Professional Documents
Culture Documents
014 Annex 2B Checklist Housing & Building
014 Annex 2B Checklist Housing & Building
2B-1
CPES CHECKLIST FOR WORKMANSHIP
PROJECT ID/NO.: ______ PROJECT TYPE: Building & HousingITEM: Structural Steel
________VISIT LOCATION: ________________ DATE OF VISIT: / /
2B-2
CPES CHECKLIST FOR WORKMANSHIP
PROJECT ID/NO.: ______ PROJECT TYPE: Housing & Building ITEM: Common Items of Work
_______VISIT LOCATION: ________________ DATE OF VISIT: / /
2B-3
CPES CHECKLIST FOR WORKMANSHIP
PROJECT ID/NO.: ______ PROJECT TYPE: Housing & BuildingITEM: Common Items of Work
_______VISIT LOCATION: ________________ DATE OF VISIT: / /
Major* * Refer to Section 11.4a of the CPES Guidelines for definition of Major Defects
_____x_____
HBWS-303-01 No through cracks /
=
_____x_____
HBWS-303-02 No honeycomb (no exposed rebars/aggregates) /
=
_____x_____
HBWS-303-03 No sagging or bulging /
=
_____x_____
HBWS-303-04 Conformance to required quality of concrete mix /
=
Minor
_____x_____
HBWS-303-01 No cracks /
=
_____x_____
HBWS-303-02 No honeycomb /
=
_____x_____
HBWS-303-03 No sagging or bulging /
=
_____x_____
HBWS-303-05 Proper and adequate vibration /
=
_____x_____
HBWS-303-06 Conformance to finishing/plastering requirement /
=
_____x_____
HBWS-303-07 No chipping off of concrete cover /
=
_____x_____
HBWS-303-08 Conformance to the required concrete cover for rebars /
=
Conformance to the batching, mixing, transporting and _____x_____
HBWS-303-09 /
discharge time requirements =
Conformance to placing requirement that will not result _____x_____
HBWS-303-10 segregation of aggregates, cold joints and /
misalignment =
_____x_____
HBWS-303-11 Conformance to the jointing requirement /
=
_____x_____
HBWS-303-12 Proper curing /
=
Conformance to required dimensions, lines, _____x_____
HBWS-303-13 /
grades/elevation, and location =
_____x_____
/
=
_____x_____
/
=
Total Score (a) CAR Total
Was subcontractor used? If yes, name of company and owner:
_____________________________ & _________________________________ No. of Indicators (b)
2B-4
CPES CHECKLIST FOR WORKMANSHIP
PROJECT ID/NO.: ______ PROJECT TYPE: Building & HousingITEM: Masonry Works
________VISIT LOCATION: ________________ DATE OF VISIT: / /
Major
_____x_____
HBWS-304-01 Conformance to required quality of CHB /
=
_____x_____
HBWS-304-02 Conformance to required quality of mortar mix /
=
Minor
Conformance to specified tolerances for dimension, _____x_____
HBWS-304-03 /
location, plumbness and alignment =
_____x_____
HBWS-304-04 Proper spacing of horizontal and vertical bars /
=
_____x_____
HBWS-304-05 Rebars used free from rust /
=
_____x_____
/
=
_____x_____
/
=
_____x_____
/
=
Item 305 Brick Wall
Major
_____x_____
HBWS-305-01 Conformance to required quality of mortar mix /
=
Minor
Conformance to specified tolerances for dimension, _____x_____
HBWS-305-02 /
location, plumbness and alignment =
_____x_____
HBWS-305-03 Proper spacing of horizontal and vertical bars /
=
_____x_____
HBWS-305-04 Rebars used free from rust /
=
_____x_____
/
=
_____x_____
/
=
_____x_____
/
=
_____x_____
/
=
_____x_____
/
=
Total Score (a) CAR Total
Was subcontractor used? If yes, name of company and owner: =
_____________________________ & _________________________________ No. of Indicators (b)
=
Entered by:_____________________ Date: / / Rate = (a) / (b)
=
Rate
=
2B-5
CPES CHECKLIST FOR WORKMANSHIP
PROJECT ID/NO.: ______ PROJECT TYPE: Building & HousingITEM: Floor Finishes
________VISIT LOCATION: ________________ DATE OF VISIT: / /
2B-6
CPES CHECKLIST FOR WORKMANSHIP
PROJECT ID/NO.: ______ PROJECT TYPE: Building & HousingITEM: Floor Finishes
________VISIT LOCATION: ________________ DATE OF VISIT: / /
2B-7
CPES CHECKLIST FOR WORKMANSHIP
PROJECT ID/NO.: ______ PROJECT TYPE: Building & HousingITEM: Wall Finishes
_______VISIT LOCATION: ________________ DATE OF VISIT: / /
2B-8
CPES CHECKLIST FOR WORKMANSHIP
PROJECT ID/NO.: ______ PROJECT TYPE: Building & HousingITEM: Wall Finishes
_______VISIT LOCATION: ________________ DATE OF VISIT: / /
2B-9
CPES CHECKLIST FOR WORKMANSHIP
PROJECT NO.: ______ PROJECT TYPE: Building & HousingITEM: Ceiling Works
_______VISIT LOCATION: ________________ DATE OF VISIT: / /
2B-10
CPES CHECKLIST FOR WORKMANSHIP
PROJECT NO.: ______ PROJECT TYPE: Building & HousingITEM: Ceiling Works
_______VISIT LOCATION: ________________ DATE OF VISIT: / /
2B-11
CPES CHECKLIST FOR WORKMANSHIP
PROJECT ID/ NO.: ______PROJECT TYPE: Building & HousingITEM: Roofing System
______VISIT LOCATION/LOT:________________ DATE OF VISIT: / /
2B-12
CPES CHECKLIST FOR WORKMANSHIP
PROJECT ID/ NO.: ______PROJECT TYPE: Building & HousingITEM: Roofing System
______VISIT LOCATION/LOT:________________ DATE OF VISIT: / /
2B-13
CPES CHECKLIST FOR WORKMANSHIP
PROJECT NO.: ______ PROJECT TYPE: Building & HousingITEM: Doors, Windows, Railings
_______VISIT LOCATION: ________________ DATE OF VISIT: / /
2B-14
CPES CHECKLIST FOR WORKMANSHIP
PROJECT ID/NO.: ______ PROJECT TYPE: Building & HousingITEM: Basic Services
____VISIT LOCATION:_____________ DATE OF VISIT: / /
2B-15
CPES CHECKLIST FOR WORKMANSHIP
PROJECT ID/NO.: ______ PROJECT TYPE: Building & HousingITEM: Basic Services
____VISIT LOCATION:_____________ DATE OF VISIT: / /
2B-16
CPES CHECKLIST FOR WORKMANSHIP
2B-17
CPES CHECKLIST FOR WORKMANSHIP
PROJ. ID/NO.: ______ PROJ. TYPE: Building ITEM: Sewer & Drainage System
____VISIT LOCATION/LOT:________ DATE OF VISIT: / /
2B-18