Question 1
1 By which day Activity C will be ]nished?
Incorrect
Prepare a LOB schedule for the construction of 40 typical <oors of a high-rise commercial building. A
Mark 0.0 out of 1.0
precedence schedule showing the sequence of a typical aoor construction is given in the below
Figure. Each activity will be performed by one crew of subcontractors. Durations are in days. Add time
buffer zone of zero between activities.
C,6
A,4 3,4
Select one:
a. 164
b. 248 •D,3
c. 167
d. 334
Question 2
2 By which day Activity E will be ]nished?
Incorrect
Prepare a LOB schedule for the construction of 40 typical <oors of a high-rise commercial building. A
Mark 0.0 out of 1.0
precedence schedule showing the sequence of a typical aoor construction is given in the below
Figure. Each activity will be performed by one crew of subcontractors. Durations are in days. Add time
buffer zone of zero between activities.
Select one:
a. 164
b. 167
c. 334
d. 338
Question 3
3 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 35 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.
Select one:
a. 79
b. 11
c. 216
d. 175
e. 80
Question 4
4 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 35 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.
4
4
D
Select one:
2 6
a. 6
b. 72
c. 140
d. 142
e. 4
Question 5
5 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 35 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.
Select one:
a. 254
b. 175
c. 219
d. 84
e. 16
Question 6
6 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 30 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.
Select one:
a. 35
b. 182
c. 90
d. 6
e. 185
Question 7
7 The following precedence diagram shows all the activities involved in the construction of one aoor of
Incorrect a high-rise building. The duration of each activity is also given (in days). There are 30 typical aoors to
Mark 0.0 out of 1.0 be constructed for this high-rise building.
Select one:
a. 180
b. 182
c. 8
d. 124
e. 128
Question 8
8 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 18 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.
D E F
4
m 4 5 2
U
Select one: B
5
a. 182
b. 155
c. 146
d. 145
e. 121
Question 9
9 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 18 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.
Select one:
a. 85
b. 119
c. 121
d. 91
e. 178
Question 10
10 The following precedence diagram shows all the activities involved in the construction of one aoor of
Correct a high-rise building. The duration of each activity is also given (in days). There are 18 typical aoors to
Mark 1.0 out of 1.0 be constructed for this high-rise building.
Select one:
a. 8
b. 54
c. 3
c. 3
d. 59
e. 57