Equipment support structure mismatch

Equipment support structure mismatch


25 mm Gap between grating and floor beams
Stairs are too high from ground
Gap between building and stairs ? Reduce if not required
Supporting beams not required at 3950 level
Extra handrail
Equipment support structure mismatch
Rotate complete model by 90 degree as below image
Bolt holes are clashing with I section beams, ISMC beam
should be used to avoid clash
Pump bottom frame structure ISMC 80 x 45 mm