Professional Documents
Culture Documents
SAINT LUCIA
ARRANGEMENT OF REGULATIONS
PRELIMINARY
Regulation
1. Citation
2. Interpretation
3. Application
PART I
DECK LINE, LOAD LINE MARK AND LOAD LINE
PART II
ASSIGNMENT OF FREEBOARD AND CONDITION OF ASSIGNMENT
PART III
INITIAL SURVEY, RENEWAL SURVEY AND ANNUAL SURVEY
PART IV
LOAD LINE CERTIFICATE AND EXEMPTION CERTIFICATE
PART V
MISCELLANEOUS
SCHEDULE 1
SCHEDULE 2
SCHEDULE 3
SCHEDULE 4
SCHEDULE 5
SCHEDULE 6
SCHEDULE 7
263
Shipping (Load Line) Regulations
SAINT LUCIA
STATUTORY INSTRUMENT, 2019, No. 97
PRELIMINARY
Citation
1. These Regulations may be cited as the Shipping (Load Line)
Regulations, 2019.
Interpretation
2. In these Regulations —
“Act” means the Shipping Act, Cap. 13.27;
“amidships”, in relation to a ship, means the middle of the
ship’s length (L);
“appropriate load line” means a load line described under
regulation 5(3), 6 or 28;
“appropriate marks” means a deck line, load line mark and
load line;
“Caribbean Trading Area” means the area bounded by a line
from a point on the east coast of the United States of
America in latitude 35o00’ north, to a point 5o00’ south,
33o00’ west; thence to a point 10o00’ south, 33o00’ west;
thence to a point on the coast of Brazil in latitude 10o00’
south; then northward along the coast of Continental
America to a point in latitude 35o00’ north, on the east
coast of the United States of America;
“condition of assignment” means the condition relating to
construction, arrangement and stability with which a ship
must comply in order to be assigned a freeboard;
264
Shipping (Load Line) Regulations
more than one hundred and fifty miles from a safe port of
refuge;
“non-Saint Lucian ship” means a ship other than a Saint Lucian
ship under section 12 of the Act;
“sailing ship” means a ship designed to carry sail, whether
as the sole means of propulsion, or as a supplementary
means;
“Saint Lucian Local Load Line Certificate” means an
appropriate certificate under section 311(2)(b) of the Act;
“Saint Lucian Local Load Line Exemption Certificate” means
an appropriate certificiate issued under section 318(2)(b) of
the Act;
“watertight”, in relation to any part of the ship, means capable
of preventing the passage of water in any direction.
Application
3. Subject to section 307 of the Act, these Regulations apply to
Saint Lucian ships, on an international voyage or while in Saint Lucian
waters and to foreign ships while in Saint Lucian waters.
PART I
DECK LINE, LOAD LINE MARK AND LOAD LINE
Fig.4 Timber Load Line Mark and lines to be used with this mark
PART II
ASSIGNMENT OF FREEBOARD AND CONDITION OF
ASSIGNMENT
Assignment of freeboard
10.—(1) The Minister or person or organization authorized by the
Minister shall, in accordance with Schedule 2, assign to a new Saint
Lucian ship —
(a) a Summer Freeboard;
(b) a Tropical Freeboard;
(c) a Winter Freeboard;
(d) a Winter North Atlantic Freeboard;
(e) a Fresh Water Freeboard;
(f) a Tropical Fresh Water Freeboard;
272
Shipping (Load Line) Regulations
the vertical distance by which the position of the deck line is altered
under that regulation.
(2) The reference point to which the deck line has been marked,
and the identity of the deck which has been taken as the freeboard
deck, must be specified in the certificate issued in respect of the ship.
Condition of assignment
12. A ship to which a freeboard is assigned under regulation 10
must comply with the condition of assignment applicable to that ship
and set out in Schedule 3.
Record of particulars
13.—(1) A record of particulars relating to a condition of assignment
in the form set out in Schedule 4 must be provided on a ship.
(2) A record of particulars under subregulation (1) must be
furnished to the Minister or a person or organization authorized by the
Minister and be retained on board at all times.
Equivalents
15.—(1) A ship which fails to comply with a condition of assignment
specified under regulation 12 may be required to meet equivalent
conditions in accordance with subregulation (2).
Notice
16.—(1) A notice of the draught and freeboard relating to the depth
to which the ship is loaded, the density of the water in which the ship is
floating and all other related particulars under section 332(2)(b) of the
Act must be in the form set out in Schedule 5.
(2) Subregulation (1) does not apply to a ship employed on a Near
Coastal Voyage.
275
Shipping (Load Line) Regulations
PART III
Survey of ship
19. A Saint Lucian ship is subject to —
(a) an initial survey under regulation 20;
(b) a renewal survey under regulation 21; and
(c) an annual survey under regulation 22.
Initial survey
20.—(1) Before a ship is put into service, the owner of the ship shall
make an application to a surveyor of ships for an initial survey.
(2) In an initial survey a surveyor of ships shall —
(a) include a complete inspection of a ship’s structure and
equipment under these Regulations; and
277
Shipping (Load Line) Regulations
Renewal survey
21.—(1) Within three months before the expiry of a Load Line
Certificate or after the expiry of a Load Line Certificate, the owner of
a ship shall make an application to a surveyor of ships, for the purposes
of section 321(2) of the Act, for a renewal survey.
(2) In a renewal survey, a surveyor of ships shall ensure that the
structure, equipment, arrangements, materials and scantlings comply
with these Regulations.
Annual survey
22.— (1) The owner of a ship shall make an application to a surveyor
of ships for an annual survey, for the purposes of section 321(3) of the
Act, three months before or after the expiry of a Load Line Certificate.
(2) In an annual survey the surveyor of ships shall ensure that —
(a) alterations have not been made to the hull or super
structures which would affect the calculations determining
the position of the load line;
(b) the fittings and appliances for the protection of openings,
guard rails, freeing ports and means of access to crew’s
quarters are maintained in an effective condition;
(c) the appropriate marks are correctly and permanently
indicated; and
(d) information is provided under regulations 17 and 18.
(3) A surveyor of ships shall, on being satisfied with the annual
survey under subregulation (2), endorse the Load Line Certificate.
PART IV
PART V
MISCELLANEOUS
Detention
33. If a ship is detained under section 334 of the Act, section 458
of the Act applies in relation to a detention notice issued under section
460 of the Act as it applies in relation to section 457 of the Act.
283
Shipping (Load Line) Regulations
SCHEDULE 1
(Regulation 6)
2.4.2 North Atlantic Winter Seasonal Zone II, as set out in paragraph
4.2 as lies between the meridians of longitude 150W and 500W;
during the winter seasonal periods applicable in those zones;
2.5 the Summer load line, in the case of a sailing ship, except in
circumstances in which subparagraph 2.4 applies;
2.6 an All Seasons load line, in the case of a ship marked under
regulation 8;
2.7 the Timber load line, corresponding to the seasons and zones, in
the case of a ship marked with Timber load lines and carrying timber
deck cargo.
Seasonal periods:
WINTER: 16th day of October to 15th day of April.
SUMMER: 16th day of April to 15th day of October.
4.2 The North Atlantic Winter Seasonal Zone II lies within the meridian
of longitude 68o 30’W from the coast of the United States to latitude
40oN, thence the rhumb line to the point latitude 36oN longitude 73oW,
thence the parallel of latitude 36oN to longitude 25oW and thence the
rhumb line to Cape Toriñana.
Excluded from this zone are the North Atlantic Winter Seasonal Zone I,
the North Atlantic Winter Seasonal Area and the Baltic Sea bounded by
the parallel of latitude of The Skaw in the Skagerrak.
285
Shipping (Load Line) Regulations
Seasonal periods:
WINTER: 16th day of October to 15th day of April.
SUMMER: 16th day of April to 15th day of October.
to the point latitude 34oS longitude 50oW, thence the parallel of latitude 34oS to
longitude 17oE, thence the rhumb line to the point latitude 35o10’S, longitude
20oE, thence the rhumb line to the point latitude 34oS, longitude 28oE, thence
the rhumb line to the point latitude 35o30’S, longitude 118oE, and thence the
rhumb line to Cape Grim on the northwest coast of Tasmania; thence along the
north and east coasts of Tasmania to the southernmost point of Bruny Island,
thence the rhumb line to Black Rock Point on Stewart Island, thence the
rhumb line to the point latitude 47oS, longitude 170oE, thence the rhumb line
to the point latitude 33oS, longitude 170oW, and thence the parallel of latitude
33oS to the point latitude 33oS, longitude 79oW, thence the rhumb line to the
point latitude 41oS, longitude 75oW, thence the rhumb line to Punta Corona
lighthouse on Chiloe Island, latitude 41o47’S longitude 75o53’W, thence along
the north, east and south coasts of Chiloe Island to the point latitude 43o20’S,
longitude 74o20’W, and thence the meridian of longitude 74o20’W, to the
parallel of latitude 45o45’S, including the inner zone of Chiloe channels from
the meridian 74o20’W to the east.
Seasonal Periods:
TROPICAL ZONE
Northern Boundary of the Tropical Zone
8. The northern boundary of the Tropical Zone is the parallel of latitude
13oN from the east coast of the American continent to longitude 60oW, thence
the rhumb line to the point latitude 10oN, longitude 58oW, thence the parallel
of latitude 10oN to longitude 200W, thence the meridian of longitude 20oW
to latitude 30oN and thence the parallel of latitude 30oN to the west coast of
Africa; from the east coast of Africa the parallel of latitude 8oN to longitude
70oE, thence the meridian of longitude 70oE to latitude 13oN, thence the
parallel of latitude 13oN to the west coast of India; thence the south coast
of India to latitude 10o30’N on the east coast of India, thence the rhumb line
to the point latitude 9oN, longitude 82oE, thence the meridian of longitude
82oE to latitude 8oN, thence the parallel of latitude 8oN to the west coast of
Malaysia, thence the coast of South-East Asia to the east coast of Vietnam at
latitude 10oN, thence the parallel of latitude 10oN to longitude 145oE, thence
the meridian of longitude 145oE to latitude 13oN and thence the parallel of
latitude 13oN to the west coast of the American continent.
Saigon is to be considered as being on the boundary line of the Tropical
Zone and the Seasonal Tropical Area.
287
Shipping (Load Line) Regulations
Seasonal periods:
TROPICAL: 1st day of November to 15th day of July.
SUMMER: 16th day of July to 31st day of October.
11.2 In the Arabian Sea
An area bounded on the west by the coast of Africa, the meridian of
longitude 45oE in the Gulf of Aden, the coast of South Arabia and the
meridian of longitude 59oE in the Gulf of Oman; on the north and east
by the coasts of Pakistan and India; on the south by the northern boundary
of the Tropical Zone.
Seasonal periods:
TROPICAL: 1st day of September to 31st day of May.
SUMMER: 1st day of June to 31st day of August.
11.3 In the Bay of Bengal
The Bay of Bengal north of the northern boundary of the Tropical
Zone.
Seasonal periods:
TROPICAL:1st day of December to 30th day of April.
SUMMER: 1st day of May to 30th day of November.
11.4 In the South Indian Ocean
11.4.1 An area bounded on the north and west by the southern
boundary of the Tropical Zone and the east coast of Madagascar;
on the south by the parallel of latitude 20oS;on the east by the rhumb
line from the point latitude 20oS, longitude 50oE, to the point
latitude 15oS, longitude 51o30’E, and thence by the meridian of longitude
51o30’E to latitude 10oS.
Seasonal periods:
TROPICAL: 1st day of April to 30th November.
SUMMER: 1st day of December to 31st March.
11.4.2 An area bounded on the north by the southern boundary
of the Tropical Zone; on the east by the coast of Australia;
on the south by the parallel of latitude 15oS from longitude
51o30’E, to longitude 114oE and thence the meridian of
longitude 114oE to the coast of Australia; on the west by the
meridian of longitude 51o30’E.
289
Shipping (Load Line) Regulations
Seasonal periods:
TROPICAL: 1st day of May to 30th day of November.
SUMMER: 1st day of December to 30th day of April.
11.5 In the China Sea
An area bounded on the west and north by the coasts of Vietnam and
China from latitude 10oN to Hong Kong; on the east by the rhumb line
from Hong Kong to the Port of Sual (Luzon Island) and the west coasts
of the Islands of Luzon, Samar and Leyte to latitude 10oN;on the south
by the parallel of latitude 10oN.
Hong Kong and Sual are to be considered as being on the boundary of the
Seasonal Tropical Area and Summer Zone.
Seasonal periods:
TROPICAL: 21st day of January to 30th day of April.
SUMMER: 1st day of May to 20th day of January.
11.6 In the North Pacific
Seasonal periods:
TROPICAL: 1st day of April to 31st day of October.
SUMMER: 1st day of November to 31st day of March.
11.6.2 An area bounded on the north and east by the west coast of the
American continent;on the west by the meridian of longitude
1230W from the coast of the American continent to latitude 33oN
and by the rhumb line from the point latitude 33oN, longitude
123oW to the point latitude 13oN, longitude 105oW; on the south by the
parallel of latitude 13oN.
Seasonal periods:
Seasonal periods:
TROPICAL: 1st day of April to 30th day of November.
SUMMER: 1st day of December to 31st day of March.
11.7.2 An area bounded on the north by the southern boundary of
the Tropical Zone; on the south by the parallel of latitude of
24oS from the east coast of Australia to longitude 154oE, thence by the
meridian of longitude 154oE to the Tropic of Capricorn and
thence by the Tropic of Capricorn to longitude 150oW, thence by the
meridian of longitude 150oW to latitude 20oS and thence by the
parallel of latitude 20oS to the point where it intersects the
southern boundary of the Tropical Zone; on the west by the
boundaries of the area within the Great Barrier Reef included
in the Tropical Zone and by the east coast of Australia.
Seasonal periods:
TROPICAL: 1st day of April to 30th day of November.
SUMMER: 1st day of December to 31st day of March.
SUMMER ZONES
12. The remaining sea areas constitute the Summer Zones.
However, for ships of one hundred metres or less in length, the area
bounded on the north and west by the east coast of the United States; on
the east by the meridian of longitude 68o30’W from the coast of the United
States to latitude 40oN and thence by the rhumb line to the point latitude 36oN
longitude 73oW; on the south by the parallel of latitude 36oN; is a Winter
Seasonal Area.
Seasonal periods:
WINTER: 1st day of November to 31st day of March.
SUMMER: 1st day of April to 31st day of October.
ENCLOSED SEAS
13. Baltic Sea
This sea bounded by the parallel of latitude of The Skaw in the Skagerrak
is included in the Summer Zones.
However, for ships of one hundred metres or less in length, it is a Winter
Seasonal Area.
291
Shipping (Load Line) Regulations
Seasonal periods:
WINTER: 1st day of November to 31st day of March.
SUMMER: 1st day of April to 31st day of October.
14. Black Sea
This sea is included in the Summer Zones.
However, for ships of one hundred metres or less in length, the area
north of latitude 44oN is a Winter Seasonal Area.
Seasonal periods:
WINTER: 1st day of December to 28th or 29th day of February.
SUMMER: 1st day of March to 30th day of November.
15. Mediterranean
This sea is included in the Summer Zones.
However, for ships of one hundred metres or less in length, the area
bounded on the north and west by the coasts of France and Spain and the
meridian of longitude 3oE from the coast of Spain to latitude 40oN; on the
south by the parallel of latitude 40oN from longitude 3oE to the west coast of
Sardinia; on the east by the west and north coasts of Sardinia from latitude
40oN to latitude 9oE to the south coast of Corsica, hence by the west and north
coasts of Corsica to longitude 9oE and thence by the rhumb line to Cape Sicié;
is a Winter Seasonal Area.
Seasonal periods:
Seasonal periods:
WINTER: 1st day of December to 28th or 29th day of February.
SUMMER: 1st day of March to 30th day of November.
292
Shipping (Load Line) Regulations
SCHEDULE 2
(Regulation 10(1))
ASSIGNMENT OF FREEBOARD
Interpretation
1. Expressions in this Schedule have the same meanings as those assigned
in Schedule 3, and —
“block coefficient (Cb)” means the product of —
where —
T(L - S)
(L)
where —
T is the mean thickness of the exposed sheathing clear of deck
openings;
(b) in a ship having a rounded gunwale with a radius greater than 4 per
cent of the breadth of the ship or having topsides of unusual form, the
depth calculated in accordance with subparagraph (a), would be the
depth for freeboard purposes of a ship having a midship section with
vertical topsides and with the same round of beam and the same area
of topside section as that of the midship section of the actual ship;
293
Shipping (Load Line) Regulations
Freeboards: general
2.1 Except as otherwise provided in subparagraph 2.2, the freeboards,
other than Timber freeboards, to be assigned to a ship shall be determined
in accordance with the provisions of Part I, and Timber freeboards to be
assigned to a ship shall be determined in accordance with Part II.
2.2 The freeboards to be assigned to —
2.2.1 sailing ships;
294
Shipping (Load Line) Regulations
2.2.2 tugs;
2.2.3 ships of wood or of composite construction or of other
materials;
2.2.4 ships with constructional features such as to render freeboards
determined in accordance with subparagraph 2.1 unreasonable
or impracticable; and
2.2.5 unmanned barges having on the freeboard deck only small
access openings closed by watertight gasketed covers of steel;
shall be determined in accordance with the provisions of Part III of
this Schedule.
where —
is the displacement in salt water in metric tons at the Summer
load waterline, and T represents metric tons per centimetre
immersion in salt water at that waterline.
295
Shipping (Load Line) Regulations
5.7 In the case of a ship constructed before the 8th day of June, 2000, the
following assumptions are made for the purposes of calculations under
subparagraphs 5.3.4 and 5.5.3 —
5.7.1 the vertical extent of damage is equal to the depth of the ship
at the point of damage, measured from and including
the freeboard deck at side to the underside of the keel;
5.7.2 the transverse penetration of damage is not more than one fifth
of the breadth of the ship (B), this distance being measured
inboard from the ship’s side at right angles to the centre line of
the ship at the level of the Summer load waterline. The depth
of transverse penetration damage assumed shall be that which
results in the most severe conditions;
5.7.3 except in the case of compartments under subparagraph 5.5.3.1,
no transverse bulkhead is damaged;
5.7.4 the height of the centre of gravity above the baseline is assessed
allowing for homogeneous loading of cargo holds and for 50
per cent of the designed capacity of consumable fluids and
stores.
5.8 In the case of a ship constructed on or after the 8th day June, 2000,
the following assumptions shall be made for the purposes of the calculations
under subparagraphs 5.3.5 and 5.5.4 —
TABLE 1
5.10.1 This subparagraph applies to a Type “B” ship of not more than one
hundred metres in length having enclosed superstructures the total
effective length (E) of which does not exceed 35% of the ship’s
length (L).
5.10.2 The freeboard calculated in respect of such a ship under paragraph
5.10.1 in accordance with subparagraphs 5.1, 5.2 and 5.9 must be
increased by the following amount —
5.11 In the case of a ship with a block coefficient (Cb) exceeding 0.68, the
freeboard calculated in accordance with subparagraphs 5.1 to 5.10 must
multiplied by the factor —
(Cb) + 0.68
1.36
5.12 Corrections in accordance with paragraphs 6 to 16 must be applied
to the freeboard calculated under subparagraphs 5.1 to 5.11 and,
subject to paragraph 3.3, the freeboard corrected is the Summer
freeboard to be assigned to the ship.
302
Shipping (Load Line) Regulations
Basic freeboard
6. In the following paragraphs “basic freeboard” means the accordance with
paragraph 4 or 5, whichever is applicable, but ship, the corrections referred to
in paragraph 4.3, or in the case of a referred to in paragraph 5.12.
(L) , in the case of a ship less than 120 metres in length; and
0.48
250 in the case of a ship of 120 metres or more in length.
7.2 Where (D) is less than (L), the basic freeboard of the ship shall be
15
reduced by —
millimetres
where, but only where, the ship has, subject to subparagraph 7.3 —
7.2.1 an enclosed superstructure covering at least 0.6 (L)
amidships;
7.2.2 an efficient trunk extending for the ship’s length; or
7.2.3 a combination of enclosed superstructures connected by
efficient trunks, being a combination extending for the ship’s
length.
303
Shipping (Load Line) Regulations
TABLE 2
Standard heights for intermediate lengths of the ship are obtained by linear
interpolation.
two-thirds of the fore and aft extent of the curvature to a maximum of one half
the breadth of the superstructure at the point of intersection of the curved end
of the superstructure with its side.
9.3.1 In the case of an enclosed superstructure of standard height, the
effective length of a superstructure (E) shall be, subject to subparagraph 9.3.3
—
9.3.1.1 its length; or
9.3.1.2 where the superstructure is set in from the sides of the ship,
its length modified in the ratio b/Bs, where —
9.3.1.2.1 “b” is the breadth of the superstructure at the
middle of its length; and
9.3.1.2.2 “Bs” is the breadth of the ship at the middle of
the length of the superstructure:
where the superstructure is only set in for part of its length, this
modification shall be applied only to that part.
9.3.2 In the case of an enclosed superstructure of less than standard height the
effective length of a superstructure, subject to subparagraphs 9.3.1 and 9.3.3
are its length reduced in the ratio of the actual height of the superstructure to
its standard height.
9.3.3 In the case of an enclosed superstructure consisting of a raised quarter
deck the effective length of a superstructure must, if the deck is fitted with an
intact front bulkhead, be its length subject to a maximum of 0.6 of the ship’s
length and, where not so fitted, be determined by treating the raised quarter
deck as a poop of less than standard height.
9.3.4 A superstructure which is not an enclosed superstructure as defined in
paragraph 9.3.1 has no effective length.
TABLE 3
PERCENTAGE OF DEDUCTION FOR TYPE “A” SHIPS
TABLE 4
Measurement of Sheer
12.1 The sheer is measured from the deck at side to a line of reference
drawn parallel to the keel through the sheer line amidships.
12.2 In ships designed with a rake of keel, the sheer is measured
in relation to a line of reference drawn parallel to the design load
waterline.
12.3 In flush deck ships and in ships with detached superstructures
the sheer is measured at the freeboard deck.
12.4 In ships with topsides of unusual form in which there is a step
or break in the topsides, the sheer is considered in relation to the
equivalent depth amidships.
12.5 In ships with a superstructure of standard height which extends
over the whole length of the freeboard deck, the sheer is measured
at the superstructure deck. If the height of the superstructure exceeds
the standard height the least difference (Z) between the actual and
308
Shipping (Load Line) Regulations
13. The ordinates of the standard sheer profile are given in Table 5 —
TABLE 5
14.2 If the after half of the sheer profile is greater than the standard
sheer profile and the forward half is less than the standard sheer
profile, no credit is allowed for the part in excess, and deficiency only
is measured.
14.3 If the forward half of the sheer profile exceeds the standard
sheer profile, and the after half of the sheer profile is not less than
75 % of the standard sheer profile, credit shall be allowed for the part
in excess. If the after half of the sheer profile is less than 50% of the
standard sheer profile, no credit shall be given for the excess of sheer
forward. Where the sheer in the after half is between 50% and 75%
of the standard sheer profile, intermediate allowances may be granted
for excess sheer forward.
14.4 If sheer credit is given for a poop or forecastle the following
formula is used —
s = yL1
3L
where —
s = sheer credit, to be deducted from the deficiency or added to the
excess of sheer;
y = difference between actual and standard height of superstructure
at the after or forward perpendicular; and
L’= mean enclosed length of poop or forecastle up to a maximum
length of 0.5 (L).
This formula provides a curve in the form of a parabola tangential to
the actual sheer curve at the freeboard deck and intersecting the end
ordinate at a point below the superstructure deck at a distance equal to
the standard height of the poop or forecastle. The superstructure deck
is not less than standard height above this curve at any point. This
curve is used in determining the sheer profile for the forward and the
after halves of the ship.
0.75 - s
2L
15.2 In the case of a ship with sheer less than the standard sheer
profile, the correction for deficiency of sheer determined in accordance
310
Shipping (Load Line) Regulations
where (L) is less than two hundred and fifty metres; and
TABLE 6
centimetres
313
Shipping (Load Line) Regulations
where —
Unmanned barges
21. The freeboards to be assigned to unmanned barges having on the
freeboard deck small access openings closed by watertight gasketed covers
of steel shall be freeboards determined in accordance with the provisions of
Part I of this Schedule omitting paragraphs 5 and 16. Such freeboards may be
reduced by such amounts not exceeding twenty-five per cent as the Director
may direct in each particular case.
FREEBOARD TABLES
TABLE A
TABLE B
FREEBOARD TABLE FOR TYPE “B” SHIPS
Length of Freeboard Length of Freeboard Length of Freeboard
Ship (metres) (millimetres) ship (metres) (millimetres) ship (metres) (millimetres)
24 200 72 754 120 1690
25 208 73 769 121 1709
26 217 74 784 122 1729
27 225 75 800 123 1750
28 233 76 816 124 1771
29 242 77 833 125 1793
30 250 78 850 126 1815
31 258 79 868 127 1837
32 267 80 887 128 1859
33 275 81 905 129 1880
34 283 82 923 130 1901
35 292 83 942 131 1921
36 300 84 960 132 1940
37 308 85 978 133 1959
38 316 86 996 134 1979
39 325 87 1015 135 2000
40 334 88 1034 136 2021
41 344 89 1054 137 2043
42 354 90 1075 138 2065
43 364 91 1096 139 2087
44 374 92 1116 140 2109
45 385 93 1135 141 2130
46 396 94 1154 142 2131
47 408 95 1172 143 2171
48 420 96 1190 144 2190
49 432 97 1209 145 2209
50 443 98 1229 146 2229
5l 455 99 1250 147 2250
52 467 100 1271 148 2271
53 478 101 1293 149 2293
54 490 102 1315 150 2315
55 503 103 1337 151 2334
56 516 104 1359 152 2354
57 530 105 1380 153 2375
318
Shipping (Load Line) Regulations
SCHEDULE 3
(Regulation 12)
CONDITION OF ASSIGNMENT
1.1 In this Schedule, except where the context otherwise requires—
“breadth (B)” means the maximum breadth of the ship measured
amidships to the moulded line of the frame in the case of a
ship having a metal shell, or to the outer surface of the hull
in the case of a ship having a shell of another material;
“enclosed superstructure” means a superstructure —
(a) which has enclosing bulkheads of efficient construction
in which all access openings are fitted with sills and
weathertight doors; and
(b) in which all other openings in sides or ends are fitted
with efficient weathertight means of closing;
but does not include a bridge or poop fulfilling these
requirements unless access to machinery and other
working spaces within the bridge or poop is provided
by alternative means which are available at times when
access openings in the bulkheads of the bridge or poop
are closed;
“exposed position” means a position which is —
(a) exposed to weather and sea; or
(b) within a structure so exposed other than enclosed
superstructure;
“forward perpendicular” means the perpendicular taken at
the forward end of the ship’s length, coinciding with
the foreside of the stem on the waterline on which such
length is measured; and “after perpendicular” means the
perpendicular taken at the after end of such length;
“freeing port area (A)” means the sum of the areas of the openings
of freeing ports on each side of the ship for each well;
“height” in relation to a superstructure means the least vertical
height measured at side from the top of the superstructure
deck beams to the top of the freeboard deck beams; and
the “standard height” of a superstructure means the height
ascertained in accordance with the provisions of paragraph
9 of Schedule 2;
321
Shipping (Load Line) Regulations
1.2.2.4 50% of the individual total capacity of all tanks and spaces
fitted to contain consumable liquids and stores is allowed for. It shall
be assumed that for each type of liquid, at least one transverse pair
or a single centreline tank has maximum free surface, and the tank or
combination of tanks to be taken into account shall be those where the
effect of free surfaces is the greatest; in each tank the centre of
gravity of the contents shall be taken at the centre of volume of the
tank. The remaining tanks shall be assumed either completely empty
or completely filled, and the distribution of consumable liquids
between these tanks shall be effected so as to obtain the greatest
possible height above the keel for the centre of gravity;
2.2.3 The maximum righting lever shall occur at an angle of heel not
less than 30o.
2.2.4 The initial transverse metacentric height shall not be less than
0.15 metres. In the case of a ship carrying a timber deck cargo which
complies with subparagraph 2.2.1 by taking into account the volume
of timber deck cargo, the initial transverse metacentric height shall not
be less than zero point zero five metres.
2.3 To determine whether the ship complies with the requirements of
subparagraph 2.2 the ship shall, unless otherwise permitted, be subject
to an inclining test which shall be carried out in the presence of a surveyor
appointed by the Minister or, for the ships listed under regulation 17 (5),
a Survey or of ships appointed by the Minister or a person or an
organization authorized by the Minister.
327
Shipping (Load Line) Regulations
TABLE 1
Portable beams
5.3.1 If portable beams for supporting hatchway covers are made of mild
steel, their strength must be such as to withstand the assumed load given
in Table 1, and the product of the maximum stress thus calculated and
the factor 5 does not exceed the minimum ultimate strength of the
material.
329
Shipping (Load Line) Regulations
Pontoon covers
5.4.1 If pontoon covers of mild steel are used in place of portable beams
and covers, their strength must be such as to withstand the assumed load
given in Table 1, and the product of the maximum stress thus calculated
and the factor 5 does not exceed the minimum ultimate strength of the
material.
5.4.2 Pontoon covers must be so designed as to limit the deflection
to not more than 0.0022 times the span under the assumed load in Table
1 appropriate to the pontoon cover.
5.4.3 Mild steel plating forming the tops of pontoon covers must not
be less in thickness than one per cent of the spacing of the stiffeners or
six millimetres, whichever is the greater.
5.4.4 In the case of pontoon covers not made of mild steel, the strength
and stiffness of the cover shall be equivalent to those of a cover of mild
steel.
Carriers or sockets
5.5 Carriers or sockets for portable beams shall be of substantial
construction and provide efficient means for the fitting and securing of
the beams. If rolling types of beams are used the arrangements shall
ensure that the beams remain properly in position when the hatchway is
closed.
Cleats
5.6 Cleats must be set to fit the taper of the wedges. Cleats must be at least
sixty-five millimetres wide and spaced not more than six hundred millimetres,
centre to centre. The cleats along each side or end of the hatchway shall not be
more than one hundred and fifty millimetres from the hatch corners.
Tarpaulins
5.8 At least two layers of tarpaulin must be provided for a hatchway.
The tarpaulin must be waterproof, in good condition, and have satisfactory
strength and quality.
Coamings
6.1.1 Except as otherwise provided in subparagraph 6.1.2, a hatchway
must have a coaming of substantial construction the height of which above the
deck shall be at least —
6.1.1.1 six hundred millimetres, where the hatchway is in Position 1;
6.1.1.2 four hundred and fifty millimetres, where the hatchway is in
Position 2.
6.1.2 A hatchway may have a coaming of less than the height applicable
under the provisions of subparagraph 6.1.1, or in exceptional circumstances a
coaming may be dispensed with altogether, if that —
6.1.2.1 the safety of the ship is not impaired in the worst sea
or weather conditions likely to be encountered by the ship in
service;
Weathertight covers
6.2.1 The strength of a cover of mild steel must be such as to withstand
the assumed load given in Table 1, and the product of the maximum stress
thus calculated and the factor 4.25 does not exceed the minimum ultimate
strength of the material. A cover of mild steel must be so designed as to limit
the deflection under such a load to not more than 0.0028 times the span.
6.2.2 A cover of mild steel made of materials other than mild steel must
have a strength and stiffness equivalent to that required for a cover of mild
steel.
6.2.3 A cover of mild steel must be fitted with efficient means by which
it can be secured and made weathertight.
6.2.4 Mild steel plating forming the top of a cover must be not less in
thickness than 1% of the spacing of the stiffeners or six millimetres whichever
is the greater.
Ventilators
9.1.1 Except as otherwise provided in subparagraph 9.1.2, a ventilator
in Position 1 or Position 2 leading to spaces below the freeboard deck or
below the deck of an enclosed superstructure must have a coaming of steel or
equivalent material, substantially constructed and efficiently connected to the
deck. The height of the coaming is at least —
9.1.1.1 nine hundred millimetres above the deck, if the ventilator is
in Position 1;
333
Shipping (Load Line) Regulations
9.1.1.2 seven hundred and sixty millimetres above the deck, if the
ventilator is in Position 2.
9.1.2 If the coaming for a ventilator under subparagraph 9.1.1 above is
situated in a position in which it will be especially exposed to weather and sea
the height of the coaming is increased by such an amount as is necessary to
provide adequate protection having regard to its position.
9.2 If the coaming of a ventilator referred to in the subparagraph
9.1 exceeds nine hundred millimetres in height above the deck it must be
efficiently supported by stays, brackets or other means.
9.3 A ventilator in Position 1 or Position 2 which passes through a
superstructure, other than an enclosed superstructure, must have a coaming
of steel or equivalent material at the freeboard deck substantially constructed
and efficiently connected to that deck and at least nine hundred millimetres in
height above that deck.
9.4 Subject to subparagraph 9.5, a ventilator opening in Position 1 or
Position 2 must be provided with an efficient appliance by which it can be
closed and secured weathertight. A closing appliance provided on board a ship
of not more than one hundred metres in length must be permanently attached
and, in the case of another ship, must be so attached or be conveniently stowed
near to the ventilator for which it is provided.
9.5.1 A ventilator in Position 1 the coaming of which exceeds 4.5
metres in height above the deck and a ventilator in Position 2 the coaming
of which exceeds two point three metres in height above the deck, may not
be fitted with a closing appliance unless the fitting of such an appliance is
considered necessary by the Minister or person or organization authorized by
the Minister in order to provide adequate protection.
9.5.2 A ventilator leading to a battery room must not be fitted with a
closing appliance.
Air pipes
10.1 The exposed parts of an air pipe leading to a ballast or other tank
and extending above the freeboard deck or a superstructure deck must be of
substantial construction.
10.2 The exposed opening of air pipe must be fitted with efficient means
of closing the opening weathertight, which must be permanently attached so
as to be ready for immediate use.
10.3 Subject to subparagraph 10.4, the height above the deck of the
exposed opening of an air pipe must be —
334
Shipping (Load Line) Regulations
10.3.1 at least seven hundred and sity millimetres, if that deck is the
freeboard deck;
10.3.2 at least four hundred and fifty millimetres, if that deck is a
superstructure deck or, if the superstructure is of less than standard
height, such height as is necessary to adequately compensate for the
lower height of the superstructure.
10.4 The heights given in subparagraph 10.3 may be reduced if —
10.4.1 the working of the ship would be unreasonably impaired if those
heights were adhered to; and
10.4.2 the closing arrangements will ensure that the lower height is
adequately compensated for.
Side scuttles
13.1 Every side scuttle to a space below the freeboard deck or to a space
within an enclosed superstructure must be fitted with a hinged inside deadlight
so that it can be effectively closed and secured watertight.
13.2 No side scuttle must be fitted in a position such that its sill will be
below a line drawn parallel to the freeboard deck at side and having its lowest
point —
13.2.1 tow point five per cent of the breadth of the ship above the Summer
load waterline, or Summer Timber load waterline, if assigned; or
13.2.2 five hundred millimetres above the Summer load
waterline, or Summer Timber load waterline, if assigned;
whichever is the greater distance.
13.3 A side scuttle, glass and deadlight, where fitted, must be of substantial
construction and be efficiently fitted.
made for rapidly freeing the decks of water in bulk and for draining them,
and in particular the requirements set out in subparagraphs 14.2 to 14.9 shall
be complied with.
14.2 Except as otherwise provided under subparagraphs 14.4 and 14.5,
the freeing port area (A) for each well shall —
14.2.1 if the well is on the freeboard deck or on a raised quarter deck,
be not less than the area ascertained in accordance with subparagraph 14.3;
and
14.2.2 if the well is on a superstructure deck, other than a raised
quarter-deck, be not less than one half of the area given by subparagraph
14.3.
14.3.1 Subject to subparagraph 14.3.3 below, if the length (l) of a
bulwark in the well is twenty metres or less —
(A)= 0.7+ 0.035 (1) (square metres); and
14.3.2 Subject to subparagraph 14.3.3 below, where (l) exceeds twenty
metres,
(A)= 0.07 (1) (square metres).
The length (l) need in no case be greater than 0.7(L).
14.3.3 If the bulwark is more than one point two metres in average
height the required area shall be increased by zero point zero zero four square
metres per metre of length of well for each zero point one metre difference
in height. If the bulwark is less than zero point nine metre in average height,
the required area may be decreased by zero point zero zero four square metre
per metre of length of well for each zero point one metre difference in height.
14.4.1 If the deck on which the well is situated has no sheer, the freeing
port area shall be the area ascertained under subparagraph 14.3 increased by
fifty per cent.
14.4.2 If the deck on which the well is situated has sheer less than
standard sheer, the freeing port area is the area ascertained under subparagraph
14.3 increased by a percentage to be obtained by linear interpolation.
14.4.3 If the deck on which the well is situated has sheer, two thirds of
the freeing port area must be situated in the half of the well which is nearest
to the lowest point of the sheer.
14.5 The lower edge of a freeing port must be as near to the deck as
practicable.
14.6 A freeing port more than two hundred and thirty millimetres in depth
must be protected by rails or bars so fixed that the distance between the lowest
338
Shipping (Load Line) Regulations
rail or bar and the lower edge of the freeing port does not exceed two hundred
and thirty millimetres.
14.7 A freeing port fitted with a shutter must have sufficient clearance
to prevent jamming of the shutter, and the shutter hinges shall have pins or
bearings of efficient non-corrodible material.
14.8 Efficient provision must be made for freeing water from a
superstructure other than an enclosed superstructure.
14.9 If a ship fitted with a trunk does not comply with the requirements
of paragraph 10.2.2.6 of Schedule 2, “Freeboards”, or if continuous or
substantially continuous hatchway side coamings are fitted between detached
superstructures the minimum area of the freeing port openings must be
calculated using the following table:
15.4 Guard rails or guard wires fitted under with subparagraph 15.2
consist of courses of rails or wires supported by stanchions efficiently secured
to the deck. The opening between the lowest course of the rails or wires and
the deck must not exceed two hundred and thirty millimetres in height and no
opening above that course of rails or wires shall exceed three hundred and
eighty millimetres in height. If the ship has rounded gunwales, the stanchions
must be secured at the perimeter of the flat of the deck.
15.5 Gangways, underdeck passages and another means of access used
by the crew to pass between their quarters, the machinery space and another
space in the ship in the course of their necessary work shall be so designed and
constructed, and be fitted, if necessary, with life lines, access ladders, guard
rails, guard wires, hand rails or other safety fittings, as to afford effective
protection for the crew.
15.6 Deck cargo carried on a ship must be so stowed that an opening which
is in way of the cargo and which gives access to and from the crew’s quarters,
the machinery space and all other parts used in the necessary work of the ship,
can be properly closed and secured against the admission of water. Effective
protection for the crew in the form of guard rails or life lines must be provided
above the deck cargo if there is no convenient passage on or below the deck
of the ship.
15.7 The requirements of this paragraph do not apply in the case of
unmanned barges.
Application
16. The requirements of paragraphs 17 to 20 apply to Type “A” ships.
Machinery casings
17.1 Subject to subparagraph 17.2. a casing enclosing a machinery space
opening in Position 1 or Position 2 must be protected by —
17.1.1 an enclosed poop or bridge of at least standard height; or
17.1.2 a deckhouse of equal height and equivalent strength and
weathertightness.
17.2 Subparagraph 17.1 does not apply and the casing need not be protected
if —
17.2.1 there is no opening in the casing which gives direct access from
the freeboard deck to the machinery space; or
340
Shipping (Load Line) Regulations
17.2.2 the only opening in the casing has a steel weathertight door and
leads to a space or passage way which is as strongly constructed as the casing
and is separated from the stairway to the machinery space by a second steel
weathertight door.
Hatchway covers
19. The covers of hatchways in exposed positions on the freeboard deck,
on a forecastle deck or on the top of an expansion trunk must be of steel, of
efficient construction, and watertight when secured.
Freeing arrangements
20.1 Exposed parts of the freeboard deck and superstructure decks must
be fitted at their perimeter for at least half their length with guard rails or guard
wires in lieu of bulwarks or with other equally effective freeing arrangements.
Such guard rails or guard wires must comply with the requirements set out in
relation to such rails or wires in paragraph 18.2.1.
20.2 The upper edge of the sheer strake must be as low as practicable.
20.3 If superstructures of the ship are connected by a trunk, the exposed
parts of the freeboard deck in way of the trunk must be fitted at their perimeter
throughout their length with guard rails or guard wires complying with the
requirements set out in paragraph 18.2.1.
20.4 If the ship is so constructed that notwithstanding the provision of
freeing ports and arrangements it will be particularly subjected under service
conditions to the building up of quantities of water on the freeboard deck
efficient breakwaters must be fitted in suitable positions on that deck.
Application
21. The requirements of paragraphs 22 to 25 apply to Type “B” ships
assigned a reduced freeboard under the paragraph 5.3 of Schedule 2.
and shall be fitted on each side and throughout its length with guard rails or
guard wires complying with the requirements as set out in paragraph 18.2.1.
If the length of the gangway exceeds seventy metres, shelters complying with
the requirements under paragraph 18.3.3.5 must be provided in way of the
gangway.
24.1 In adverse weather conditions, if the crew in the course of its duties
may be required to go to working areas forward of the detached bridge, or
forward of the poop in cases where there is no detached bridge, access must
be by —
24.1.1 the means described under paragraph 18.3;
24.1.2 the means described under paragraph 23.2; or
24.1.3 equivalent means of access.
24.2 If hatchway coamings are six hundred millimetres or more in
height, two walkways complying with the following requirements may be
provided in lieu of subparagraph 24.1 —
24.2.1 the walkways must be efficiently constructed and of satisfactory
strength;
24.2.2 the walkways shall each be at least one metre in width and be
fitted on the freeboard deck alongside the outboard structure of the
hatchway coamings, one to port and the other to starboard of the
hatchways; and
24.2.3 on the side outboard of the hatchways each walkway must be
fitted with guard rails or guard wire complying with the requirements set
out in paragraph 18.2.1.
Freeing arrangements
25. A ship must comply with the requirements of paragraph 20.4.
Superstructures
27.1 A ship must have a forecastle of not less than the standard height
of an enclosed superstructure and not less in length than 0.07(L).
27.2 If the ship is less than one hundred metres in length it must be
fitted after with —
27.2.1 a poop of not less than standard height; or
27.2.2 a raised quarter deck having either a deck house or a strong
steel hood, so that the total height is not less than the standard
height of an enclosed superstructure.
Stowage
Siting, distribution and stowage of timber deck cargo
30.1 Cargo must be distributed and stowed so —
345
Shipping (Load Line) Regulations
Access
30.4.1 If timber deck cargo occupies the whole or substantially the
whole of the uncovered space on the deck of a ship, means of access
must be provided for the crew between their quarters and the
346
Shipping (Load Line) Regulations
machinery spaces and other parts of the ship used in the working of
the ship, as follows.
30.4.2 The means of access must be provided in the form of a
walkway fitted over the timber deck cargo, and the walkway must
be —
30.4.2.1 as near as practicable on the centreline of the ship;
30.4.2.2 not less than six hundred millimetres in width; and
30.4.2.3 provided with a lifeline which, if practicable, has
a wire rope set taut with a stretching screw.
30.4.3 In addition guard rails or lifelines spaced not more than three
hundred and fifty millimetres apart vertically shall be provided on each
side of the deck cargo to a height of at least one metre above the cargo.
30.4.4 The stanchion supports to all guard rails and lifelines must be so
spaced as to prevent undue sagging.
Uprights
30.5 If the nature of the timber is such that uprights are necessary in order
to comply with subparagraphs 30.6 and 30.7, uprights must be fitted which
are of sufficient strength for the purpose and be secured in position by angles
or metal sockets of sufficient strength for the purpose or by equivalent means
and must be so spaced as to provide efficient support taking into account the
nature and length of the timber, However the space between two uprights fore
and aft must not exceed three metres.
by independent overall lashings spaced not more than three metres apart. Eye
plates for these lashings shall be efficiently attached to the sheer strake or to
the deck stringer plate at intervals of not more than three metres. The distance
from an end bulk head of a superstructure to the first eye plate must be not
more than two metres. Where there is no bulkhead, eye plates and lashings
must be provided at distances of zero point six metres and fifteen metres from
the ends of the timber deck cargo.
30.7.2 Lashings must be of not less than nineteen millimetres close link
chain or of flexible wire rope of equivalent strength, fitted with sliphooks and
turnbuckles so positioned as to be accessible at all times. Wire rope lashings
must have a length of long link chain sufficient to permit the length of lashings
to be regulated.
30.7.3 When timber is in lengths less than three point six metres, the
spacing of the lashings must be reduced or suitable provision made to suit the
length of timber.
348
Shipping (Load Line) Regulations
SCHEDULE 4
(Regulation 13)
In forecastle
bulkhead
In bridge
forward
bulkhead
In bridge after
bulkhead
In raised
quarter deck
bulkhead
In poop
bulkhead
In exposed
machinery
casings on
freeboard or
raised quarter
decks
In exposed
machinery
casings on
superstructure
decks
In machinery
casings within
superstructures
or deckhouses
on freeboard
deck
In deckhouses
in Position
1 enclosing
openings
leading below
freeboard deck
350
Shipping (Load Line) Regulations
In deckhouses
in Position
2 enclosing
openings
leading within
enclosed
superstructures
or below
freeboard deck
In exposed
pump room
casings
Spacing
Bf x tf
D x tw
b2 x t f
Bearing surface
Means of
securing
each beam
351
Shipping (Load Line) Regulations
Material
PORTABLE Thickness
COVERS
Direction fitted
Bearing surface
Spacing of cleats
No. of layers
Tarpaulins Material
Height of coaming
352
Shipping (Load Line) Regulations
Cover Material
How
attached
Number and spacing of
Toggles
Positions and Reference
No. on Sketch or Plan
Dimensions
Height of coaming
COVER Material
How
attached
Number and spacing of
Toggles
SIDE SCUTTLES
Indicate the vertical distance between the freeboard deck and the lower
sill of the side scuttle positioned at the greatest vertical distance below the
freeboard deck . . . . . . . . . . . . . . . . . . . . . . . . . . .
357
Shipping (Load Line) Regulations
FREEING PORTS
LENGTH HEIGHT NUMBER TOTAL REQUIRED
OF OF AND AREA AREA
BULWARK BULWARK SIZE OF EACH SIDE EACH SIDE
FREEING
PORTS
EACH SIDE
FREEBOARD
DECK AFTER
WELL
FORWARD
WELL
SUPER-
STRUCTURE
DECK
INITIAL SURVEY
..........................
(Surveyor’s Signature)
..........................
(Date)
I have completed the periodical survey and am satisfied that the fittings
and appliances are in accordance with the particulars shown in this record
and are in good condition and that approved stability information and, where
applicable, information relating to loading and ballasting of the ship is on
board.
Signature Port of Survey Date of Survey
........... .............. ................
........... .............. ................
........... .............. ................
359
Shipping (Load Line) Regulations
SCHEDULE 5
(Regulation 16(1))
NOTICE OF LOAD LINES TO BE POSTED UP BEFORE SAILING
1. In this Schedule “freeboard” means the distance measured vertically
downwards amidships from the upper edge of the deckline marked on the side
of the ship to the surface of the water.
(5) Allowance for fresh water for all freeboards other than Timber
freeboards..................millimetres
Notes
1. The particulars to be given above of freeboards and allowances for fresh
water to be taken from the load line certificate currently in force in respect
of the ship.
2. All freeboards given on the load line certificate must be stated.
3. The mean draught to be given above is the mean of the draughts which
would be shown on the scales of measurement on the stem and on the stern
post of the ship if it were so loaded that the upper edge of the load line on each
side of the ship appropriate to the particular freeboard were on the surface of
the water.
4. Where the draught is shown on the scales of measurement on the stem
and on the stern post of the ship in feet the mean draught must be given in
millimetres.
PARTICULARS OF LOADING
1 2 3 4 5 6 7 8 9
DATE PLACE ACTUAL DRAFT MEAN FREEBOARD SIGNATURE OF
MASTER AND AN
OFFICER
Notes
1. The actual mean freeboard (Column 6) is the mean of the freeboards on
each side of the ship at the time when the ship is loaded and ready to leave.
2. Where the actual mean freeboard is less than the appropriate minimum
saltwater freeboard as shown on the load line certificate there must be entered
in Column 7 the corrected freeboard arrived at after making any allowances
361
Shipping (Load Line) Regulations
for density of water, rubbish to be discharged overboard and fuel, water and
stores to be consumed on any stretch of river or inland water, being allowances
duly entered in the ship’s official log-book.
3. Where the actual mean freeboard is greater than the appropriate salt water
freeboard, Column 7 need not be filled in.
SCHEDULE 6
(Regulation 17(2))
the weight of water absorbed shall be taken as fifteen per cent of the weight
when loaded.)
6. A diagram or scale showing —
6.1 the load line mark and load lines with particulars of the corresponding
freeboards; and
6.2 the displacement, tonnes per centimetre immersion, and deadweight
corresponding to a range of mean draughts extending between the waterline
representing the deepest load line and the waterline of the ship in light
condition.
7.1 A diagram or tabular statement showing the hydrostatic particulars
of the ship, including the heights of the transverse metacentre and the
values of the moment to change trim one centimetre. These particulars shall
be provided for a range of mean draughts extending at least between the
waterline representing the deepest load line and the waterline of the ship in
light condition.
7.2 If a tabular statement is used to comply with subparagraph 7.1, the
intervals between such draughts shall be sufficiently close to permit accurate
interpolation.
7.3 In the case of ships having raked keels, the same datum for the
heights of centres of buoyancy and metacentres must be used as for the centres
of gravity referred to in paragraphs 3, 4 and 5.
8. The effect on stability of free surface in each tank in the ship in which
liquids may be carried, including an example to show how the metacentric
height is to be corrected.
9.1 A diagram or table showing cross curves of stability, covering the
range of draughts referred to in paragraph 7.1.
9.2 The information must indicate the height of the assumed axis from
which the righting levers are measured and the trim which has been assumed.
9.3 In the case of ships having raked keels and where a datum other
than the top of keel has been used, the position of the assumed axis must be
clearly defined.
9.4 Subject to subparagraph 9.5, only enclosed superstructures and
efficient trunks as defined in paragraph 10 of Schedule 2 must be taken into
account in deriving such curves.
9.5 The following structures may be taken into account in deriving such
curves if the Director is satisfied that their location, integrity and means of
closure will contribute to the ship’s stability —
363
Shipping (Load Line) Regulations
13. The ships referred to in regulation 17(3), (4)(a) and (5)(a) of the
Regulations are as follows:
13.1 an oil tanker over one hundred metres in length;
13.2 a bulk carrier, or an ore carrier, over one hundred and fifty metres
in length;
13.3 a single deck bulk carrier over one hundred metres in length but
not exceeding one hundred and fifty metres in length;
13.4 a single deck dry cargo ship over one hundred metres in length;
13.5 a purpose built container ship over one hundred and twenty-five
metres in length;
13.6 a column stabilised mobile offshore drilling unit; or
365
Shipping (Load Line) Regulations
SCHEDULE 7
FORMS
FORM 1
APPLICATION FOR INTERNATIONAL LOADLINE CERTIFICATE
(1966)
(Regulation 23(a)(i))
SAINT LUCIA
PARTICULARS OF SHIP
IMO / HIN / Caribbean
Number
Port of Registry
(if known)
Delete as appropriate
Type of Ship (dry cargo, oil
tanker, ro-ro, passenger, etc.)
Construction Material Overall Length
The upper edge of the deck line from which these freeboards are measured is …………..mm
above/below from deck at side
SURVEYORS DECLARATION
4. A copy of the attending Surveyor’s completed check list for the load line
is attached.
5. For an initial survey a copy of the Naval Architect’s freeboard calculations
and the completed and signed off Stability Book is attached.
6. The initial survey must make a complete inspection of the ship’s structure
and equipment and the relevant information.
7. For a renewal survey, proof of structure has been surveyed is attached,
such as photographs of void space showing internal structure remaining
unchanged due to modification, fracture or failure.
Signature:
Date:
Registrar of Ships
OFFICIAL USE ONLY
Division of Maritime Affairs
Address Entry in Register made on
Telephone:
Fax: _____/_____/______
Email: (d/m/y)
At__________________(time)
FORM 2
(Regulation 23(a)(ii)
SAINT LUCIA
APPLICATION FOR SAINT LUCIA LOCAL LOADLINE CERTIFICATE FOR
VESSELS UNDER TWENTY-FOUR METERS
PARTICULARS OF SHIP
IMO/HIN/ Caribbean Number Port of Registry
(if known)
(delete as appropriate)
Type of Ship (dry cargo,
oil tanker, ro-ro, passenger,
etc.)
Overall Length
Construction Material
NB:- (Freeboards and load lines which are not applicable need not be entered on the certificate.
Subdivision load lines may be entered on the certificate on a voluntary basis).
E-mail addresse(es)
SIGNATURE
Place
Date ___/___/___
(d/m/y) Signature of Witness
Signature:
Date:
____/___/___(d/m/y)
at___________(time).
Or
SAINT LUCIA
PARTICULARS OF SHIP
IMO / HIN / Caribbean
Number
Port of Registry
(if known)
Delete as appropriate
372
Shipping (Load Line) Regulations
Construction Material
SURVEYORS DECLARATION
Signature:
Date:
374
Shipping (Load Line) Regulations
At________________(time).
FORM 3
(Regulation 23 (b)(i))
SAINT LUCIA
APPLICATION FOR INTERNATIONAL LOADLINE EXEMPTION
CERTIFICATE FOR VESSELS UNDER 24 METERS AND ABOVE
PARTICULARS OF SHIP
IMO / HIN / Caribbean
Number
Port of Registry
(if known)
Delete as appropriate
Type of Ship (dry cargo, oil
tanker, ro-ro, passenger, etc.)
Overall Length
Construction Material
Year to Build Country to Build
PARTICULARS OF FREEBOARD
Freeboard from deck line Load line
Tropical ..………. Mm (T) ....................mm. Above (S)
375
Shipping (Load Line) Regulations
SURVEYORS DECLARATION
2. The survey showed that the freeboards have been assigned and the load
lines shown above have been marked as per photographs of the port and
starboard load line marks and draught marks showing the subject vessel’s
name.
3. The application for the issuance of a Saint Lucian load line is made direct
to The Division of Maritime Affairs on behalf of the registered owner.
4. A copy of the attending Surveyor’s completed check list for the load line
is attached.
5. For an initial survey a copy of the Naval Architect’s freeboard calculations
and the completed and signed off Stability Book is attached.
6. The initial survey must make a complete inspection of the ship’s structure
and equipment and the relevant information.
7. For a renewal survey, proof of structure has been surveyed is attached,
such as photographs of void space showing internal structure remaining
unchanged due to modification, fracture or failure.
At________________(time).
FORM 4
(Regulation 23(b)(ii))
SAINT LUCIA
APPLICATION FOR SAINT LUCIA LOCAL LOADLINE EXEMPTION CERTIFICATE
FOR VESSELS UNDER TWENTY-FOUR METERS
PARTICULARS OF SHIP
IMO / HIN / Caribbean
Number
Port of Registry
(if known)
Delete as appropriate
Type of Ship (dry cargo, oil
tanker, ro-ro, passenger, etc.)
Overall Length
Construction Material
Year to Build Country to Build
PARTICULARS OF FREEBOARD
Freeboard from deck line Load line
Tropical ..………. Mm (T) ....................mm. Above (S)
Allowance for fresh water for all freeboards
other than timber
....................mm
For timber freeboards ....................mm
The upper edge of the deck line from which these freeboards are measured is …………..mm
above/below from deck at side
NB:- (Freeboards and load lines which are not applicable need not entered on the certificate.
Subdivision load lines may be enterd on the certificate on a voluntary basis)
E-mail address(es)
SIGNATURE
Place Signature of Witness
Date ___/___/___
(d/m/y)
Signature of Owner(s) In Full Name of Witness
case of a body corporate, an
authorized officer of the body
corporate
Address Of Witness
SURVEYORS DECLARATION
Signature:
Date:
_____/_____/_____
(d/m/y)
At________________(time).
PARTICULARS OF SHIP
IMO / HIN / Caribbean
Number
Port of Registry
(if known)
Delete as appropriate
Type of Ship (dry cargo, oil
tanker, ro-ro, passenger, etc.)
Overall Length
Construction Material
Year to Build Country to Build
PARTICULARS OF FREEBOARD
Freeboard from deck line Load line
Tropical ..………. Mm (T) ....................mm. Above (S)
Allowance for fresh water for all freeboards ....................mm
other than timber
NB:- (Freeboards and load lines which are not applicable need not be entered on the certificate.
Subdivision load lines may be enterd on the certificate on a voluntary basis)
SURVEYORS DECLARATION
Name of Surveyor:
Signature:
Date:
FORM 5
(Regulation 24(1)(a))
(Official seal)
The upper edge of the deck line from which these freeboards are measured is
.... mm (inches) ...... deck at side.
This is to certify that this ship has been surveyed and that the freeboards have
been assigned and load lines shown above have been marked in accordance
with the International Convention on Load Lines, 1966.
Issued at ...................................................................................
or
................................................................................(Signature)
NOTES:
1. When a ship departs from a port situated on a river or inland waters, deeper
loading shall be permitted corresponding to the weight of fuel and all other
materials required for consumption between the point of departure and the
sea.
2. When a ship is in fresh water of unit density the appropriate load line
may be submerged by the amount of the fresh water allowance shown above.
Where the density is other than unity, an allowance shall be made proportional
to the difference between 1.025 and the actual density.
Reverse of certificate
The provisions of the Convention being fully complied with by this ship, the
validity of this certificates, in accordance with Article 19(2) of the International
Convention on Load Lines, 1966, extended until .............................
FORM 6
(Regulation 24(1)(b))
PARTICULARS OF SHIP
Regulations ...............................................................................
Note: Freeboards and Load Lines which are not applicable need not be entered
on the certificate.
386
Shipping (Load Line) Regulations
The upper edge of the deck line from which these freeboards are measured is
THIS IS TO CERTIFY that this ship has been surveyed and the freeboards
and load lines shown above have been assigned in accordance with the
Shipping (Load Line) Regulations.
Issued at on
Signed
Name
Name of Ship
CONDITIONS:
This is to certify
Place Date
................................................. Name
Signature of an authorized official
Place Date
................................................. Name
Signature of an authorized official
387
Shipping (Load Line) Regulations
Place Date
................................................. Name
Signature of an authorized official
Place Date
................................................. Name
Signature of an authorized official
Notes
1. When a ship departs from a port situated on a river or inland water, deeper
loading shall be permitted corresponding to the weight of fuel and all other
materials required for consumption between the point of departure and the sea.
2. When a ship is in fresh water of unit density, the appropriate load line
may be submerged by the amount of the freshwater allowance showed
above. Where the density is other than unity, an allowance shall be made
proportional to the difference between 1.025 and the actual density.
FORM 7
(Regulation 24(2)(a))
..............................................................................................
..............................................................................................
388
Shipping (Load Line) Regulations
This is to certify that the above-mentioned ship is exempted from the provisions
of the International Convention on Load Lines, 1966, under the authority
conferred by Article 6(2)/Article 6(4) * of the Convention.
..............................................................................................
..............................................................................................
The voyage for which exemption is granted under Article 6(4) is:
From:.......................................................................................
To : .........................................................................................
..............................................................................................
Issued at ...................................................................................
or
...............................
(Signature)
Reverse of Certificate
This is to certify that this ship continues to comply with the conditions under
which this exemption was granted.
This ship continues to comply with the conditions under which this exemption
was granted and the validity of this certificate is, in accordance with Article 19
(4) (a) of the Convention, extended until ............................................
FORM 8
(Regulation 24(2)(b)
Issued under the Shipping (Load Line) Regulations under the authority of the
Government by the Division of Maritime Affairs.
PARTICULARS OF SHIP
Name of Ship___________________________________________________
Port of Registry_________________________________________________
....................................... Name______________________
An authorized official of the
Division of Maritime Affairs
Name of Ship
391
Shipping (Load Line) Regulations
CONDITIONS (Continued):
Place________________________Date_______________________________
Signed................................ Name_____________________________
An authorized official of the
Division of Maritime Affairs
Place________________________ Date__________________________
Signed.................................. Name_________________________
An authorized official of the
Division of Maritime Affairs
Place________________________Date______________________________
Signed.............................. Name______________________________
An authorized official of the
Division of Maritime Affairs
Place________________________Date______________________________
Signed................................. Name_____________________________
An authorized official of the
Division of Maritime Affairs.
STEPHENSON KING,
Minister responsible for shipping.
SAINT LUCIA
PRINTED BY THE NATIONAL PRINTING CORPORATION
CASTRIES