You are on page 1of 14

North-South Commuter Railway Exte

CP N-05 : Building and Civil Engineering Work for Depo


Infrastructure and Track Work Ballast
(Contract No : NS

WORK INSPECTION REQ


WIR NO. NSCR-PSC-N05-MABDPT-WIR-QA-000000

We request your attendance to inspect the following works :

1. TYPE :
Buildings Roads
2. INSPECTION TIME :

Zone
3. LOCATION :

4. INSPECTION
● First

5. DESCRIPTION OF WORKS :

REF. DRAWINGS/DOCUMENT NO.


6. The works involve the following trades (Tick more than one if required) :

Surveying Architectural ✘ Civil

CONSTRUCTION QUA

SIGNATURE

NAME

POSITION

DATE

7. COMMENTS :

Inspection Status :
NONO (Approved) NONOC-C (Approved with Comments)

CONSTRUCTION QUA

SIGNATURE

NAME

POSITION
DATE

8. COMMENTS HAVE BEEN CLEARED:


(ARE/RE/SRE)

Name:

Signature:

Approval shall not relieve the Contractor of his liabilities under the Contract or constitute authorization of any changes to the Co
Mechanical Engr.
muter Railway Extension Project
neering Work for Depot Building Including Related
last
(Contract No : NSCREX-03-N05)

ECTION REQUEST (WIR)


DATE OF REQUEST:

Infrastructure ✘ Others
DATE :

Road Stations/Nodes

Second Third

REV. REMARKS
Electrical Mechanical Others

QUALITY ENGINEER

Comments) NONOC-B (Resubmission) NOR (Rejected) Cancelled

QUALITY ENGINEER
Date:

of any changes to the Contract Documents


Others

Cancelled
North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including Related
Infrastructure and Track Work Ballast
(Contract No : NSCREX-03-N05)

INSPECTION REPORT
TOWER CRANE ERECTION CHECKLIST
LOCATION: REPORT NO: DATE:

LINE OR STRUCTURE: DOCUMENT REF & REV NO: IR REF. NO:


ITP NO:
POSCO E&C
DESCRIPTION ENGINEER REMARKS
CONSTRUCTION QC

TOWER SECTION
All mast section components must be free from dents, deformation and no twist. HP RI RI

No cracks on frames and cracks on welded joints. HP RI RI

Pins on the connecting joints must be properly fitted and not loose. HP RI RI

Bolted joints must be properly tightened and no koint clearances. HP RI RI

No leaks on cylinder jacks and hoses. HP RI RI

IN-HOUSE CHECKING AND COMMISSIONING


Initial Checking and commisioning to be done by erector HP WP RI

FINAL ACCEPTANCE
Final inspection of TOWER CRANE ERECTION by 3rd party HP WP WP

OTHER REMARKS:

INITIALS REFERENCE BOX : (WRITE DOWN YOUR INITIALS AS SIGNED ABOVE AND NAME)
SIGNATURE

NAME

POSITION

DATE:

CONSTRUCTION QC
ENGINEER
POSCO E&C

LEGEND: HP : HOLD POINT WP : WITNESS POINT RI : RANDOM INSPECTION NA : NOT APPLICABLE


North-South Commuter Railway Extension Project
CP N-05 : Building and Civil Engineering Work for Depot Building Including Related
Infrastructure and Track Work Ballast
(Contract No : NSCREX-03-N05)

INSPECTION REPORT
PLUBMING AND SANITARY SYSTEM INSTALLATION CHECKLIST
LOCATION: REPORT NO: DATE:

LINE OR STRUCTURE: DOCUMENT REF & REV NO: IR REF. NO:


ITP NO:
SUBCONTRACTOR POSCO E&C
DESCRIPTION ENGINEER REMARKS
CONSTRUCTION QC CONSTRUCTION QC

Survey and Setting out

Check the installation of anchors, brackets, hangers and supports as per drawing HP HP HP WP RI
Check and ensure that installation are as per approved drawings and manufacturer
recommendation HP HP HP WP WP

Check installed pipe laid as per correct level and slope HP HP HP WP WP

Ensure installed pipe are free from sag and bends HP HP HP WP WP

Check after installation of pipe are free from crack and damage HP HP HP WP WP
Check section of the pipe to be tested are fully completed, Ensure that free from physical
defects and connection are remidied HP HP HP WP WP

Ensure clean and adequate water supplied for the test HP HP HP WP WP

Check both end of the pipe section are full plugged and blanked
HP HP HP WP WP

Check section of the pipes under testing for any leaks at the joints HP HP HP WP WP

Check the installation of vent pipes and fittings


HP HP HP WP WP

Check the installation of floor draing and clean out location


HP HP wp WP RI

Check the installation of the roof drain HP HP HP HP WP

Indication and label installed (if required) HP HP HP WP RI

FINAL ACCEPTANCE
Final inspection of PLUBMING AND SANITARY system installation HP HP HP HP HP

OTHER REMARKS

INITIALS REFERENCE BOX : (WRITE DOWN YOUR INITIALS AS SIGNED ABOVE AND NAME)
SIGNATURE

NAME

POSITION

DATE:

CONSTRUCTION QC CONSTRUCTION QC
ENGINEER
SUBCONTRACTOR POSCO E&C

LEGEND: HP : HOLD POINT WP : WITNESS POINT RI : RANDOM INSPECTION NA : NOT APPLICABLE

You might also like