Da… / M… / CONS0009-5243_00343 / Week 8 LOB / Online Quiz 3 - LOB (5%)


QUIZ

Started on Thursday, 4 April 2024, 11:43 PM


State Finished
Completed on Friday, 5 April 2024, 12:12 AM
Time taken 28 mins 57 secs
Marks 7.0/10.0
Grade 3.5 out of 5.0 (70%)

Question 1
1 By which day Activity C will be ]nished?
Incorrect
Prepare a LOB schedule for the construction of 40 typical <oors of a high-rise commercial building. A
Mark 0.0 out of 1.0
precedence schedule showing the sequence of a typical aoor construction is given in the below
Figure. Each activity will be performed by one crew of subcontractors. Durations are in days. Add time
buffer zone of zero between activities.

C,6

A,4 3,4

Select one:

a. 164

b. 248 •D,3
c. 167

d. 334 

Question 2
2 By which day Activity E will be ]nished?
Incorrect
Prepare a LOB schedule for the construction of 40 typical <oors of a high-rise commercial building. A
Mark 0.0 out of 1.0
precedence schedule showing the sequence of a typical aoor construction is given in the below
Figure. Each activity will be performed by one crew of subcontractors. Durations are in days. Add time
buffer zone of zero between activities.
Select one:

a. 164

b. 167

c. 334

d. 338 

Question 3
3 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 35 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.

When Should Activity E Start?

Select one:

a. 79 

b. 11

c. 216

d. 175

e. 80

Question 4
4 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 35 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.

When Should Activity B Start?


When Should Activity B Start?

4
4

D
Select one:
2 6
a. 6

b. 72 

c. 140

d. 142

e. 4

Question 5
5 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 35 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.

When Activity E Can Complete?

Select one:

a. 254 

b. 175

c. 219

d. 84

e. 16

Question 6
6 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 30 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.

When Should Activity D Start?


When Should Activity D Start?

Select one:

a. 35 

b. 182

c. 90

d. 6

e. 185

Question 7
7 The following precedence diagram shows all the activities involved in the construction of one aoor of
Incorrect a high-rise building. The duration of each activity is also given (in days). There are 30 typical aoors to
Mark 0.0 out of 1.0 be constructed for this high-rise building.

When Activity C can complete?

Select one:

a. 180

b. 182

c. 8

d. 124 

e. 128

Question 8
8 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 18 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.

What is the Total Project Duration?

D E F
4
m 4 5 2
U
Select one: B
5
a. 182

b. 155

c. 146

d. 145

e. 121 

Question 9
9 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 18 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.

When Should Activity F Start?

Select one:

a. 85 

b. 119

c. 121

d. 91

e. 178

Question 10
10 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 18 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.

When Should Activity B Start?

Select one:

a. 8

b. 54

c. 3 
c. 3 

d. 59

e. 57