NAME OF PROJECT CONSTRUCTION OF G+5 STORIED NEW HR BUILDING, DULIAJAN, DIST.

DIBRUGARH,ASSAM
CLIENT OIL INDIA LIMITED
CONSULTANT RITES LIMITED
CONTRACTOR M/S BADRI RAI & COMPANY

Date of Checking :

BAR BENDING SCHEDULE OF PILE CAP


Bar Length (mm)
No. of Diameter of Cutting Total
Sl. No. Description Shape Spacing No. Of Bar Total
Structures Bar A B C D E Length (M) Length (M)

PILE CAP

A C
1 Bottom Main Bar 1 25 228 450 34000 450 34900 34.9 7957.20
B

2 Lap 3 25 228 1175 1175 1.175 803.70

3 Bottom Dist. Bar 1 A C 25 228 450 34000 450 34900 34.9 7957.20
B

4 Lap 3 25 228 1175 1175 1.175 803.70

A C
5 Top Main Bar 1 25 195 450 34000 450 34900 34.9 6815.47
B

6 Lap 3 25 195 1175 1175 1.175 687.38

A C
7 Top Dist. Bar 1 25 125 450 34000 450 34900 34.9 4362.50
B

8 Lap 3 25 125 1175 1175 1.175 440.63

A C
9 Top Dist. Bar 1 20 113 450 34000 450 34900 34.9 3943.70
B

10 Lap 3 20 113 940 940 0.94 318.66

B C D
11 Chair Bar 1 20 900 250 575 850 575 250 2500 2.5 2250.00
A E

A
12 Binder 1 10 3 136600 136600 136.6 409.80

13 Lap 1 10 36 470 470 0.47 16.92

Comments / Remarks :

For M/s B R C For RITES Limited For Oil India Limited


NAME OF PROJECT CONSTRUCTION OF G+5 STORIED NEW HR BUILDING, DULIAJAN, DIST. DIBRUGARH,ASSAM

CLIENT OIL INDIA LIMITED


CONSULTANT RITES LIMITED
CONTRACTOR M/S BADRI RAI & COMPANY

Date of Checking :

BAR BENDING SCHEDULE OF COLUMN-C1


No. of Bar Length (mm) Cutting Total
Sl. No. Description Shape Diameter No. Total
Structures A B C D E Length (M) Length (M)

C1 ( Pedestal Top to PLTop Level) 600X600

1 Vertical bar 1 B 20 4 1375 1375 1.375 5.50

2 Vertical bar 1 B 16 16 1375 1375 1.375 22.00

A D
3 Master Stirrup 1 8 9 520 520 520 520 192 2272 2.272 20.45
C

A
Inner Rectangular D B
4 Stirrup 1 8 36 520 120 520 120 160 1440 1.44 51.84
C
(1,2,3,4)

Comments / Remarks :
For M/s B R C For RITES Limited For Oil India Limited
NAME OF PROJECT CONSTRUCTION OF G+5 STORIED NEW HR BUILDING, DULIAJAN, DIST. DIBRUGARH,ASSAM

CLIENT OIL INDIA LIMITED

CONSULTANT RITES LIMITED

CONTRACTOR M/S BADRI RAI & COMPANY

Date of Checking :

BAR BENDING SCHEDULE OF COLUMN-C2


No. of Bar Length (mm) Cutting Total
Sl. No. Description Shape Diameter No. Total
Structures A B C D E Length (M) Length (M)
C2 ( Pedestal Top to PLTop Level) 600X600

1 Vertical bar 5 B 20 12 1375 1375 1.375 82.50

2 Vertical bar 5 B 16 8 1375 1375 1.375 55.00

A
3 Master Stirrup 5 D
8 9 520 520 520 520 192 2272 2.272 102.24
C

Inner A

Rectangular D B
4 5 8 36 520 120 520 120 160 1440 1.44 259.20
Stirrup C
(1,2,3,4)

Comments / Remarks :

For M/s B R C For RITES Limited For Oil India Limited


NAME OF PROJECT CONSTRUCTION OF G+5 STORIED NEW HR BUILDING, DULIAJAN, DIST. DIBRUGARH,ASSAM
CLIENT OIL INDIA LIMITED
CONSULTANT RITES LIMITED
CONTRACTOR M/S BADRI RAI & COMPANY

Date of Checking :

BAR BENDING SCHEDULE OF COLUMN-C3


No. of Bar Length (mm) Cutting Total
Sl. No. Description Shape Diameter No. Total
Structures A B C D E Length (M) Length (M)

C3 ( Pedestal Top to PLTop Level) 600X600

1 Vertical bar 2 B 20 20 1375 1375 1.375 55.00

A D
2 Master Stirrup 2 8 9 520 520 520 520 192 2272 2.272 40.90
C

Inner A

Rectangular D B
3 2 8 36 520 120 520 120 160 1440 1.44 103.68
Stirrup C

(1,2,3,4)

Comments / Remarks :

For M/s B R C For RITES Limited For Oil India Limited


NAME OF PROJECT CONSTRUCTION OF G+5 STORIED NEW HR BUILDING, DULIAJAN, DIST. DIBRUGARH,ASSAM

CLIENT OIL INDIA LIMITED

CONSULTANT RITES LIMITED

CONTRACTOR M/S BADRI RAI & COMPANY

Date of Checking :

BAR BENDING SCHEDULE OF COLUMN-C4


No. of Bar Length (mm) Cutting Total
Sl. No. Description Shape Diameter No. Total
Structures A B C D E Length (M) Length (M)
C4 ( Pedestal Top to PLTop Level) 600X600

1 Vertical bar 2 B
25 12 1375 1375 1.375 33.00

2 Vertical bar 2 B
20 8 1375 1375 1.375 22.00

3 Master Stirrup 2 A D 8 9 520 520 520 520 192 2272 2.272 40.90
C

A
Inner Rectangular
D B
4 Stirrup 2 8 36 520 120 520 120 160 1440 1.44 103.68
(1,2,3,4) C

Comments / Remarks :

For M/s B R C For RITES Limited For Oil India Limited


NAME OF PROJECT CONSTRUCTION OF G+5 STORIED NEW HR BUILDING, DULIAJAN, DIST. DIBRUGARH,ASSAM
CLIENT OIL INDIA LIMITED
CONSULTANT RITES LIMITED
CONTRACTOR M/S BADRI RAI & COMPANY

Date of Checking :

BAR BENDING SCHEDULE OF COLUMN-C5


No. of Bar Length (mm) Cutting Total
Sl. No. Description Shape Diameter No. Total
Structures A B C D E Length (M) Length (M)

C5 ( Pedestal Top to PLTop Level) 600X600

1 Vertical bar 3 B
25 20 1375 1375 1.375 82.50

2 Master Stirrup 3 A D 8 9 520 520 520 520 192 2272 2.272 61.34
C

A
Inner Rectangular
D B
3 Stirrup 3 8 36 520 120 520 120 160 1440 1.44 155.52
(1,2,3,4) C

Comments / Remarks :

For M/s B R C For RITES Limited For Oil India Limited


NAME OF PROJECT CONSTRUCTION OF G+5 STORIED NEW HR BUILDING, DULIAJAN, DIST. DIBRUGARH,ASSAM

CLIENT OIL INDIA LIMITED

CONSULTANT RITES LIMITED

CONTRACTOR M/S BADRI RAI & COMPANY

Date of Checking :

BAR BENDING SCHEDULE OF COLUMN-C6


No. of Bar Length (mm) Cutting Total
Sl. No. Description Shape Diameter No. Total
Structures A B C D E Length (M) Length (M)

C6 ( Pedestal Top to PLTop Level) 600X600

1 Vertical bar 16 B 25 4 1375 1375 1.375 88.00


C

2 Vertical bar 16 B 20 16 1375 1375 1.375 352.00


C

A D
3 Master Stirrup 16 8 9 520 520 520 520 192 2272 2.272 327.17
C

A
Inner Rectangular
D B
4 Stirrup 16 8 36 520 120 520 120 160 1440 1.44 829.44
(1,2,3,4) C

Comments / Remarks :

For M/s B R C For RITES Limited For Oil India Limited


NAME OF PROJECT CONSTRUCTION OF G+5 STORIED NEW HR BUILDING, DULIAJAN, DIST. DIBRUGARH,ASSAM

CLIENT OIL INDIA LIMITED

CONSULTANT RITES LIMITED

CONTRACTOR M/S BADRI RAI & COMPANY

Date of Checking :

BAR BENDING SCHEDULE OF COLUMN-C7


No. of Bar Length (mm) Cutting Total
Sl. No. Description Shape Diameter No. Total
Structures A B C D E Length (M) Length (M)

C7 ( Pedestal Top to PLTop Level) 600X600

1 Vertical bar 7 B 25 20 1375 1375 1.375 192.50


C

A D
2 Master Stirrup 7 8 9 520 520 520 520 192 2272 2.272 143.14
C

A
Inner Rectangular
D B
3 Stirrup 7 8 36 520 120 520 120 160 1440 1.44 362.88
(1,2,3,4) C

Comments / Remarks :

For M/s B R C For RITES Limited For Oil India Limited


NAME OF PROJECT CONSTRUCTION OF G+5 STORIED NEW HR BUILDING, DULIAJAN, DIST. DIBRUGARH,ASSAM

CLIENT OIL INDIA LIMITED

CONSULTANT RITES LIMITED

CONTRACTOR M/S BADRI RAI & COMPANY

Date of Checking :

BAR BENDING SCHEDULE OF COLUMN-C8


Bar Length (mm)
No. of Cutting Total
Sl. No. Description Shape Diameter No. Total
Structures A B C D E Length (M) Length (M)

C8 ( Pedestal Top to PLTop Level) 600X600

1 Vertical bar 3 B 25 24 1375 1375 1.375 99.00


C

A D
2 Master Stirrup 3 8 9 520 520 520 520 192 2272 2.272 61.34
C

A
Inner Rectangular
D B
3 Stirrup 3 8 36 520 120 520 120 160 1440 1.44 155.52
(1,2,3,4) C

Inner single leg


4 3 A 8 9 520 192 712 0.712 19.22
stirrup

Comments / Remarks :

For M/s B R C For RITES Limited For Oil India Limited


NAME OF PROJECT CONSTRUCTION OF G+5 STORIED NEW HR BUILDING, DULIAJAN, DIST. DIBRUGARH,ASSAM

CLIENT OIL INDIA LIMITED

CONSULTANT RITES LIMITED

CONTRACTOR M/S BADRI RAI & COMPANY

Date of Checking :

BAR BENDING SCHEDULE OF SHEAR WALL-SW1


No. of Bar Length (mm) Cutting Total
Sl. No. Description Shape Diameter No. Total
Structures A B C D E Length (M) Length (M)

SWI ( Pedestal Top to PLTop Level) AS/SCHEDULE

1 Vertical bar 1 B 20 48 1375 1375 1.375 66.00


C

2 Vertical bar 1 B
16 96 1375 1375 1.375 132.00
C

A
3 Master Stirrup 1 1 B
8 9 2310 250 2310 250 192 5312 5.312 47.81
D

4 Master Stirrup 2 2 D B 8 9 2630 180 2630 180 192 5812 5.812 104.62
C

5 Master Stirrup 3 2 D B 8 9 400 180 400 180 192 1352 1.352 24.34
C

A
Inner Rectangular Stirrup1
6 1 D B 8 81 108 250 108 250 192 908 0.908 73.55
(1 to 9)
C

Inner Rectangular Stirrup2 D B


7 1 8 90 130 180 130 180 192 812 0.812 73.08
(1 to 10) C

8 Single Leg Stirrups 3 A


8 9 180 192 372 0.372 10.04

Comments / Remarks :

For M/s B R C For RITES Limited For Oil India Limited


NAME OF PROJECT CONSTRUCTION OF G+5 STORIED NEW HR BUILDING, DULIAJAN, DIST. DIBRUGARH,ASSAM
CLIENT OIL INDIA LIMITED
CONSULTANT RITES LIMITED
CONTRACTOR M/S BADRI RAI & COMPANY

Date of Checking :

BAR BENDING SCHEDULE OF SHEAR WALL-SW2


No. of Bar Length (mm) Cutting Total
Sl. No. Description Shape Diameter No. Total
Structures A B C D E Length (M) Length (M)
SW2 ( Pedestal Top to PLTop Level) AS/SCHEDULE

1 Vertical bar 1 B 20 80 1375 1375 1.375 110.00

2 Vertical bar 1 B 16 170 1375 1375 1.375 233.75

3 Vertical bar 2 B 12 84 1375 1375 1.375 231.00

Binder 2 10 9 6200 6200 6.2 111.60


A

4 Master Stirrup 1 1 D B
8 9 5740 250 5740 250 192 12172 12.172 109.55
C

5 Master Stirrup 2 3 D
B
8 9 2430 180 2430 180 192 5412 5.412 146.12
C

6 Master Stirrup 3 2 D B 8 9 400 180 400 180 192 1352 1.352 24.34
C

7 Master Stirrup 4 1
D B
8 9 620 180 620 180 192 1792 1.792 16.13
C

A
Inner Rectangular
B
8 Stirrup1 1 D
8 216 125 250 125 250 192 942 0.942 203.47
(1 to 24) C

A
Inner Rectangular
9 Stirrup2 3 D B
8 81 123 180 123 180 192 798 0.798 193.91
(1 to 9) C

10 Single Leg Stirrups 7 A


8 9 180 192 372 0.372 23.44

Comments / Remarks :

For M/s B R C For RITES Limited For Oil India Limited


NAME OF PROJECT CONSTRUCTION OF G+5 STORIED NEW HR BUILDING, DULIAJAN, DIST. DIBRUGARH,ASSAM

CLIENT OIL INDIA LIMITED

CONSULTANT RITES LIMITED

CONTRACTOR M/S BADRI RAI & COMPANY

Date of Checking :

BAR BENDING SCHEDULE OF COLUMN-Pedestal


No. of Bar Length (mm) Cutting Total
Sl. No. Description Shape Diameter No. Total
Structures A B C D E Length (M) Length (M)

Pedestal

Vertical bar B D
1 34 12 11 300 875 1520 875 300 3870 3.87 1447.38
X-Direction A
E

Vertical bar B D
2 34 12 11 300 875 1520 875 300 3870 3.87 1447.38
X-Direction A
E

3 Binder 34 A 10 3 6680 6680 6.68 681.36

Comments / Remarks :

For M/s B R C For RITES Limited For Oil India Limited