LIKELIHOOD OF
OCCURRENCE(1-
ID RISK DESCRIPTION 10) IMPACT (1-10) SEVERITY(%) OWNER MITIGATING ACTION CONTINGENT ACTION
Project manager/Quantity
2 Price flactuations 9 10 90 Surveyor Bulk procurement of resources Contingency reserves
3 Delay in construction period 1 10 10 Project manager Closely monitor programme of works Crash programming, Work overtime
Complete all drawings before project Complete drawings necessary for work
4 Incomplete drawings 0 90 0 Architect begins packages to begin
16 Land and air pollution 7 3 21 Health and Safety Officer Use sustainable construction methods. Proper disposal of waste and dust management
17 Noise 8 3 24 Health and safety officer Temporary shields and noise barriers -
18 Fire outbreaks 1 10 10 Health and safety officer Ensure fire protective conditions Use emergency fire outbreak practices
20 Disputes 4 8 32 Quantity Surveyor Proper drafting of contract Alternative dispute resolutions mechanisms