Professional Documents
Culture Documents
Lenz's law
It states that the current induced in a circuit due to a change in a magnetic field is
directed to oppose the change in flux and to exert a mechanical force which
opposes the motion.
3. Synchronism
On confirmation that the frequency difference is small (1 Hz or less),
position “SYNCHROSCOPE” switch to D/G 2 and observe the movement
of the synchroscope pointer as well as the brilliance change of the synchro
lamps.
Synchroscope pointer is rotating in “FAST” direction (clockwise). The
generator frequency (D/G 2 ‘s) is higher than the bus frequency (D/G 1 ‘s).
The sequence of the synchro lamp brilliance change is also in clockwise
direction.
Synchroscope pointer is rotating in “SLOW” direction (anticlockwise). The
incoming generator frequency is lower than the bus frequency. The sequence
of the synchro lamp brilliance change is also in anticlockwise direction.
7. Load Division
On closure of D/G 2 ACB, operate “GOVERNOR MOTOR” switch for D/G
2 to RAISE so that D/G 2 takes on KW load and let each generator share the
load in proportion to their capacity ratio.
Also operate “GOVERNOR MOTOR” switch for D/G 1 if necessary to
maintain the bus frequency at 60 Hz. Then position “SYNCHROSCOPE”
switch to OFF.
8. Load Shift
To remove one of the generators running in parallel, first transfer load on
that generator to other generator(s). When the KW output of this generator is
reduced to almost zero, remove the generator from the bus by opening its
ACB.
For example, to remove D/G 1 running in parallel with D/G 2as mentioned
above, operate “GOVERNOR MOTOR” switch for D/G 1 to lower; load
on D/G 1 transfers to D/G 2.
Also operate GOVERNOR MOTOR” switch for D/G 2 if necessary to
maintain the bus frequency at 60 Hz. When D/G 1 output is reduced to about
5% of its rated output, operate “ACB CONTROL” switch for D/G 1 to open
from the bus.
Cautions
1. Pay attention to the variation in bus frequency during the load division or shift
control, and be sure to maintain it at 60 Hz.
2. Pay attention to the loading condition of the generator(s) remaining on the bus
during the load shift control, and do not overload it for them.
3. If the output of a generator is reduced below 0 KW during the load shift control,
the induction type reverse power relay (RP setting: 10% of the rated output,
time setting: 10 sec) will operate and trip the generator ACB.
Synchroscope Method
1. The synchroscope consists of a small motor with coils on the two poles
connected across two phases. Let’s say it is connected in red and yellow
phases of the incoming machine and armature windings supplied from red
and yellow phases from the switchboard bus bars.
2. The bus bar circuit consists of an inductance and resistance connected in
parallel.
3. The inductor circuit has the delaying current effect by 90 degrees relative to
current in resistance.
4. These dual currents are fed into the synchroscope with the help of slip rings
to the armature windings which produces a rotating magnetic field.
5. The polarity of the poles will change alternatively in north/south direction
with changes in red and yellow phases of the incoming machine.
6. The rotating field will react with the poles by turning the rotor either in
clockwise or anticlockwise direction.
7. If the rotor is moving in clockwise direction this means that the incoming
machine is running faster than the bus bar and slower when running in
anticlockwise direction.
8. Generally, it is preferred to adjust the alternator speed slightly higher, which
will move the pointer on synchroscope is in clockwise direction.
9. The breaker is closed just before the pointer reaches 12 o clock position, at
which the incoming machine is in phase with the bus bar.
1. The two lamps will be bright and one lamp will be dark when incoming
machine is coming in phase with the bus bar.
2. The movement of these bright and dark lamps indicates whether the incoming
machine is running faster or slower.
3. For e.g. there is a moment when lamp A will be dark and lamp B & C will be
bright, similarly there will be instance when B is dark and others are bright
and C is dark and other two are bright. This example indicates that machine is
running fast and the movement of the lamps from dark and bright gives an
clockwise movement
4. Clockwise movement indicates fast and anti clockwise direction indicates
slow running of incoming generator.
18. How do you check press and temp alarms. What equipment used for same
20. If on starting Generator you find that voltage is not building up what you
do?
Residual magnetism is lost. So supply power from outside by connecting battery.
26. What is meaning of power factor. What is best value. What is normal
value onboard. How do you improve?
Power Factor :- The power factor of an AC electric power system is defined as the
ratio of the real power flowing to the load to the apparent power and is a
dimensionless number between 0 and 1
The best value is 0.85. The normal value onboard varies in between 0.8 to 0.9.
Power factor can be improved by connecting a Capacitor in parallel.
35. What precautions to take while using megger ion circuits containing
Electronic components.
45 Why load picked by crane does not fall if power goes off
Because Electro-magnetic brakes get operated.
47.Maintenance on Alternator?
a. Ventilation passages & air filters to clean.
b. Insulation resistance to check for Stator, rotor winding. If low, then varnish to be
done
c. Air gap to check using plastic feeler gauge.
d. Bearing oil to be renewed.
e. Use vaccum cleaner to remove dirt/ dust.
f. Terminal box cover gasket integrity to check.
g. Terminal connections to check for tightness.
h. AVR components, diodes to keep free from oil, moisture or any dirt.
i. Heaters to be checked.
48. How to carry out Open Circuit & Short circuit test?
Open Circuit Test: The purpose of this test is to determine no load loss or core loss.
One winding of the transformer, usually high voltage side if left open and the other
is connected to its supply of normal voltage and frequency. A wattmeter, voltmeter
and the ammeter are connected in the low voltage winding.
With the normal voltage applied to the low voltage side, normal flux will be set up
in the core, hence normal iron losses will occur which are recorded by the
Wattmeter.
The load current on the low voltage winding will be small(2 to 5 % of rated full
load current ), the copper loss in the winding will be negligible and will be nil in
the high voltage side winding..
So, the wattmeter reading will represent practically the core loss under no load
condition.
Short-Circuit Test: This is also known as Impedance test.
In this test, the low voltage winding is short circuited by using a thick conductor
(or Ammeter, which serves additional purpose of Indicating Rated load current).
A low voltage at correct frequency is applied to the primary and is cautiously
increased till full load current is flowing the high voltage side.
In this test, the applied voltage is small percentage of its rated value, hence flux
produced is small with the result that iron losses will be negligible and the
Wattmeter reading will represent the full load Cu-loss.
49. Suppose your motor has short-circuited, then how much value will you get
on Megger.
53. How is the load decided on AC Compressor & how does it works?
54. What is Open-circuit & short-circuit in a control unit ?
58. what is the routine maintenance on the starter of main air compressor
which is of automatic start stop type?
69. What all testing equipment is used for testing an electric motor?
79. There are following reasons for using double tube light fitting.
1. Saving in number of fittings for a given illumination.
2. Two tubes emit light at small distance from each other, so shadows get blurred
and light is more uniform.
3. Often double tube light fixture is provided with a capacitor in series with one
tube, and its choke is different from the other. This phase difference in the two
tubes creates a time difference in light flicker from the two tubes. Since peaks
and valleys of flicker from two sources differ in time, you get flicker free
uniform light.
A p-n junction
It is an interface or a boundary between two semiconductor material types, namely
the p-type and the n-type, inside a semiconductor. The p-side or the positive side of
the semiconductor has an excess of holes and the n-side or the negative side has an
excess of electrons.
A voltage doubler
It is an electronic circuit which charges capacitors from the input voltage and
switches these charges in such a way that, in the ideal case, exactly twice
the voltage is produced at the output as at its input.
Ni-Cd Battery
The cell is the basic unit of the NiCad battery. It consists of positive and negative
plates, separators, electrolyte, cell vent, and cell container. The positive plates are
made from a porous plaque on which nickel-hydroxide has been deposited. The
negative plates are made from similar plaques on which cadmium-hydroxide is
deposited.
The electrolyte used in the NiCad battery is a 30 percent solution of potassium
hydroxide (KOH) in distilled water.
The hydroxyl ions go to cathode and potassium ions go to the anode. The
following chemical reaction takes place during discharging.
Thus, the anode is converted from Ni(OH)4 to NI(OH)2 and cathode is converted
from cadmium (Cd) to cadmium hydroxide [Cd(OH)2]. The strength of the
electrolyte remains the same.
Charging: When the battery is put on charging, the hydroxyl (OH-) ions move
towards the anode, whereas the potassium ions (K+) move towards the cathode.
The following chemical reaction takes place during the charging:
Thus anode and cathode regain their previous chemical composition without
changing the strength of electrolyte.
The potassium hydroxide in NiCad batteries is an alkali solution that
is dangerous and highly corrosive to skin. This fluid can be released in the event of
damage to the battery. If it comes in contact with the skin, it can cause burns.
Contact with the eyes can result in permanent eye damage.
Blackout Testing
Obtain permission Port clearance
Deactivation of critical equipment
Generate RA.
Before a Blackout
Emergency generator should be tested and has to be kept in auto mode.
All the flashlights are recharge or with new battery and ready to use.
Inform the master in Bridge and cargo control room (must give a public
announcement).
Steering gear system manual and stop the pumps.
Ensure that the UPS is working correctly.
Shutdown and switch off the cargo monitoring system .
One of the standby aux engines is to be changed over to the pre-lubrication
priming pump supply is given from the emergency generator.
Aux boilers Main steam valve shut and stop the boiler, power supply off (local
panel and remote PC)
Stop all purifies and power supply off.
Change over all the pumps from auto to manual.
power supply off Unnecessary pumps and AC and the Reefer plant.
incinerator and Inert gas system switch off – main and local panel
Ensure main and emergency air bottles are free from water and full
All the expansion tanks level in normal
Ensure proper operation of emergency air compressor
All the compressors are to be changed to manual and should be switched off
If any equipment operates with PLC, it needs to be switch oft (Diesel engine power
packs)
Stand by generators are to be in manual mode
Reduce the running generator load to minimum
Manually disconnect ACB from main Bus bar on running generator
Check emergency generator auto-start and takes load withing 45 sec
Stop the running generator engine
After Blackout recovery (consider ship’s specific)
Start one of the standby generater in engine side, if not started automatically (Rem:
If revs are not enough open all Do valves to supply AE from DO service Tank by
gravity)
Alternator ACB Connect it to the main bus bar
Check sequential start pumas if not start manually and monitor all the pumps are in
operation
Start the aux boiler and purifiers, check function and ensure all in good order
Restart all other essential equipment and ensure all in good order
Switch on all PCs and the communication system
Power supply on the cargo monitoring system, check the function and ensure
whether all in good order.
Ensure not any alarms are activated in the alarm monitoring system
Stop and keep the Emergency generator in auto mode.
Switch on the inert gas system and incinerator and ensure the proper function of
the PLO-operation function
Ensure all the equipment and machineries are in good order