PROJECT TITLE:

EXPRESSWAY WEAVING SEGMENT TYPE A SCENARIO DEV AM REF: HCM 2000

1) INPUTS
𝐿_ 350 𝑚_

𝑆_𝐹𝐹 80 Km/h FREE FLOW SPEED 𝑉_𝑜1


PJ1 849 J5
𝑁_ 4 lane WEAVING NUMBER OF LANE
𝐿_ 350 Meter WEAVING SEGMENT LENGTH 𝑉_𝑤2 251

𝑉_𝑤1 646

TO KL RAMP 𝑉_𝑜2 FROM KL RAMP


173

2) TRAFFIC VOLUME (PCU/H)

𝑃𝐶𝑈/ℎ DESCRIPTION
𝑉_𝑜1 849 LARGER OF NON-WEAVING FLOW RATE
𝑉_𝑜2 173 SMALLER OF NON-WEAVING FLOW RATE
𝑉_𝑤1 646 LARGER OF WEAVING FLOW RATE
𝑉_𝑤2 251 SMALLER OF WEAVING FLOW RATE
𝑉_𝑤 897 TOTAL WEAVING FLOW RATE
𝑉_𝑛𝑤 1022 TOTAL NON WEAVING FLOW RATE
𝑉 1919 TOTAL FLOW RATE IN WEAVING SEGMENT
〖𝑉𝑅〗 _ 0.467 VOLUME RATIO
𝑅_ 0.280 WEAVING RATIO

3) WEAVING AND NONWEAVING SPEEDS

UNCONSTRAINED CONSTRAINED
w nw w nw
a 0.15 0.0035 0.35 0.0020
b 2.20 4.00 2.20 4.00
c 0.97 1.30 0.97 1.30
d 0.80 0.75 0.80 0.75
WEAVING INTENSITY FACTOR
𝑊_𝑖=(𝑎(1+𝑉𝑅)^𝑏 (𝑉/𝑁)^𝑐)/(3.28𝐿)^𝑑
0.496 0.252 1.156 0.144

WEAVING / NON-WEAVING SPEED (KM/H)

𝑆_𝑖=24+(𝑆_𝐹𝐹−16)/(1+𝑊_𝑖 )
66.8 75.1 53.7 80.0

TYPE OF OPERATION
= 1.96 𝑁_𝑤 (𝑀𝑎𝑥) 1.4
𝑁_𝑊=(1.21(𝑁)𝑉𝑅^0.571 𝐿^0.234)/𝑆_𝑊
= Constrained Operation

4) WEAVING SEGMENT SPEED, DENSITY, LEVEL OF SERVICE

LEVEL OF SERVICE B
WEAVING SEGMENT SPEED (KM/H)
𝑆_ =𝑉/((𝑉_𝑤/𝑆_𝑤 )+(𝑉_𝑛𝑤/𝑆_𝑛𝑤 ) )
65.1

WEAVING SEGMENT DENSITY (PC/KM/ln)


𝐷_ =((𝑉/𝑁))/𝑆
7.4 B
PROJECT TITLE:

EXPRESSWAY WEAVING SEGMENT TYPE A SCENARIO DEV AM REF: HCM 2000

1) INPUTS
𝐿_ 350 𝑚_

𝑆_𝐹𝐹 80 Km/h FREE FLOW SPEED 𝑉_𝑜1


KUNDANG 1405 KUANG
𝑁_ 4 lane WEAVING NUMBER OF LANE
𝐿_ 350 Meter WEAVING SEGMENT LENGTH 𝑉_𝑤2 639

𝑉_𝑤1 32

TO KL RAMP 𝑉_𝑜2 FROM KL RAMP


382

2) TRAFFIC VOLUME (PCU/H)

𝑃𝐶𝑈/ℎ DESCRIPTION
𝑉_𝑜1 1405 LARGER OF NON-WEAVING FLOW RATE
𝑉_𝑜2 382 SMALLER OF NON-WEAVING FLOW RATE
𝑉_𝑤1 32 LARGER OF WEAVING FLOW RATE
𝑉_𝑤2 639 SMALLER OF WEAVING FLOW RATE
𝑉_𝑤 671 TOTAL WEAVING FLOW RATE
𝑉_𝑛𝑤 1787 TOTAL NON WEAVING FLOW RATE
𝑉 2458 TOTAL FLOW RATE IN WEAVING SEGMENT
〖𝑉𝑅〗 _ 0.273 VOLUME RATIO
𝑅_ 0.952 WEAVING RATIO

3) WEAVING AND NONWEAVING SPEEDS

UNCONSTRAINED CONSTRAINED
w nw w nw
a 0.15 0.0035 0.35 0.0020
b 2.20 4.00 2.20 4.00
c 0.97 1.30 0.97 1.30
d 0.80 0.75 0.80 0.75
WEAVING INTENSITY FACTOR
𝑊_𝑖=(𝑎(1+𝑉𝑅)^𝑏 (𝑉/𝑁)^𝑐)/(3.28𝐿)^𝑑
0.461 0.197 1.075 0.112

WEAVING / NON-WEAVING SPEED (KM/H)

𝑆_𝑖=24+(𝑆_𝐹𝐹−16)/(1+𝑊_𝑖 )
67.8 77.5 54.8 81.5

TYPE OF OPERATION
= 1.43 𝑁_𝑤 (𝑀𝑎𝑥) 1.4
𝑁_𝑊=(1.21(𝑁)𝑉𝑅^0.571 𝐿^0.234)/𝑆_𝑊
= Constrained Operation

4) WEAVING SEGMENT SPEED, DENSITY, LEVEL OF SERVICE

LEVEL OF SERVICE B
WEAVING SEGMENT SPEED (KM/H)
𝑆_ =𝑉/((𝑉_𝑤/𝑆_𝑤 )+(𝑉_𝑛𝑤/𝑆_𝑛𝑤 ) )
72.0

WEAVING SEGMENT DENSITY (PC/KM/ln)


𝐷_ =((𝑉/𝑁))/𝑆
8.5 B
PROJECT TITLE:

EXPRESSWAY WEAVING SEGMENT TYPE A SCENARIO DEV AM REF: HCM 2000

1) INPUTS
𝐿_ 300 𝑚_

𝑆_𝐹𝐹 80 Km/h FREE FLOW SPEED 𝑉_𝑜1


PJ1 1142 J5
𝑁_ 4 lane WEAVING NUMBER OF LANE
𝐿_ 300 Meter WEAVING SEGMENT LENGTH 𝑉_𝑤2 387

𝑉_𝑤1 191

TO KL RAMP 𝑉_𝑜2 FROM KL RAMP


124

2) TRAFFIC VOLUME (PCU/H)

𝑃𝐶𝑈/ℎ DESCRIPTION
𝑉_𝑜1 1142 LARGER OF NON-WEAVING FLOW RATE
𝑉_𝑜2 124 SMALLER OF NON-WEAVING FLOW RATE
𝑉_𝑤1 191 LARGER OF WEAVING FLOW RATE
𝑉_𝑤2 387 SMALLER OF WEAVING FLOW RATE
𝑉_𝑤 578 TOTAL WEAVING FLOW RATE
𝑉_𝑛𝑤 1266 TOTAL NON WEAVING FLOW RATE
𝑉 1844 TOTAL FLOW RATE IN WEAVING SEGMENT
〖𝑉𝑅〗 _ 0.313 VOLUME RATIO
𝑅_ 0.670 WEAVING RATIO

3) WEAVING AND NONWEAVING SPEEDS

UNCONSTRAINED CONSTRAINED
w nw w nw
a 0.15 0.0035 0.35 0.0020
b 2.20 4.00 2.20 4.00
c 0.97 1.30 0.97 1.30
d 0.80 0.75 0.80 0.75
WEAVING INTENSITY FACTOR
𝑊_𝑖=(𝑎(1+𝑉𝑅)^𝑏 (𝑉/𝑁)^𝑐)/(3.28𝐿)^𝑑
0.423 0.172 0.986 0.098

WEAVING / NON-WEAVING SPEED (KM/H)

𝑆_𝑖=24+(𝑆_𝐹𝐹−16)/(1+𝑊_𝑖 )
69.0 78.6 56.2 82.3

TYPE OF OPERATION
= 1.48 𝑁_𝑤 (𝑀𝑎𝑥) 1.4
𝑁_𝑊=(1.21(𝑁)𝑉𝑅^0.571 𝐿^0.234)/𝑆_𝑊
= Constrained Operation

4) WEAVING SEGMENT SPEED, DENSITY, LEVEL OF SERVICE

LEVEL OF SERVICE B
WEAVING SEGMENT SPEED (KM/H)
𝑆_ =𝑉/((𝑉_𝑤/𝑆_𝑤 )+(𝑉_𝑛𝑤/𝑆_𝑛𝑤 ) )
71.8

WEAVING SEGMENT DENSITY (PC/KM/ln)


𝐷_ =((𝑉/𝑁))/𝑆
6.4 B
PROJECT TITLE:

EXPRESSWAY WEAVING SEGMENT TYPE A SCENARIO DEV AM REF: HCM 2000

1) INPUTS
𝐿_ 300 𝑚_

𝑆_𝐹𝐹 80 Km/h FREE FLOW SPEED 𝑉_𝑜1


KUNDANG 2178 KUANG
𝑁_ 4 lane WEAVING NUMBER OF LANE
𝐿_ 300 Meter WEAVING SEGMENT LENGTH 𝑉_𝑤2 890

𝑉_𝑤1 441

TO KL RAMP 𝑉_𝑜2 FROM KL RAMP


234

2) TRAFFIC VOLUME (PCU/H)

𝑃𝐶𝑈/ℎ DESCRIPTION
𝑉_𝑜1 2178 LARGER OF NON-WEAVING FLOW RATE
𝑉_𝑜2 234 SMALLER OF NON-WEAVING FLOW RATE
𝑉_𝑤1 441 LARGER OF WEAVING FLOW RATE
𝑉_𝑤2 890 SMALLER OF WEAVING FLOW RATE
𝑉_𝑤 1331 TOTAL WEAVING FLOW RATE
𝑉_𝑛𝑤 2412 TOTAL NON WEAVING FLOW RATE
𝑉 3743 TOTAL FLOW RATE IN WEAVING SEGMENT
〖𝑉𝑅〗 _ 0.356 VOLUME RATIO
𝑅_ 0.669 WEAVING RATIO

3) WEAVING AND NONWEAVING SPEEDS

UNCONSTRAINED CONSTRAINED
w nw w nw
a 0.15 0.0035 0.35 0.0020
b 2.20 4.00 2.20 4.00
c 0.97 1.30 0.97 1.30
d 0.80 0.75 0.80 0.75
WEAVING INTENSITY FACTOR
𝑊_𝑖=(𝑎(1+𝑉𝑅)^𝑏 (𝑉/𝑁)^𝑐)/(3.28𝐿)^𝑑
0.900 0.490 2.101 0.280

WEAVING / NON-WEAVING SPEED (KM/H)

𝑆_𝑖=24+(𝑆_𝐹𝐹−16)/(1+𝑊_𝑖 )
57.7 66.9 44.6 74.0

TYPE OF OPERATION
= 1.72 𝑁_𝑤 (𝑀𝑎𝑥) 1.4
𝑁_𝑊=(1.21(𝑁)𝑉𝑅^0.571 𝐿^0.234)/𝑆_𝑊
= Constrained Operation

4) WEAVING SEGMENT SPEED, DENSITY, LEVEL OF SERVICE

LEVEL OF SERVICE C
WEAVING SEGMENT SPEED (KM/H)
𝑆_ =𝑉/((𝑉_𝑤/𝑆_𝑤 )+(𝑉_𝑛𝑤/𝑆_𝑛𝑤 ) )
60.0

WEAVING SEGMENT DENSITY (PC/KM/ln)


𝐷_ =((𝑉/𝑁))/𝑆
15.6 C