Professional Documents
Culture Documents
I
B8.3.4.6.4 Alarm annunciation and Sequence of Events Recording
functions (SER) 35
B8.3.4.6.5 System diagnostics and configuration 37
B8.3.5 Boiler protection system (BPS) 39
B8.3.5.1 Design requirements 39
B8.3.5.2 System architecture 39
B8.3.5.3 Hardware requirements 39
B8.3.5.4 Software requirements 39
B8.3.5.5 Emergency shut-down 40
B8.4 Technical requirements for Data exchange with the AGC 40
B8.4.1 General 40
B8.4.2 Requirements for the control center 40
B8.4.3 Requirements for Automatic Generation Control (AGC) 40
B8.4.3.1 Data Requirements for Control Center 41
B8.4.3.2 Data for transmission switchgear monitoring and control 45
B8.4.3.3 Data for transformer monitoring and control. 47
B8.4.3.4 Data for substation common alarms and measurements. 49
B8.5 Technical requirements Communication system 50
B8.5.1 Telephone system 50
B8.5.2 Public address system 51
B8.5.3 Intercom system 52
B8.5.4 CCTV 53
B8.6 Technical Schedules 53
II
B8. Instrumentation and control works
B8.1 General
• Distributed digital control system (DCS) for the main systems of the
plant
• Boiler protection systems
• Field-mounted equipment
• Systems for flue gas emission monitoring
• Central control room and central electronic room equipment
• Communication systems
• Telephone
• Public address
• Portable radio
• Intercom system
• CCTV system
• Local Control Systems:
• Coal handling system
• Ash handling system
• Water treatment plant (WTP) system
• Demineralization plant system
• Electrochlorination plant (ECP) system
• Waste water treatment plant (WWTP) system
including Local Control Rooms (LCRs) and Data Exchange with main
DCS.
B8 - 1
B8.1.1 General Operation and Control Philosophy
The control and instrumentation system shall minimize the power station
personnel in operation and maintenance.
The malfunction of any component or loss of supply shall lead to fail safe
condition. All equipment shall be designed that in all conditions which
occur in electrical, pneumatic or hydraulic supplies, there shall be no
damage to plant and personnel.
The automation system must consist of modules for each unit and one
module for the common part. The modules must be separated from each
other, but they are all connected to the redundant data highway.
Additional systems must be connected "intelligently" (e.g. via PLC) so, that
they can be supervised from the CCR.
The CCR shall be the operational focus for the whole plant from where all
major plant items such as the boilers, turbine generators, etc. shall be
capable of being started, on-line regulated and shut down.
All systems, if not configured on the DCS but using own microprocessor
based system, shall be able to communicate with DCS for operator
monitoring and/or control from CCR.
B8 - 2
For the power plants major auxiliary systems which are stand-alone and not
directly related to the load dispatch, shall have their own control panels and
Local Control Rooms (LCR) as per the Tenderer’s design. However, the
equipment status, process parameters, and alarms should be available via
DCS in the CCR. All systems shall have independent control facilities.
Monitoring of these auxiliary systems, which are essential for plant on-line
coordination shall also be possible from the CCR.
The local control systems shall follow the DCS concept for safe, reliable and
efficient operation, including, but not limited to:
• Redundant controller with hot stand-by
• Redundant VDU’s
• Required mimics of plant P&ID’s status monitoring, control, trending,
history (archiving), alarm system, etc.
• Hierarchical control with automatic, semi-automatic and manual
operations
• Maintenance functions
• Necessary engineering work stations
• System diagnostics.
Plant operations including start-up, loading and shutdown of the power units
under all operational conditions shall be done from the central control room
(CCR) based on functionally distributed hierarchical control system.
The control system design of the man machine system, indication, alarm and
control equipment shall be based on minimization of the incidence of
operator error and maximization of the operators’ efficiency.
B8 - 3
B8.1.4 Principles of Boiler automation
The start up, loading and transfer to range pressure control of each Steam
Generator (SG) shall be done in hierarchical control functions utilizing
breakpoints.
The operation of the STGs shall be fully automated. The complete start-up
and shut down shall be remotely supervised and conducted in a automatic
mode from the CCR. The Turbine shall be automatically started and
accelerated to its rated speed and after synchronization loaded with its initial
load.
B8 - 4
B8.2 Scope of supplies and services
B8.2.1 General
This section sets out the scope of installations covered by this specification as
well as requested supplies and services, but without excluding other necessary
components and services not mentioned.
The Tenderer shall submit their automation system structures for approval.
General requirements for the I&C equipment and materials are specified under
Section B0. The material used for all equipment shall fully meet the
requirements regarding safety and operational conditions of the media to be
measured.
The instrumentation and control equipment and the control functions specified
in the various sections shall be supplied as a minimum requirement.
Further instrumentation shall be provided as far as required for the fulfillment
of the specified degree of automation and for a safe and satisfactory operation
and supervision of the plants.
The scope of supply within this section comprises at least, but not limited to:
Field equipment
• All measuring and signal conditioning equipment installed in the field as
well as in the electronic rooms, LCRs and CCR. Basically, common
transmitting sensors are to be used for control, alarming and supervision
of each variable.
• Portable programmers for programming and calibration of SMART
transmitters (for number see table at the end of this chapter).
• For general start-up and maintenance all necessary local instrumentation
shall be provided including at least the following:
B8 - 5
Pumps Suction and discharge pressure gauges
Gland sealing pressure gauge (if applicable)
B8 - 6
The flue gas and emission measuring points shall include at least, but not be
limited to:
B8 - 7
• Data interfaces for remote attendance and maintenance, via Modem
or intranet
• Closed-loop control system
All necessary closed-loop control systems as specified in this Section B8.
In addition to the task description included in this chapter the task
description in the specifications of the relevant mechanical equipment
shall be considered.
• Open-loop control system
Complete control equipment for all manually remote or automatically
controlled drives in accordance with the operating conditions described
under this Section B8 including all necessary safety interlocking and
protections. The extent of the supplied open-loop control system shall
fulfill the specified control philosophy and degree of automation.
• Open-loop control and signal exchange as described in Section B7,
electrical and associated works.
• Alarm Annunciation and Sequence of Events Recording (SER) as
specified under this Section B8.
• Data highway equipment
All necessary data highway equipment in accordance with the technical
requirements as specified under this Section B8.
• DCS engineering, diagnosis and maintenance equipment for common
parts of plant as well as each single unit. This platform must also enable
the diagnosis and parameterization of the SMART transmitters (in
addition to the diagnosis and parameterization via portable
programmers).
• Engineering stations in accordance with the technical requirements
specified under this Section B8
• Laser printer - A4 format.
• Laser printer - A3 format
• Print Server
• Process Information Data Archive, to provide any kind of current or
historical process information for plant operation analysis or plant
operation optimization systems. These systems will be linked to the
terminal bus via appropriate interfaces. If the Tenderer can provide
integrated solutions for this type of analysis and optimization, he is asked
to offer these solutions.
For the number of systems, see table and schematic of DCS structure at the
end of this chapter.
B8 - 8
Various PLC based control systems for package equipment
• One programming device for each type of supplied PLC controller for
each case.
For the number of systems, see table at the end of this chapter.
The control room shall have an ergonomically and esthetically well suited
appearance. For the number of systems and a possible layout, see table and
schematic at the end of this chapter.
B8 - 9
Telephone system
The telephone system shall consist of:
• Amplifier station
• Control unit for the control room desk with microphone and function
keyboard
• Control unit in the office building
• Loudspeaker groups, with 10 loudspeakers each
• Digital memory for alarm tones and standard messages
• Tape decks for special message recording.
For the number of systems, see table at the end of this chapter.
Intercom system
The wireless personnel paging system shall consist of:
• Desk top control base station (central control room)
• Goose neck microphone
• Build-in loudspeaker
• Slave units with build-in loudspeaker and microphone.
CCTV
The CCTV system shall be provided to:
B8 - 10
Clock system
The clock system shall consist of:
• Master clock (GPS based)
• Slave clocks
Systems to be provided
System Numbers
Portable programmers for programming and 3
calibration of SMART transmitters
DCS engineering work stations 3
A4 laser printer 3
A3 laser printer 3
VDU per station 3
Print Server 1
Process Information Data Archive 1
Non DCS control system Engineering work 1 for each
station (in addition to communication program system
PCU)
printer 1 for each
system
Telephone systems 1 system
Public address systems 1 system
Central Control Room (CCR) 1
Operator stations as necessary
VDUs per station 5
Large Screen projection per station 1
Shift supervisor operator station 3
VDUs per station 1
Hardwired Digital MW/Turbine Speed 3 sets
(automatically changed at synch.), MSP,
MST and clock - all readings to tally with
DCS, vice versa.
low noise printers 6
hard copier 4
multi-layers slidable board 1
Local Control Rooms (LCRs) as defined in
B8.1
Operator stations/control panels as necessary
VDUs per station Redundant
Shift supervisor operator station as necessary
VDUs per station as necessary
low noise printers as necessary
hard copier as necessary
B8 - 11
Spare capacity after completion of commissioning
At least 5% free space shall be available in all cubicles, junction boxes and
marshaling racks after final commissioning. This free space shall be
distributed inside the cubicles in such a way that additional terminals,
equipment or modules may be added to any group of controls. At least 5%
spare cores shall be provided in each control and monitoring cable. All spare
cores have to be terminated.
All services required for a safe, reliable, efficient and trouble free
instrumentation and control equipment shall be provided by the Contractor.
These services shall include but not be limited to:
As far as the final execution of the work is concerned all design data,
interlocking conditions, control loops and logic diagrams supplied by the
various subcontractors shall be checked, verified and closely coordinated
with the other subcontractors of the corresponding equipment. For this
purpose close collaboration with all subcontractors supplying control
equipment shall be arranged.
B8 - 12
B8.2.4 Erection, cabling, wiring, labeling
The scope of this contract covers complete erection, cabling and wiring of all
control and monitoring equipment and shall comply to the general
requirements stated under Section B0 and B7.
The Contractor shall be, in all cases, fully responsible for the correct
installation and erection with regard to the measuring and control functions of
all the supplied equipment.
The Contractor shall make all necessary provisions for the site testing and
commissioning of the control and instrumentation systems which include but
shall not be limited to the following:
All tests performed on site, including the results and deficiencies, have to be
recorded and the test protocols have to be submitted to the Owner.
All cabling for the field equipment in the scope of this contract, shall be
supplied, laid and terminated.
For the supplied field cabling all necessary cable routes, supporting
traywork, surge diverters (if necessary) and intermediate marshaling shall be
provided.
B8 - 13
B8.2.5 Commissioning
The Contractor shall be entirely responsible for the commissioning of the DCS
in conjunction with the plant system. Commissioning shall be carried out in
accordance with the commissioning procedures prepared by the Contractor
and approved by the Owner.
B8.3.1 General
The I&C systems shall be so designed that the power plant units shall be
remotely controlled exclusively from the CCR.
The control system making up the scope of supply shall permit complete and
centralized monitoring of plant operations as well as automated operation
under the following aspects:
• Normal operation of the plants, for example during changes in the boiler
or turbine load, shall be automatic.
B8 - 14
• All functions for protecting plants and equipment shall proceed in all
cases reliably and without manual intervention. The plant protection
system shall prevent the unit from reaching impermissible loading
conditions and, should any faults arise, shall keep their consequences
within the specified limits. The same applies for switch-on and
switchover functions of redundant and reserve equipment with the
possibility for pre-selecting the operating equipment.
• The plant shall be put into and taken out of operation by manual initiation
of the functional group controls of all subsystems. All drives required for
start-up and shutdown of the unit in accordance with the specified control
philosophy shall be remotely controlled from the CCR.
For this plant the individual drive level, sub-group level, functional group
level and unit co-ordination level shall be provided:
Drive level
• Start, stop, protection and manual operation for individual drives.
Position control for regulating actuators.
Sub-group-level
• The combined or sequential control of associated drives such as main
pump drives and associated discharge/suction valve drives. Auto standby
functions. Closed-loop control functions.
Unit co-ordination
• Start-up, shutdown, on line co-ordination and protection of the unit.
Normal operation shall be under unit coordination level. All the
sequence shall be based on sequence breakpoints.
B8 - 15
The task of the unit co-ordination level is to lead the sequence and to
generate the setpoints for the control of the plant for start-up, online
operation and shut down conditions. The required unit capacities shall be
reached with minimum run up time but under strict consideration of
allowable thermal stress limits.
In general the Operator shall have direct access to all four control levels
through the operator interface located in the CCR.
All field equipment supplied under this contract shall comply with the
relevant requirements of Section B0.6.18.
For important parameters which are concerning the safety operation of the
generation units, triple redundancy shall be applied; for interlock and alarm
signal, double redundancy shall be supplied.
Local direct reading instrumentation and controls not forming part of the
central control and supervisory system shall be provided only for the
following cases:
B8.3.4.1 General
This subsection covers the minimum requirements for the design and
fabrication of the DCS. The Contractor shall be responsible for all hardware,
software, interface to other systems, system testing, documentation,
delivery, installation, supervision and field support and any other services as
required for the procurement of the system as defined within this
specification.
B8 - 16
The design of the DCS shall conform to the state of the art, and shall already
have been proven in other similar plants. Prototype equipment will not be
accepted. A reference list shall be supplied by the Contractor in his
quotation. This list shall include the name of the end user and details of the
system application size, model, release etc.
For the system offered, a guarantee shall be given that spare parts will still
be available at least 15 years after commissioning of the plant and the
provided system shall be compatible with the future upgrading of the
system.
The DCS system shall achieve the functions of data acquisition, signal
conditioning, closed-loop control, open-loop control, calculation, alarm
processing and annunciation, sequence of event recording, historical and
real time trend recording, graphic display of process and communication
with other devices/systems.
It shall be suitable for control and monitoring of all main plant processes.
System Configuration shall be user friendly, i.e. simple and flexible with
regard to re-configuration of loop connection and display formats to suit
changes in operational requirements. System software security, including
data base configuration, controller loop tuning parameters shall be available.
The highest demands are placed on the control and monitoring equipment
with regard to availability, plant safety and reliability. All central
components that can affect large part of the plant operation shall be
redundant with hot standby, that is duplicated with automatic switch-over
and fault reporting and diagnostic facilities.
B8 - 17
The data highway system shall be completely duplicated and spatially
separated. Different routing for the cable trays shall be foreseen. The second
system must be in hot stand-by. Failure of one of the data highways shall not
reduce the availability of any of the system components or degrade system
performance. Fail over from one data link to the other shall be automatic.
Connection of additional equipment shall be possible on line without
disrupting operation. Any data communication failure shall not disrupt
process control.
The main machine interface controllers shall be redundant and support all
the VDUs. In the event of a controller failure, all VDUs shall be available
for control and monitoring functions.
The DCS shall mainly consist of process stations, data highway and operator
stations.
B8.3.4.4.1 General
B8 - 18
The main functions of the process stations shall be acquisition of digital and
analog signals from the process, signal conditioning and processing, output
of digital and analog signals, closed-loop control and open-loop control.
Control loops that obtain data via the data highway shall revert to safe state
on data highway transmission failure.
Failures shall be indicated by alarms and LED's, and logged, including the
hardware address of the failed module.
Dedicated hardware modules for input and output signal conditioning shall
be provided. The process I/O shall be able to accept signals from
commercially available signal sources. Conversion into engineering units
and linearization of the signals shall be possible.
The outputs of analog and binary output cards shall be short-circuit proof.
To compensate for possible hardware failure on testing, an 'override
function' shall be available to allow 'forcing' of the measurement associated
B8 - 19
with a specific hardware input point (analog or digital) or to mask changes
to an output (digital).
The Tenderer shall explain in his offer his philosophy to achieve the
requested high availability, i.e. redundant or decentralized design of the I/O
modules. If he has chosen the decentralized design he shall indicate the
degree of decentralization by giving the number of different I/Os per
module. The redundant design will be preferred.
Analog I/O
The following minimum requirements shall be considered for the analog I/O
modules:
• For the analog inputs the system software shall check for signal integrity
and if the input signal exceeds ±5% of the specified range the
measurement shall be declared invalid.
• The analog output modules shall provide 4 - 20 mA DC, capable of
driving up to 600 ohms total loop resistance.
• Each analog output shall be short-circuit proof.
• Normal thermocouple linearizations shall be accurate to 0.25 °C of the
measured temperature. All type of thermocouples linearization shall be
available. For thermocouple signals automatic compensation of cold
junction temperature shall be provided. Cold junction compensation in a
special cold junction compensation box outside the DCS is acceptable.
• Linearity shall be within 0.2% of all inputs.
• For analog 4-20 mA inputs, the inputs resistance shall not remain under
250 ohm, due to the requirements of SMART-Communication.
• Analog inputs shall contain over-range protection circuits to protect the
equipment from ground faults or high voltage either in common or
normal mode. Ground fault detection alarm shall be provided.
• Analog signals shall be programmable per channel.
Binary I/O
The following minimum requirements shall be considered for the binary I/O
modules:
• Inputs shall be individually isolated.
• The binary input modules shall be able to supervise the circuit integrity
and they shall ensure that the current through the closed contacts of
binary transmitters shall be at least 3 mA.
• Input modules for pulse inputs shall be available.
B8 - 20
• Input modules for proximity switches shall be available.
• The digital output modules shall provide dry contacts rated at 2 amperes,
24 V DC.
• The system shall have the capability to provide faster scan rates for some
selected digital points (Sequence of Event Recording), a scan rate of 10
milliseconds per point or better shall be possible.
Electric valve positioners shall be of solid state type (no contacts), plug
in/drawn out units and shall be accommodated in cubicles in the electronic
room.
The closed-loop control system shall permit control actions from the open-
loop control system, such as automatic MANUAL/AUTO switch-over and
controlled OPEN/CLOSED actions of the control valve, and shall issue
corresponding checkback signals to the open-loop control systems.
The normal closed-loop function shall be guaranteed also independently of
the open-loop control system.
Besides the modulating control function PID, the controllers shall contain
facilities for bumpless transfer, anti-reset windup, auto/manual switching,
cascading, feed-forward control, signal exchange with open-loop controls,
etc.
B8 - 21
In the event of failure of the auxiliary power supply or withdrawal of a plug-
in element, the control valves shall retain their position, or if necessary
traverse to a position which is safe for the process. Faults in the power
supply shall not result in any unwanted or dangerous switching actions.
Cascade control
The tracking of cascade loops must be done automatically so that the manual
balances and bumpless operation can be achieved at any time without
having to specially configure the signal tracking.
Feed-forward control
The system must allow implementation of feed-forward control applications
and ratio-control applications. Standard algorithms like lead/lag logic, ratio
control and free programming capability must be provided. Moreover,
facilities to activate and deactivate feed-forward and ratio controls must be
provided.
General
Open-loop control system shall be hierarchically organized and shall contain
individual drive controls and sequential controls for drive, group level,
functional group and unit level. In addition to these control levels the
protection and safety interlocks of the drives shall be provided by the open-
loop control system.
B8 - 22
To allow for the process redundancies 'Functional distribution' shall be
provided i.e. the grouping of the functional subgroups controlled by one
common redundant microprocessor shall be done in such a way that the loss
of the controller shall not cause any dangerous operational conditions or
plant shutdown. For example, if the control of feedwater pump 1 is
disturbed, the control of feedwater pump 2 must still be available.
Group controls must be capable of being switched 'on' and 'off' and must
have defined commands for 'automatic' and 'manual'.
Any faults in the control system, which could cause the control sequence to
stop, must be confined to one control sequence.
Any faults in the control system or in the plant equipment must lead to an
automatic changeover from a faulty unit to an appropriate stand-by unit.
If a sequence control is stopped for any reason it should be possible to :
For this reason jump conditions shall be foreseen. Before entering in the step
the sequence logic shall check the status of the jump condition. If the jump
conditions is fulfilled the respective step commands will not be executed
and the control sequence will be continued with the next step of the
sequence.
Drive control
Every remote operated drive or circuit breaker shall be controlled by means
of a software drive control module as the standard interface between the
DCS and the switchgear. To this module all orders i.e. from the operator
station via the keyboard, step signals of the control sequences, interlocks or
protection as well as all check-back signals of the drive or switchgear shall
be connected. After the processing of these signals the control module shall
issue the order to the switchgear via coupling relays.
B8 - 23
The Tenderer shall describe in his offer the hardware and software modules
he intends to use for the drive control.
In the event of any tripping or failure, a group signal must be passed via the
annunciation equipment and the fault status must be displayed individually
for each drive in the appropriate operation display on the operator station.
For unidirectional motor drives (pumps, fans) the issued command shall be
an impulse (e.g. reset by switchgear feedback signal) which shall be
memorized in the switchgear by selfholding, so that the interposing relays
shall not be permanently energized.
For reversing drives (actuators for valves, dampers), the control command
shall be reset by stroke end or by torque switches. Drives/actuators with
intermediate positions shall be designed either with a stop command or for
inching operation.
B8 - 24
The interposing relays shall be housed in the motor control centers of the
switchgear and are to be considered as part of the open-loop control system.
Solenoid valves that do not exceed the drive control module power limit
may be energized directly from the drive control module.
The control commands from the drive control module to the switchgear
shall be transmitted to the switchgear through two interposing relays, one for
the ON and one for the OFF command. The coils of the interposing relays
shall be connected with free wheeling diodes.
Active and passive interlocks must not be capable of being switched off
operationally from the control room. All protections have to work fully
automatically and independent of the operator and always have to be
effective for all procedures (manual, partial automatic, fully automatic).
After a stop or close action by protection, the restart of the equipment shall
be possible only after the fault is rectified and the protection signal is reset.
Simple cancellation of protection signal by start command shall not be
possible. The protection action and the operator reset shall be recorded by
the DCS.
B8 - 25
B8.3.4.4.6 Interlocks for alarm annunciation
The communication system shall have all necessary fault diagnostics. Any
errors shall be alarmed and recorded in the CCR.
Operation of dual highway system shall be such that failure of one highway
shall not affect the operation of the plant and control shall be automatically
switched from failed highway to the functioning one.
In case of loss of both data highways, the individual controllers must remain
in operation. Under no circumstances shall one single failure lead to an
outage of the complete data system.
The data protocol used shall safeguard against erroneous data transmission
and allow for error detection, recovery and initiate switch-over to the
redundant data highway.
B8.3.4.6.1 General
All analog signals from field equipment shall be shown on the CRT's, in the
dynamic graphic displays or/and other displays. It shall be possible to
provide a historical and real time trend display for analog and status signals.
B8 - 26
For high availability of the plant redundant operator stations have to be
provided. In case if one operator station should fail, operation of the plant
shall still be possible using the remaining operator stations.
The CRT update and process response time shall be less then 2 second.
• Operator desk
• CRTs (see B8.3.2)
• One functional keyboard
• One mouse or trackball
• Printers (see B8.3.2).
Each of the operator desk stations shall also be equipped with the
communication equipment.
Generally, it must be possible to supervise any unit and any part of the plant
from every operator station.
Hardwired emergency push buttons for boiler trip, turbine trip and generator
trip and a minimum number of discrete controls shall be provided on the
control desks to allow the units to be shut-down safely in the event of major
DCS failure.
• Operator desk
• CRTs (see B8.3.2)
• One functional keyboard
• Hardcopy printers (see B8.3.2).
At the operator station the operator must be able to choose any kind of
display and execute control on any of the unit assigned CRTs from any of
the keyboards.
B8 - 27
All necessary information concerning process behavior, control instrument
and controller integrity for modulating control, sequential control and alarm
function shall be immediately available to the operator at the operator
station.
The system shall be provided with the main and bulk memories of adequate
size including 20% spare capacity, i.e. 20% of the installed memory shall be
free for future extended functions. If during execution of this project,
memory sizes prove inadequate, Contractor shall increase memory at no
cost.
Bulk memory shall be provided with hard disks and shall be redundant.
Floppy disks or tapes shall not be used for holding foreground programs or
their data. They may be used only to load and to extract programs or data.
All data entry and operator commands shall be subject to two steps of
operating action so as not to cause any inadvertent actions. Regularly used
keys shall be of extra rugged design. Keyboard operation must be conceived
in such a manner that the selection of the different displays and access to the
process variables, motors and actuators shall be possible directly from a
dedicated functional keyboard, with only a few key strokes. In critical
situations the switch from a general display to a display suitable for direct
B8 - 28
control must be possible directly without the need to select additional
intermediate displays.
For the arrangement of CRT’s and control equipment in the control desk, the
Contractor shall provide an ergonomic design of modern furniture matching
the control room design. Each operator station shall include a conventional
control desk Section for hardwired controls such as emergency shut down
functions, etc. Lighting of the control room shall be chosen and designed in
such a way that shall not have any reflection and white spot on the CRTs.
The system software shall contain functional software modules that will
perform the basic control, monitoring and calculations. Function blocks in
the form of standard software modules shall be available.
The function blocks will be linked to build the required control functions.
Implementation of the control functions shall be easily possible using
readily understandable configuration procedures. All configuration
modifications shall be implemented on- line. The software shall be menu
driven. There shall be no requirement to write basic software machine
program for any update or modification.
The library of software modules shall contain all the functions required for:
B8 - 29
The configuration control software must include provisions for setting each
loop's scan rate. The configuration software must also be able to be
implemented by means of fill in the blank templates or other user friendly
approaches that allow the user to easily create and modify control strategies
by lining the predefined algorithms.
The DCS system must have provision to develop sequences and must be
capable of being programmed directly from logic flow charts using an
operator oriented language.
The MMI of the DCS shall include a hierarchic visualization concept tuned
to the requirements of plant operation. Through it the operator
communication and monitoring shall be performed.
For this purpose graphic elements (plant displays, curves, loop displays,
alarm displays, operating windows etc.) arranged in an hierarchic order shall
display easily, quickly and transparently the status of the plant, of the control
equipment and of the control loops.
The highest demand in the designing of the MMI shall be placed on user
friendly displays. For the control room operator displays for monitoring,
information and control functions shall be provided. The displays shall
present process sequences and statuses in a functionally related manner.
MMI update
The system shall be capable of processing all inputs in such a manner that
all displayed data shall be updated within maximum 1 sec. for analog inputs
and within maximum 1 sec. for digital inputs. The system must be capable
of accepting spontaneous events from the process with a time resolution of
10 ms (SER function), independent from the above mentioned scanning
cycle times. The system shall however be capable of inhibiting any nuisance
alarms during the period when the equipment is out of service.
VDU Structure
The tenderer shall design and propose the VDU structure, operator control
function templates, mimic display standard, symbols standard, piping and
alarm color code for the Owner’s approval.
The structure shall include, but not limited to, content with key assignment,
overview display, P&I Ds, single line diagram, control station, Mill &
burner management system, drive level, sub group level, group level, unit
level, alarm summary, alarm functional group summary, SOE recorder,
B8 - 30
trending, process parameter, maintenance functions, reporting, on load test,
Permit To Work management.
The VDU mimics shall have all the required parameters and control
functions for operator perusal. The parameters shall include, but not limited
to, equipment status, process values, setpoints, control output,
valve/damper/coupling position, control status, breakpoint status, sequence
timing, permits, protection parameters, sequence status, shift & monthly
management reports, transmitter redundancy and selection, process
parameters status and alarm points, DCS hardware and module status, etc.
Overview display
An overview display shall enable the operator to determine the overall
operation of a large segment of the plant. It shall indicate the alarm status of
all loops. The operator shall be able to call up directly any overview display.
B8 - 31
All new alarm messages shall be displayed on the next available line and
shall flash until acknowledged from the keyboard. Every new alarm shall
activate a bell to call the attention of the operator. There shall be dedicated
bell annunciation for alarm, fault and trip status. If more alarms are detected
than are to be shown on the CRT, more recent ones shall be displayed and
the earlier messages shall be shifted to the alarm backlog memory. In this
case a special message on the screen will indicate presence of messages in
the backlog memory. A key facility to recall the backlog messages on the
CRT display shall be provided.
Loop display
The loop display shall contain all detail information of the individual control
or measurement loop, including:
The detailed information shall be key coded or access code word protected
from unauthorized alteration.
Trend display
The system shall be capable of displaying both real time and historical
trends as follows:
• Real time trend. The real time trend shall be for a minimum of 8 hours at
a sampling rate of 10 seconds.
• Historical trend. The historical trend shall be for a minimum period of
96 hours. Historical data shall be stored on a non-volatile memory device
such as hard disk. It shall be able to be archived for recall.
B8 - 32
The available storage shall be sufficient for all analog points for a period of
one month at a sampling rate of 10 seconds or better. Varying the sampling
rate or producing averages such as one minute, two minute etc. shall make it
possible to store more points or for longer periods.
The system shall also have a multi-trend feature from which it shall be able
to display the set point, measured variable and output of any combination of
variables on the same trend variable.
When a particular operator input has been accepted by the DCS, this
condition shall be indicated to the operator by a change of color, short
blinking, short audible tone etc.
• Entering/setting of value
• Confirmation/execution of the entry.
In all cases the current and the entered data shall be shown separately.
B8 - 33
Logging
The system shall be able to assemble data and print various kinds of
standard reports, all of which shall be also available on demand keystroke.
The system shall provide the following basic types of reports as a minimum:
• Event lists
• Operator action reports
• Custom reports with fixed and variable formats.
The above reports shall use real time data, historical data, or calculated data
generated, by any node in the system or any connected device to the system
such as PLC's or process computers. All points in the system shall be
available for logging.
• On demand
• At a predefined time (hourly, shift, daily, etc.)
• Event triggered
• Real time events with six hours worth of data to help in diagnosing
shutdown incidents.
Demand for immediate output of a report must not affect any scheduled
reports that have been set up previously.
The report generator must be able to build and print many types of reports.
These will include:
• Sequence programs
• Historical summary reports for hourly, daily, etc. type activities
• Instantaneous reports for such items as current plant status.
The types or classes of data used by the report generator must include:
B8 - 34
• Calculated variables
• Historical data values and status
• Other retrievable tagged items.
The report generator must also be able to incorporate text supplied for report
titles, subheading, messages, etc. Data validity indicators must be
propagated throughout report production to provide information on the
reliability of requested values.
Math functions must be a standard part of the report package. The software
package must be easy to use and not require programming skills.
All alarms and events of the power plant shall be recorded in the DCS alarm
summary, functional group alarm summary, alarm and event printers.
Alarm shall be prioritized and identified with color coding depending on the
priority of the alarm as follows:
• Trip
• Very High/Very Low
• High/Low
• Control module/hardware failure
• Bad quality input/parity fault
B8 - 35
Alarms shall have pop up link to the related VDU mimics for prompt
identification of source of abnormality.
The SER shall monitor detailed tripping signals for boiler trip, turbine trip,
generator trip and major auxiliaries.
SER shall be required to record all tripping signals and sequence as per real
timing to enable correct diagnosis and analysis.
During the tripping, SER log shall be available on the DCS and print out.
B8 - 36
• The alarm condition of each point shall be clearly shown in group
graphics and individual point displays. Alarms shall be displayed as they
happen on the correct screen in the allocated area. It shall be easy to
determine from these displays if the alarm has been acknowledged (for
example, blinking indication for not acknowledgment alarms).
• System alarms.
If alarms transmitted from other control systems (e.g. black boxes) to the
DCS via a serial links are processed in the SER then this alarms have to be
transmitted with the corresponding time tag and the clocks of the two
control systems have to be synchronized. If this requirement cannot be
fulfilled then the processing of these signals in the SER is not allowed.
In this case the important alarms from the black box's control system shall
be hardwired to the DCS.
The most important requirement for the SER function is that in case of plant
upsets correct time information shall be available for all signals processed in
the SER and that all signals of the plant which can trigger plant upsets shall
be included in the SER , i.e. the offered SER shall be a plant wide SER.
Clock system
The clock system shall interface to a GPS Master clock Receiver to provide
accurate time for the DCS slave clocks and the other slave clocks into the
associated systems.
B8 - 37
The engineer's console shall allow system configuration, writing and
executing of user written macros, graphics development, report generation,
logging specification, system self documentation functions, system
monitoring functions (which show the result of self diagnostic tests), system
database load/save etc. In addition it shall be possible to tune controllers,
change limit set-points, view all loop variables, configure control systems,
add and delete alarms, change data of the DCS in online operation, set input
and output signals as well as internal variables, with automatic logbook
functionality of executed simulations.
Finally, the system must enable the diagnosis and parameterization of the
SMART transmitters.
Printers shall be provided allowing for CRT hard copies, configuration and
parameter printout etc.
The system shall monitor itself continuously for failures by means of self-
diagnostics. Diagnostic routines shall be applied for each control module.
Detailed diagnostic messages shall be displayed on the instrument
engineering console's CRT and printer, and group alarms shall be given at
the process operator's desk.
Diagnostic displays shall be available to assist fault location. It is expected
that most faults will be quickly repaired by simple replacement of a card or
module. The diagnostic display shall clearly identify the faulty component,
the nature of the fault and the component location.
The Tenderer shall submit with the offer a description of the offered
engineering station and the diagnostic hardware/software/displays.
Examples of the different type of design documentation and methodology
shall be included and explained with the offer in regard to system software.
B8 - 38
B8.3.5 Boiler protection system (BPS)
• The equipment shall be recognized third party audited or certified for this
kind of application
• There shall be numerous systems of this kind in use for industrial control
• Hardware and software shall be standard catalogue products
• The application program, once defined is not user variable.
Redundant output channels must not be on the same circuit board or in the
same bin.
Output channels shall be short circuit proof.
B8 - 39
B8.3.5.5 Emergency shut-down
In case of a major failure of the DCS a safe shut-down of the plant must be
guaranteed. The fail safe control system must bring the plant into a safe
operational status in this case.
B8.4.1 General
There are associated analog and digital signals which are required for
effective operations of the AGC, amongst which are set point feedback,
AGC control request, unit selected on AGC control, AVR on auto, unit
active power, unit reactive power, base / droop mode, LFC upper limit, LFC
lower limit, ramp rate and also block / unit mode. The final signal list
required for the AGC will be mutually agreed between Tenderer, customer
and TNB during project implementation.
The SCS may communicate with the Facility either by serial communication
link or by hardwired connection. In the former, dual redundant links and
B8 - 40
communication apparatus must be provided. However, the watchdog
signaling logic must be hardwired so that this will continue to operate
effectively even during SCS failure.
ii. Output
• Unit Gross MW
• Unit Gross MVAr
• Unit Net MW
• Unit Net MVAr
• Block Net MW
• Block Net MVAr
B8 - 41
• Ramp Rate Up
• Ramp Rate Down
• High Regulation Limit
• Low Regulation Limit
• Unit Active Power Setpoint Feedback
• Unit Reactive Power Setpoint Feedback
• Block Active Power Setpoint Feedback
• Forbidden Zone Low Limit
• Forbidden Zone High Limit
The following is a description of how some of the data listed above are to be
used or implemented for AGC purposes.
UNIT DCS
AGC REQUEST ON/OFF (1-bit digital)
MW SETPOINTS (analog)
• The Figure above shows the input and output signals needed for AGC.
B8 - 42
• Only one analog signal will be sent by Control Center to the DCS, i. e.
the MW Set-point (MWSPNT). This is the input signal to the station’s
unit / block controller (4-20 mA signal).
• The MW Set-point (MWSPNT) is what Control Center requires the
station’s unit / block to produce after the generator transformers, that is
MW output on the HV side (Net MW Output). The station’s unit / block
controller thus has to ensure that the Gross MW Output caters not just
for the transformer losses, but also for the auxiliary consumption to
ensure that the Net MW Output matches the given MW Set-point.
XFormer
Gross MW
~ Net MW
Auxiliary
B8 - 43
• The following is the functional requirements for all units operating under
AGC.
Set point sent less than b) Wait for a valid set point
LFC min from Control Center or auto
revert to LOCAL and wait for
plant operator intervention
Set point 0
6 Reactive power MVAr control Independent of AGC controls
control
B8 - 44
Function Category Requirements
7 Free governor The free governor must be
operational whilst under AGC
with the specified dead band
and droop settings
8 Regulation Range Unit / Block must have a
contiguous regulation range
that is at least 40% of its
capacity
The following data are required for transmission switchgear monitoring and
control
B8 - 45
• Distance Protection Main 2 Operated
• Distance Protection Zone 1 Trip
• Distance Protection Zone 2 Trip
• Distance Protection Zone 3 Trip
• Distance Protection Red-Yellow
• Distance Protection Red-Blue
• Distance Protection Yellow-Blue
• Distance Protection Red-Earth
• Distance Protection Yellow-Earth
• Distance Protection Blue-Earth
• Power Swing Block
• Current Differential Protection Red Phase
• Current Differential Protection Yellow Phase
• Current Differential Protection Blue Phase
• Directional Earth Fault Trip
• Overcurrent Protection Trip
• Stub Protection Trip
• Thermal Overload Trip
• Switch Onto Fault
• Trip Circuit Supervision
• Protection Relay Faulty
• Relay Panel MCB Trip
• Control Panel MCB Trip
• Intertrip Receive
• Intertrip Send
• Carrier Receive
• Carrier Send
• Master Trip Relay Operated
• Breaker Failure Trip
• VT MCB Trip / VT Supervision
• CB Spring Uncharged
• Pole Discrepancy
• SF6 Low Stage 1
• N2 Low Stage 1
• Oil Level Low
• SF6 Low Stage 2
• N2 Low Stage 2
• CB Lock Out
• CB Lock In
• Single Pole Auto Reclose
• Three Pole Auto Reclose
B8 - 46
• Auto Reclose Attempt
• Auto Reclose Maintenance Alarm
• Auto Reclose Lock Out
• Auto Reclose Out Of Service
• Auto Reclose Syncheck Fail
• Under Frequency Trip
• Under Frequency Stage 2 Trip
• Under Frequency Stage 3 Trip
• Under Frequency Stage 4 Trip
• Line MW
• Line MVAr
• Busbar Voltage (for each busbar / section)
• Busbar Frequency (for each busbar / section)
The SCS must block the Control Center execution of “Master Trip Relay
RESET” for the affected circuit breakers under the following conditions of
tripping:
• Busbar Protection
• Breaker Failure
• Transformer Differential Protection
• Transformer Bucholz
The following data are required for transformer monitoring and control.
B8 - 47
• LV Bus Coupler OPEN / CLOSE
• LV Section OPEN / CLOSE
• Neutral Earthing Switch OPEN / CLOSE
B8 - 48
• AVR Supervisory Override SELECT / CANCEL
• Tap Changer RAISE / LOWER
The following data are required for substation common alarms and
measurements.
B8 - 49
B8.5 Technical requirements Communication system
A telephone set should be installed in each room with located personnel and
in every main process area, as like as near to the local control panels.
• Internal traffic
Internal calls are set up automatically by all subscribers via the central
exchange.
• Direct outward dialing
Outgoing trunk lines will be provided for connection to the Malaysian
public telephone network telephone system.
• Incoming calls go direct, or if the extension number is not known, the
operator can connect the caller to the required subscriber.
• After normal working hours or if the switchboard is unattended,
incoming exchange calls go straight through to one or more extensions.
All lines with external link shall be protected against any high transient in
voltage due to lightning.
The system shall not require standby batteries for its operation.
B8 - 50
The system shall be modular in design, enabling flexibility in
re-configuring, building up and expanding the system when required.
Besides the exchange lines, one fax line and one dedicated fire signaling line
to a fire station, inclusive of the digital communicator, shall be provided.
The complete public address (PA) system shall conform with the latest state of
art in the field of P.A. system engineering.
1 – fire alarm
2 – major, large-scale breakdown
3 – gas alarm
4 – all-clear signal (for resetting of alarm)
B8 - 51
• collective call of all loudspeaker lines.
The loudspeaker lines shall be organized for the following zones (minimum)
inclusive of the rooms, which belong to them:
The number and placing of the respective loudspeakers shall suit the
conditions of operation and of the environment in such a way that broad cast
announcements can be clearly understood by the operating personnel at
every corner of the plant including the sub-station, non-technical buildings,
etc. The P.A. system shall serve the whole plant complex, including
non-technical areas.
The control base station shall be located in the control room. It shall be
communication via a desk top loudspeaker/microphone console.
B8 - 52
B8.5.4 CCTV
Colored closed circuit TV shall be provided for the observance of the plant
which shall include, but not limited to:
In each case, the CCTV system shall withstand to the site environment. The
CCTV system shall have facilities of remote control, pan, tilt, zoom, focus
and other latest technology functions. For outdoor cameras humidity
conducts shall be provided.
The Tenderer shall be clearly describe the CCTV system philosophy and
configuration.
Monitors shall be supplied with a hood to avoid glare and shall be of the
non-reflecting type. As a minimum requirement the monitor shall have a
screen of diagonal measurement of not less than 440 mm.
All the supplied equipment shall be for 240 V, 50 Hz power supply, without
any step-down transformers. The power supply shall be taken from the UPS
busbar.
B8 - 53