Professional Documents
Culture Documents
KUALA LUMPUR
NOTES:
1. Contractor to verify existing building survey and structure prior to start of work. SSL stated in design drawings
are based on assumption of spot levels. Contractor to highlight to the Architect or related consultants any
discrepancies found on site.
2. Contractor to demolish all existing walls, dry walls, glass walls, columns and slabs as marked in the drawing.
3. Contractor to demolish & remove floor screed, floor finishes, wall finishes and doors including frames, as
marked in the drawing to expose structural slab / soffit /surfaces.
4. Contractor to demolish & remove all existing sanitary wares and fittings, and pipings connection. Method of
statement to be submitted for consultant’s approval prior to start of work.
5. Contractor to remove all existing ceilings to expose soffit.
6. Contractor to demolish all facade, windows, curtain wall items and to ensure openings are protected from
weather during construction. Method of statement to be submitted for consultant’s approval prior to start of
work.
7. Contractor to remove all existing M&E items including its supports, accessories and sundries except items
related to construction site fire safety. Contractor is responsible for fire and safety during construction.
8. Contractor to inspect the existing skin wall and overall building condition for moisture presence/leaking and to
rectify if found any.
9. Contractor to make good all remaining existing walls and structures to receive new finishes.
10. Contractor to re-cast new floor slab as demarcated in the drawings.
11. Contractor to ensure building is protected from rainwater penetration during demolition and construction works
i.e rainwater to be discharged properly and all external openings to be properly sealed and protected from the
weather.
FFL +131.80
Project Title
4400
FFL +120.01
Owner & Developer
L20
THR HOTEL (KL) SDN BHD
3190
L19
3210
Architect
GDP ARCHITECTS SDN BHD
FFL +113.61 45 - 21, Plaza Level Block C
45 Medan Setia 1, Bukit Damansara
50490 Kuala Lumpur, Malaysia
L18
3200
T+603.2093.5700 F+603.2093.5711
www.GDParchitects.com Reg. No. 232661-A
Civil & Structural Engineer
RAMBOLL ENGINEERING (M) SDN BHD
(Formerly known as Web Structures (M) Sdn Bhd)
Plaza 138, #21-01/02/03/04
138 Jalan Ampang
50450 Kuala Lumpur, Malaysia
3210
T+603.2161.0907
L7 Li - Zainal
3190
L6
3200
L5
ALUM. GUTTER ALUM. GUTTER ALUM. GUTTER ALUM. GUTTER
3210
RWO RWO RWO RWO RWO RWO RWO RWO Interior Designer
FFL +68.82 Ft Ft Ft Ft Ft Ft Ft Ft LW DESIGN GROUP LLC
P.O. Box 74656
Design House,
L4
ALUM. GUTTER ALUM. GUTTER ALUM. GUTTER ALUM. GUTTER
Media Free Zone, Dubai-U.A.E.
3190
L3
ALUM. GUTTER ALUM. GUTTER ALUM. GUTTER ALUM. GUTTER ALUM. GUTTER ALUM. GUTTER
BFG
BFG CONSULTING SDN BHD
3130
(SPECIALTY RESTAURANT 2 (SPECIALTY RESTAURANT 2 (HOLDING BAR AREA (HOLDING BAR AREA ALUM. GUTTER (DROP OFF (DROP OFF (DROP OFF (DROP OFF (RECEPTION AREA (RECEPTION AREA
ROOF) ROOF) ROOF) ROOF) OUTDOOR OUTDOOR ASIAN SPECIALTY ASIAN SPECIALTY ASIAN SPECIALTY OUTDOOR OUTDOOR
TERRACE 2 TERRACE 4 (ST-9 ROOF) ROOF) ROOF) RESTAURANT RESTAURANT RESTAURANT ROOF) ROOF) ROOF) ROOF) TERRACE 3 TERRACE 1 11-03, Q Sentral 2A,
RWO RWO RWO RWO RWO RWO RWO RWO (LANDSCAPE) (LANDSCAPE) RWO RWO RWO RWO RWO RWO (LANDSCAPE) (LANDSCAPE) (LANDSCAPE) RWO RWO RWO RWO RWO RWO RWO RWO (LANDSCAPE) (LANDSCAPE) Jalan Sentral 2, Kuala Lumpur Sentral
FFL +62.500 Ft Ft Ft Ft Ft Ft Ft Ft Dft Dft Ft Ft Ft Ft Ft Ft Dft Dft Dft Dft Dft Dft Ft Ft Ft Ft Ft Ft Ft Ft Dft Dft Dft Dft Dft Dft -Build For Generations- 50470 Kuala Lumpur Malaysia
BFG Consulting Sdn Bhd
T+603.2732.93888
Landscape Architect
6040
L2 10110 Thailand
T+66.81.733.5018
FFL +56.46
Landscape Architect (Local)
T+603.5511.7131
L1
Kitchen & BOH Consultant
AV & Acoustics
G Lighting Consultant
T+65.8869.9267
FFL +38.00
B1a Drawing Title
RAINWATER DOWNPIPE
FFL +36.49
4120
FFL +33.88
B3 FFL +33.47
1910
FFL +31.97
B3a
2980
B4 FFL +30.49
2970
Note
All dimensions on this drawing shall be checked on site before work commences.
FFL +29.00
B4a
Figured dimensions shall be taken in preference to scale dimensions.
2940
FFL +27.55
NOTES:
*All pipes are UPVC pipes with acoustic insulation
CONSTRUCTION DRAWING
Scale 1 : 150 Date 9-Oct-23