Inkake Concrete
1 Intake 6 months 9.5 months
2 Headrace Tunnel #1 13 months 15 months P1B Completion
3 Headrace Tunnel #2 14 months 20 months 21 December 2028
4 Surge Tank #1 6 months 2.5 months 15.5 months
5 Surge Tank #2 4 months 20 months
6.1 Penstock Excavation 17 months
6.2 Penstock Concrete 18.5 months
Outlet Concrete
8 Outlet 6.5 months 16 months
9 Cable Termination Yard 3.5 month 7 months
10 Access Tunnel 5 months 11 months
11 Connecting Tunnel 1.5 monthss
12 Ventilation Tunnel 2.5 monthss 13 months
Package 2, 3, 4
2023
2023 2024
2024 2025
2025 2026
2026 2027
2027 2028
2028 2029
2029 2030
2030
J F M A MM J J AA SS O
O N
N DD JJ FF M
M AA M
M JJ JJ AA SS OO NN DD JJ FF MM AA MM J J J J AA SS OO NN DD J J F FMMAAMM J J J J AA S SOONND D J J F FMMA AMMJ J J JA AS SO ON ND DJ JF FMMA AM MJ JJ JA AS SO ON ND DJ JF M
F MA MA MJ JJ A
J AS O
S ON ND DJ FJ M A A
F M
Project Implementation
Plan : 2,98 %
Plan : 2,17 %
Actual : 2,86 %
Actual : 2,04 %
Deviation : -0,12 %
Deviation : - 0,137 %
Basecamp CVC BP #1
Upper Dam (LOT 1A) Power Intake
Progress : 88,05 % of Completed
(Excavation) Plan : 100 % Progress : 100 % of Plan : 100 %
Progress : 1,03 % of plan :
Excavation progress L/B. 829 – 1,07 % CVC BP #2
825 m asl. Shotcrete on, waiting • Foundation concrete (Not started)
for confirmation • Progress on the excavation • Masonry wall
and drainage ditch. • Office building finishing and RCC Batching Plant
Progress : 5,564 % plan : 12,75 % • Shotcrete equipment, accommodation - Design layout
(waiting information) modular house assembly and Progress : 2,5 % of Plan : 31` %
• Surface excavation – common (delay is increasing)
pipe installation for water and
- Warehouse (Dam works)
• Surface excavation – rocks sewage Progress : 73 % of Plan : 100 %
(no progress)
- On-site temporary office :
completed (100%) Crushing Plant
- On-site security booth : Progress : 5 % of plan : 11 %
Progress : 30 % (layout design)
(no definite schedule)
©2021. Direktorat Mega Proyek & EBT
PROGRESS OF UPPER CISOKAN PHES CONSTRUCTION – 3/3 Hydro
Land
Local Content
Acquisition
Permit and
Licenses