Internship Report

REPOR

T ON

INDUSTRIAL TRAINING
By
GANJAVE SHUBHAM DATTU
TECE-12

Duration: 03/12/2023 to 03/01/2024

Guided by: Mr. Sahil Gamne (Owner)

: Miss Palavi Mam.(TG)

DEPARTMENT OF CIVIL ENGINEERING


GURU GOBIND SINGH COLLEGE OF
ENGINEERING
& RESEARCH CENTER,
NASHIK [2022-23]
GURU GOBIND SINGH COLLEGE OF
ENGINEERING & RESEARCH
CENTER,NASHIK

Pg. 1 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

GURU GOBIND SINGH FOUNDATION’S


GURU GOBIND SINGH COLLEGE OF ENGINEERING &
RESEARCH CENTRE, NASHIK-422009.
SAVITRIBAI PHULE PUNE UNIVERSITY, PUNE

CERTIFICATE

This is to certify that the GANJAVE SHUBHAM DATTU have satisfactorily carried out sixth
semester T.E. Internship Training entitled “Industrial Training".
This work is been submitted in partial fulfilment of the requirement for third year civil engineering.
It is submitted in the partial fulfilment of the prescribed syllabus of third year civil engineering of
Savitribai Phule Pune university, Pune for the academic year 2022-2023.

MissPalavi mam. Mr.P.B.Shinde Sir.

(Internship Guide) (Internship Co-ordinator)

Mr.VM.Natraj. Mr.N.G.Nikam

(H.O.D) ( Principal)

Pg. 2 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

AKNOWLEDGEMENT
I would like to thank Mr. Sahil Gamne (Owner), my guide for the internship report, for
providing me site knowledge and also giving me practical knowledge on the site during
internship training. His valuable guidance gives me practical knowledge of the site. His time
to time guidance about the site boosted us to complete this task successfully, and your
guidance is very helpful and important as a future expansion and it is also help to improve
knowledge.

At last I must express my sincere heartfelt gratitude to all the staff members of Civil
Engineering Department who giving me the opportunity to do the internship on site. With
deep sense of gratitude we are also thankful to Guru Gobind Singh Foundation, Nashik for
providing all necessary facilities, constant encouragement and support.

Pg. 3 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

ABSTRACT
The internship report in broad-spectrum contains seven chapters in which we try to explain
my twenty days experience on construction site. The content of all chapters is broadly
explained and it is constructed from the practical basis of the site work.

The first chapter is about the background of the company.

The chapter second gives the introduction about the construction site. In this chapter we put
general detailing of the construction site, with its official address. So, it is give generaldetails of
the construction site in terms of reader can easily know the general information about the site
and access the construction site.

Chapter three gives the objectives of internship training. In this explained the objectives
learned by this training.

Chapter four gives the information about work observed during training. In this explained the
information about the work done during training period.

Chapter five gives the brief conclusion about the

training. Chapter six gives the suggetions to the

company.

Chapter seven gives the list of the refereces.

Pg. 4 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

CONTENT

Chapter Topic Page


No. No.
1 BACKGROUND OF 7
COMPANY
2 INTRODUCTION
8

3 OBJECTIVES 10

WORK
4 11
OBSERVED
DURING

5 CONCLUSION 22

6 SUGGETIONS 23

7 REFERENCES 24

Pg. 5 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

LIST OF PHOTOGRAPHS

PHOTOGRAPH No. PHOTOGRAPH Name Page No.


FRONT VIEW OF
2.1 9
APPRTMENT
STORAGE OF
4.1 11
MATERIAL
COLUMN
4.1.1 12
FORMWORK FOR SLAB
4.3.2 13
4.4.1 FORMWORK FOR 14
COLUMN
4.5.1 FORMWORK FOR BEAM 14
REINFORCEMENT
4.6.1 15
FOR
STAIRCASE
4.6.2 REINFORCEMENT FOR 16
BEAM
4.6.3 REINFORCEMENT FOR 17
SLAB
4.6.4 JUNCTION OF 18
REINFORCEMENT OF
BEAM ,COLUMN
AND
SLAB
PLACING OF CONCRETE
4.7.1 18
PLACING OF
4.7.2 20
CONCRETE

4.7.3 COMPACTION OF 21
CONCRETE
PHOTOGRAPS OF TG
VISIT 22

Pg. 6 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

Chapter No:01

About The Company

S.k Builder And Developer- is established in 2021 by the Mr.SahilGamne.


It is the leading construction company which have the more than 2active
projects.This company providing best services to the costumers. The company in the
area of construction of Appartments,Bunglow,Row houses etc.
This company converting land into dream appartments.The office is located in
Morwadi Gaon Nashik.
Companies running projects are-
1)G+6Appartment in Nagare mala
Near Samrat Symphony Building ,
Nashik
2)G+5 Apprtment in indira nagar(ready to open).

Pg. 7 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

Chapter No. 2
INTRODUCTION
 The company name S.k Builder And Developer. It is private construction company.
 Address of site:Plot No 82 And 83 Nagare mala Near Samrat Symphony Building ,
Nashik
 The site is residential (G+6) Appartment.
 This site has builtup Area of 1500 sqft.
 The margins leave on front and right side is as 1.5 m and the margins leave on
left and back side is as 1.50 m.
 The stepped footing is provided on this site. The main purpose of using stepped
footing is to keep the metal columns away from direct contact with soil to save
them from corrosive effects.
 The estimated cost of construction is Appx. 1.5 cr and the estimated time to get
the site ready is around approximately 6 months.
 The cement used for construction is of M25 grade of Ultratech cement.
 On this site the concrete is prepared by small Mixure.
 Approximately 20-22 brass sand is to be used for the construction of this site.
 Approximately 35-40 brass aggregate are to beused for the construction of this site.
 The bricks used during construction are of 2nd class brick.
 Fe 415 grade of Rajuri steel is used. Diameter of 8,10,12,16 mm steel is used for
different work. For slab diameter of 10mm steel bar used as a main steel and
diameter of 8mm steel bar used as a distribution steel.
 Sizes of bricks used: 6” and 4”
 The name of this site is “Maulidhan”.
 The name of the owner of this property: Mr. Sahil Gamne
 The construction is done by S.k Builder And Developer.

Pg. 8 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

Photograph 2.1: Side View of Building.

Pg. 9 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

Chapter No. 3

OBJECTIVES
 To study the various components used for the construction of building and during the
development of building.
 To study the various functions of different components like foundation, column,
beam, tie beam, plinth etc.
 To get an understanding how the theoretical knowledge is fitted in practice.
 To observe the different activities techniques carried out on site.
 To have a feel of how condition of site really is and hoe safety is priority.
 Observe the usages of machinery at construction site.

Pg. 10 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

Chapter No. 4

WORK OBSERVED DURING TRAINING


1. Quality of Material.

Photograph 4.1: Quality of Material

Pg. 11 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

2. Various Elements of Structure

I. Column
Column is the vertical structural member which transfer the load to the foundation.

The Size of the column is 400mm*600mm in corner column.

And Intermidiate column of size 300mm*600mm.

3. Removal of formwork.

I. On the site safety is the first priority.

II. Formwork is to be removed in such a way that it does not cause


any injury and minimum material damage.

Pg. 12 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

4. Formwork for Column,Beam and Slab.

I. Formwork is setted to achieve the desired shape and size of the


any element.

II. The internal dimensions of the formwork should match the size
of that element.

Photo 4.4.1: Formwork for Slab

Pg. 13 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

Photo 4.4.2: Formwork for Column

Photo 4.4.3: Formwork for Beam

Pg. 14 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

5. Reinforcement for Beam and Slab.

I. Reinforcement for Beam

a. 12mm bars are used as main steel and 10mm is used for stirrups
with spacing of 125mm at the Right and left support and 230mm at
midspan of the beam.

b. 40mm clear cover is used on reinforcement.

c. Two legged stirrups are used.

Photo 4.6.1: Reinforcement for Beam

Pg. 15 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

II. Reinforcement for Slab

1) 10mm dia bars are used as main steel and 8mm dia bars are
used as distribution steel.

2) For binding steel wire is used.

3) Minimum lap length of bar is 50d.

4) 20mm nominal cover is used for slab.

5) Miximum diameter of bar should not be exeed the D/8.whre D


is the depth of slab.

6) Alternate bentup bars are used.

7) Angle of bentup bar is 0.42d.where the d is depth of slab.

Photo 4.6.2.1:Reinforcement for Slab

Pg. 16 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

Photo 4.6.2.2: Junction of Column,Beam and Slab Reinforcement

Pg. 17 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

6.Concreting:-

Concreting mixing is done by the volume batching.M25 grade of concrete


is used for the concreting.

Compaction of concrete is done by manually as well as the needle vibrator.

Photo4.7.1: Placing of Concrete

Pg. 18 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

Photo 4.7.3: placing of Concrete

Photo4.7.3: Compaction of Concrete

7.Curing :
Pg. 19 Guru Gobind Singh College of Engineering and Research Centre,
Nashik
J
Internship Report

Curing is the process carried out for the to counter the hydration process to
minimize the development of cracks.

On the site curing is done by the water spradiying method.

Pg. 20 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

Chapter No. 5
CONCLUSION
As an undergraduate of the Savitribai Phule Pune University, I would like to say that this
training program is an excellent opportunity for us to get experience the things that we would
have never gained through going straight into job. I am grateful to the Savitribai Phule Pune
University, for giving us this wonderful opportunity of the internship training.

The main objective of the internship is to provide an opportunity to undergraduates to


identify, observe how to construction done on actual site. It is very beneficial to get the
practical knowledge about the construction site. It is not only to get experience on technical
practices but also to observe management practices and to interact with filed workers, site
engineer and get the practical knowledge form that. This internship training is very useful and
also we learned some new things from this internship training.

Pg. 21 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

Chapter No:06

SUGGETIONS
1) Use of the concrete cover over the Granite stones while reinforcement.
2) Use wet gunny bags for curing over the water sprading method.

Pg. 22 Guru Gobind Singh College of Engineering and Research Centre,


Nashik
J
Internship Report

Chapter No:07

References
1) www.youtube.com
2) www.google.com
3) www.wikipidia.com
4) IS 800-CODE OF PRACTICE-GENERAL CONSTRUCTION
IN STEEL.
5) IS 456-CODE OF PRACTICE-PLAIN AND
REINFORCED CONCRETE

Pg. 23 Guru Gobind Singh College of Engineering and Research Centre,


Nashik